A.I. Smith Electrical Contractors, Inc. v. City of New York (MJ-346)A.I. Smith Electrical Contractors, Inc. v. City of New York (MJ-346)
Order, Supreme Court, New York County (Leland DeGrasse, J.), entered on or about April 7,1993, which, inter alia, denied plaintiff’s motion for summary judgment seeking damages of $408,176.82 on its fifth cause of action and granted defendant’s cross-motion to amend its answer to add a second counterclaim, unanimously affirmed, without costs.
Plaintiff, an electrical contractor, was the successful bidder on two identical contracts with the City of New York for the maintenance and repair of public street lights in two of the eight geographical contract areas of the City for the period from October 1, 1985 through September 30, 1988. During the course of the contracts, plaintiff received payments of approximately $9,000,000.
The within action was brought by plaintiff in February, 1989 seeking damages totalling over $15,000,000 for breach of contract and extra work monies in connection with these contracts. In the fifth cause of action, the only one at issue here, plaintiff sought a sum in excess of $400,000 as the balance due. (Although it appears that the fifth cause of action as delineated in the amended complaint refers to only one of the contracts, the parties, as well as the motion court, have proceeded on the assumption that this claim seeks the balance due under both contracts and we will also proceed on that assumption.)
While, according to the complaint, this amount had been duly demanded by plaintiff and was due and owing at the time the complaint was filed, it is apparent that not all the paperwork required for payment had been completed at that point, since it was only during pendency of this action that final payment requisitions were submitted by plaintiff and the amounts requisitioned, less $10,000 in liquidated damages for failure to file monthly inventory reports, were certified as due plaintiff by the City’s Department of Transportation in June, 1991. The total amount certified as due under both contracts was $408,176.82.
In March, 1992, the City informed plaintiff that it was refusing to pay this sum on the ground that the Comptroller’s own review of the claim revealed that liquidated damages for breaches by plaintiff which had occurred over the duration of the contract were still due from plaintiff in excess of the
The IAS Court denied plaintiff’s motion for summary judgment and granted the City permission to assert its second counterclaim.
In light of plaintiff’s own failure to submit to the City the necessary paperwork requisitioning the payments sought under the contract until 1991, two years after commencement of this action, and plaintiff’s failure to allege anything other than conclusory claims of prejudice based on the City’s delay until 1992 in asserting its second counterclaim, we find that the IAS Court properly granted the City’s motion to amend.
Moreover, we find that the IAS Court properly denied plaintiff’s motion for summary judgment. It is clear, contrary to plaintiff’s argument, that, under the contract, the Comptroller is not bound by certification of the Department of Transportation of amounts due under the contract if subsequent investigation reveals that those certifications were wrongly made. The City has presented evidence demonstrating the existence of material issues of fact on its claim that it is entitled to $190,450 in damages under its first counterclaim based on its position that it is still owed liquidated damages for plaintiff’s alleged failure to submit written requests for extensions of time for delayed repairs. Moreover, the City has also presented evidence sufficient to withstand summary judgment in support of its second counterclaim, based on its claim
We have examined plaintiffs remaining contentions and find that they are without merit. Concur—Rosenberger, J. P., Ellerin, Nardelli and Tom, JJ.