548 S.W.2d 611 | Mo. Ct. App. | 1977
This appeal is from a judgment of the Circuit Court of the Cape Girardeau Court of Common Pleas in favor of A. E. Birk & Sons Plumbing and Heating, Inc., Cape Ready Mix Company, Inc., Riverside West Builders Supply, Inc., and Southern Illinois Stone Company and against Crites and Sail-er Construction Company in connection with the construction of a K-Mart building in Cape Girardeau, Missouri, and the establishment of mechanics’ liens against the property owned by defendant Malan Construction Company. A money judgment was also entered against Crites and Sailer Construction Company in favor of Rose Con, Inc., but Rose Con, Inc. was not awarded a mechanic’s lien against the property. The judgments entered by the trial court, in this court-tried case, were as follows: Riverside West Builders Supply, Inc., $1,365.75; Southern Illinois Stone Company, $26,420.86; A. E. Birk & Sons Plumbing and Heating, Inc., $29,215.59; Cape Ready Mix Company, Inc., $31,704.34 and Rose Con, Inc., $3,399.44. Rose Con, Inc. has not appealed from the judgment denying it a mechanic’s lien and subsequent to the institution of this appeal the mechanic’s lien of Cape Ready Mix Company, Inc. was disposed of by agreement. The judgment against Crites and Sailer Construction Company has not been appealed by that company’s Trustee in Bankruptcy.
The appellants are Malan Construction Company, the owner of the real estate, First National Bank of Minneapolis, Richard Roth, Trustee, the State of California Public Employees Retirement System, S. S. Kresge Company, and the Henry Ross Construction Company, the general contractor on the job. Crites and Sailer Construction Company was a sub-contractor for Ross on this project and the lien claimants were mechanics or materialmen who had worked for or furnished materials to Crites and Sailer Construction Company in connection with the K-Mart project.
At trial it was stipulated by and between the parties that «any recoveries in the case
In order to simplify the trial, the parties also entered into numerous stipulations and agreements leaving for determination by the trial court the following issues with respect to the parties:
A. E. Birk & Sons Plumbing & Heating, Inc.:
(1) was the mechanic’s lien timely filed?
(2) was proper notice of the intent to file mechanic’s lien given as required by law?
Riverside West Builders Supply, Inc.:
(1) was proper notice of intent to file mechanic’s lien given as required by law?
Southern Illinois Stone Company:
(1) did this lien-claimant file a just and true account required by § 429.080 RSMo. 1969, as amended?
(2) was proper notice of intent to file mechanic’s lien given as required by law?
(3) were the charges made reasonable?
One of the stipulations was that the lien-claimants filed mechanic’s lien statements in the office of the Clerk of the Common Pleas Court of Cape Girardeau County on the dates set out:
A. E. Birk & Sons Plumbing & Heating, Inc. — March 15, 1974
Riverside West Builders Supply, Inc. — February 14, 1974
Southern Illinois Stone Company — February 22, 1974
A. E. Birk and Sons Plumbing & Heating, Inc., and the appellants stipulated that the only item of work and materials purported to have been performed on a date which would satisfy the lien filing requirements and render the lien timely filed as of March 15, 1974, was work and materials furnished by the plaintiff on November 16, 1973.
Upon completion of the trial the trial court entered an Order, Judgment and Decree containing extensive findings of fact and conclusions of law in support of its judgment for the parties as previously stated and establishing the mechanics’ liens against the real estate.
On appeal the appellants contend that the judgment of the trial court should be reversed because (1) the property owner, Ma-lan Construction Company, did not receive actual notice of respondents’ intent to file mechanics’ liens, (2) the trial court erred in awarding a decree establishing a mechanic’s lien in favor of Birk (as respondent A. E. Birk & Sons Plumbing & Heating, Inc., shall hereinafter be identified) because the statement of mechanic’s lien was not filed within four months after the account had accrued, and (3) the trial court erred in awarding Southern (as Southern Illinois Stone Company shall hereinafter be identified) a mechanic’s lien for the reason that the tax lien filed by Southern was not a just and true account of the monies due it from Crites and Sailer Construction Company.
Our review of this court-tried case is governed by the principles announced in Murphy v. Carron, 536 S.W.2d 30, 32[1, 3] (Mo. banc 1976) and Rule 73.01 V.A.M.R., and we are required to sustain the judgment of the trial court unless there is no substantial evidence to support the judgment, it is against the weight of the evidence, it erroneously declares the law, or it erroneously applies the law. We are also cautioned by Murphy v. Carrón, supra, to exercise the power to set aside a decree or judgment on the ground that it is “against the weight of the evidence” with caution and with a firm belief that the decree or judgment is wrong. We find none of the aforementioned infirmities in this judgment and we therefore affirm.
Malan Construction Company’s first contention is that it did not receive actual
Whether Birk’s statement of mechanic’s lien was timely filed hinges on whether work performed by Birk on November 16, 1973, in relation to some broken “clean-outs,”
Plaintiff’s evidence on this issue was supported by the testimony of August W. Birk, the President of Birk’s, Elbert Birk, its foreman, interrogatories .of Malan to Birk and Birk’s answers thereto, some of the stipulations, and Plaintiff’s Exhibits 1 and 2, “Work Book” and “Time Sheets,” respectively. The real bone of contention is whether repair of some broken “clean-outs” on November 16, 1973, admittedly some months after what appellants claim was the completion of the contract, was chargeable to Crites’ and Sailer’s account.
The project out of which this litigation arose was the construction of a K-Mart building on property owned by Malan. Ross Construction Company was the general contractor on the project and Crites (as Crites and Sailer Construction Company shall hereinafter be identified) was a subcontractor to Ross (as Ross Construction Company shall hereinafter be identified). Birk, a general plumbing, heating and ventilating contractor, had, prior to this project, performed several jobs for Crites. Loy Crites, of Crites, phoned August Birk, Birk’s president, during the summer of 1973 and told Birk that Crites had the K-Mart job and inquired whether Birk was interested in doing the piping work. Birk replied that the company would. Loy Crites told him that the sewer pipe had already been ordered and that Birk was to order anything else necessary for the job and to back-charge Crites for it. This agreement was not reduced to writing. It was agreed, however, that it would be a “cost-plus” contract. Birk would receive its “going hourly rate” for labor plus a reasonable price for cost of materials it furnished. Both firms had previously done business and this type of contract was not unusual in their prior dealings. Crites knew Birk’s “hourly-rate” and also that Birk would treat Crites fairly on the costs of materials going into the job.
Birk entered upon performance of the agreement, installing the storm and sanitary sewers at the site, and Crites also asked it to install the water mains. Excavations were made, the necessary pipework laid, and the excavations then back-filled. When the work was done Birk also obtained several other contracts on the project, including some with Ross and some with Ma-lan, although none of these were in connec
The trial court resolved this issue in favor of Birk, and we conclude that its holding should not be disturbed. The trial court found that Birk had established a running account with Grites which commenced on July 31,1973, through November 16, 1973; that the repairs to the “clean-outs” were not, as Grites contended, pursuant to a separate contract. A “running account” is a mutual account between a buyer and seller to which charges and credits accrue or are entered as materials are sold or paid for. J. R. Meade Co. v. Forward Construction Company, 526 S.W.2d 21, 32[27, 28] (Mo.App.1975). A running account is deemed an entire contract, and, for the purpose of fixing the time for the filing of the statement of the account to perfect a mechanic’s lien, each item of the account relates to the last item of labor performed and materials delivered. In the absence of any evidence to show a separate and distinct contract as to this last item, the account will be taken and considered as it appears to be, i.e. a running account arising under and by virtue of the contract out of which the contract originally grew. The mere lapse of time between the delivery of the items or the performance of the labor incorporated as items in a contract on a running account is insufficient to commence the running of the periods of limitation barring the lien, nor is it significant that the last item of work may be a small item. J. R. Meade Co. v. Forward Construction
We believe, as did the trial court, that perfecting the damaged “clean-outs” constituted a part of the original contract and was essential to make the “clean-outs” completed in a workmanlike manner as required by the terms of the oral contract. In the absence of this work and materials and the replacement of the protruding portions of the “clean-outs” the paving would not have been accomplished in accordance with the plans and specifications and the sewers would have ultimately plugged-up from dirt and gravel. That this work was of an emergency nature is evident from the testimony. In construction of this kind, it is our belief, no subcontract may be said to be completed until the work performed thereunder and the materials installed therein can become integrated into the whole of the completed project, and minor finishing touches such as those involved on November 16,1968, are necessary to achieve that integration into the whole. It cannot be denied that this work was essential for the completion of the project, and was not performed for the mere purpose of preserving a mechanic’s lien, but, rather, was reasonably within the purview of the original contract. General Fire Extinguisher Co. v. Schwartz Bros. Commission Co., 165 Mo. 171, 65 S.W. 818, 323[8] (1901); Badger Lumber Co. v. W. F. Lyons Ice & Power Co., 174 Mo.App. 414, 160 S.W. 49, 52[8] (1913). We rule this point against the appellants.
Appellants’ final contention is that Southern intentionally omitted crediting Grites’ account with substantial payments made and therefore the statement of account filed with Southern’s lien notice was not a just and true account of the monies due it as required by § 429.080 RSMo. 1969. We find that this contention is without merit.
Appellants’ argument in support of this contention revolves around a payment made to Southern by McCarthy Brothers Construction Company in settlement of Southern’s claim against Crites for materials furnished on the construction of the St. Francis Hospital in Cape Girardeau, on which job McCarthy Brothers Construction Company was the general contractor. On May 14, 1974, McCarthy (as that company shall hereinafter be identified) paid to Southern the sum of $7,340.74 in settlement of its lien claim on the St. Francis Hospital project. It was not until May 31, 1974, that this sum was credited to the Crites’ account on the St. Francis Hospital project. It was then ascertained that at that time there was then a balance due on the Crites’ account for the St. Francis Hospital job, after a credit of $815.64 which Southern had agreed with McCarthy to give to the St. Francis Hospital job and a charge to which Crites was entitled for a hauling job for an affiliate company of Southern of $242.50, of only $2,077.45. Thus, Southern had in its possession $6,321.43 more than it was entitled to on the St. Francis Hospital job. Appellants therefore contended in the trial court, and here, that Southern was attempting to “double-charge” Crites this amount and therefore the account as stated at the time the notice of lien was filed was not a just and true account of the monies due.
Respondent Southern takes the position that at the time they filed their notice of lien in this case the statement of account was just and true, and that it was not a prerequisite to a valid lien that the payments be allocated between the accounts immediately upon receipt. It also relies on Herrman v. Daffin, 302 S.W.2d 313 (Mo.App.1957) for the proposition that the Missouri law is that undesignated payments may be applied at the choice of the creditor among the debtors accounts and that where the creditor does not make a designation as to how the allocation between the accounts shall be made, then the payment shall be applied to the oldest unsecured account.
The notice of lien was filed on February 22, 1974, by Southern. This lawsuit was instituted on June 4, 1974, and Southern was named defendant herein. On August 1, 1974, it filed its cross-claim seeking a judgment in an amount of $30,679.76
Subsequently, on November 20, 1974, Southern filed “Amended Answers to Interrogatories” amending the Answer previously given to Interrogatory 10 as follows:
“ANSWER: Yes. On May 14, 1974, Southern Illinois Stone received payment of $7,340.74 from McCarthy Brothers to be applied on Crites & Sailer’s account for the St. Francis Hospital job in furtherance of an agreement to give full credit for an additional $815.64 on that job, which credits were given on May 31, 1974. Southern Illinois Stone had previously applied payments made by Crites & Sailer to that St. Francis job account, however, whereby that job account had a balance of only $2,077.45 on its books. In addition, an affiliate company of Southern Illinois Stone owed Crites & Sailer $242.50 for hauling services and on June 8,1974, Southern Illinois Stone gave credit to Crites & Sailer for that amount. At these times, the K-Mart job was the only unpaid account owing by Crites & Sailer to Southern Illinois Stone, and, therefore, Crites & Sailer should have become entitled to a total credit of $6,321.43 on this account. However, due to an accounting oversight and the handling of this account by its attorneys, such credit entitlement has been overlooked by Southern Illinois Stone until this time. Therefore, there remains due and owing on this account the sum of $24,358.33 plus interest.”
It is apparent that the filing of Southern’s notice of lien occurred prior to the receipt of any payment from McCarthy of any monies in settlement of Southern’s claim against Crites on the St. Francis Hospital job. Therefore, at the time the lien notice was filed the evidence does not refute that the statement of account as of that date for the K-Mart job was not a just and true statement of account as required by § 429.080 RSMo. 1969, as found by the trial court. Furthermore, once it was ascertained that there was an excess over and above the payment by McCarthy, credit of some $6,321.43 was given to Crites by Southern, that being the balance left over from the $7,340.74 paid by McCarthy. To this extent at least Crites got all of the credits it was entitled to, and cannot now be heard to complain.
As Southern argues, it is the settled law in Missouri that where one owes several debts to another and makes payment thereon, the creditor has the right to apply the payments, or any part thereof, as seems proper to the creditor, in the absence of any specific arrangement or designation that the payment shall be credited to either one of the several accounts on which there is a balance remaining unpaid. Upon failure of creditor to exercise his choice, the law will apply the credit on the debt which is older or is unsecured. Scott v. Twin City State Bank, 537 S.W.2d 641, 644[4] (Mo.App.1976); Twellman v. Lindell Trust Company, 534 S.W.2d 83, 95[22] (Mo.App.1976); General Plywood Corp. v. S. R. Brunn Const. Co., 511 S.W.2d 905, 908[2] (Mo.App.1974). This Southern chose to do, as was its right.
A lien account is not vitiated by an unintentional failure to enter all of the credits to which the account is entitled, § 429.210 RSMo. 1969, nor will a lien fail due to a good faith inclusion of a charge which later is proved to have been excessive. J. R. Meade Co. v. Forward Construction Company, supra, 526 S.W.2d 32[3]. There is here no evidence that Southern
The judgment is affirmed.
. Malan Construction Company had taken a judgment against Crites and Sailer prior to the time this action was brought to trial. That judgment was in part, at least, based upon the amount of all the liens filed in this case. Crites and Sailer was in bankruptcy at the time of this trial.
. “Clean-outs” were described in evidence as a piece of cast iron pipe running from the trunk sewer line to the surface of the ground providing surface access to the trunk sewer line so that it might be flushed out in case it becomes clogged and plugged up.