48 Misc. 2d 279 | N.Y. Sup. Ct. | 1965
This is a motion and special proceeding in mandamus for an order directing the respondent Superintendent of Public Works of the State of New York to forthwith cause to be approved, or to approve and certify to the Comptroller of the State of New York for audit and payment, in
The Attorney-G-eneral submitted an answer by manner of notice of motion and moves for an order dismissing the petition on the grounds that:
1. Petition fails to set forth a right to any relief.
2. There is another action pending between the parties for the relief sought herein, and for such other further relief as the court may deem just and proper.
The court after a review of the record determines that the motion of the respondent for dismissal of the petition is denied. The petition prays for mandamus to compel the Superintendent of Public Works to perform a duty pursuant to statute and to compel the Comptroller of the State of New York to perform a duty likewise compelled by statute.
Apparently the respondent has made objections in point of law as set forth in the motion to dismiss. The respondent raised objections in point of law by setting it forth in its notice of motion and supporting affidavits. This motion is denied and the court permits the respondent to answer the petition within 30 days after notice and entry of order on this decision.
:This court has made an intermediate order for discovery of certain records of the Department of Public Works on a collateral motion for discovery made by the petitioner. This interim order does not affect the instant decision of this court, in that the issues as to whether or not mandamus shall issue shall be determined when the petition and answer and other evidence are before the court for its examination.
The court in making this determination places much significance on that part of an order of the Court of Claims dated October 11,1963, which reads as follows:
“ Ordered, that the issues with respect to the amounts due and owing to the claimant as and for the final payment for the
In effect that court recognized the duty of the Comptroller of the State of New York to act either affirmatively or negatively in respect to the claim of the petitioner, such action having not been performed and the petitioner alleging in the petition that the Superintendent of Public Works must first act upon the claim and certify the claim for payment to the Comptroller, and the Superintendent of Public Works having-failed to act since October 11, 1963 and it is conceivable that such failure to act is justified by the facts and circumstances, however, the Court of Claims order is a condition precedent required before any further action can be entertained by the court.
The Court of Claims having no jurisdiction to issue an order of mandamus to compel the performance of a duty by mandamus of a public body or officer and particularly constituted officers of the State of New York leaves the petitioner no avenue of approach to litigation except in this court.
The petitioner seeks an order of mandamus requiring- the Superintendent of Public Works to approve a final estimate and final payment of money allegedly due it under the contract which is the subject of petitioner’s claim in the Court of Claims. The Attorney-G-eneral in his brief urges that the Superintendent of Public Works is presently trying to ascertain the exact amount which the State concedes to be due. And he further states, ‘1 whether or not the Superintendent of Public Works ultimately determines that any money is due petitioner from the State, petitioner will have an opportunity, when its claim is reached for trial, to prove any damages it has sustained by reason of the State’s alleged breach of contract. Hence, petitioner clearly has a remedy in the instant situation.” This may all be true but the Superintendent of Public Works has not acted negatively or affirmatively on the certification for payment as to what sums of moneys are due or what sums of money are not due to the petitioner herein. This delay may be reasonable or unreasonable and must be tested by the mandamus proceeding.
It is true that mandamus is a discretionary remedy to enforce a clear legal right, it is not available when other means may be used to enforce the right. (Matter of Kaplan v. Lipkins, 19 A D 2d 723.) It is true that mandamus is an extraordinary
In conclusion this court determines that the motion of the respondent for dismissal of the petition is denied in all respects.