215 Conn. 604 | Conn. | 1990
On June 3, 1986, the plaintiff, A. Dubreuil and Sons, Inc., a general contractor, and the defendant, the town of Lisbon, entered into a contract for certain additions and alterations to be made by the plaintiff to the town-owned Lisbon Central School in Lisbon. The plaintiff, claiming that it was entitled to compensation for extra work performed on the project, filed a demand for arbitration with the American Arbitration Association (AAA) on November 7, 1988. The defendant thereafter informed the AAA that the contract did not require the parties to arbitrate the plaintiffs claim and that it did not agree to arbitration. As a result, the AAA notified the parties by letter dated December 16,1988, that it “would hold this file in abeyance until such time as a court orders arbitration.”
In response to the AAA’s letter of December 16, 1988, the plaintiff, by complaint dated January 7,1989, instituted an action in the Superior Court requesting an order compelling the defendant to arbitrate their differences in compliance with what it contended was their agreement requiring arbitration on the demand
The agreement between the parties, as it concerns arbitration, is embodied in §§ 7.9.1, 7.9.2 and 7.9.3 of the standard American Institute of Architects’ (AIA) printed contract document A201. The relevant portion of § 7.9.1 in its original form in the standard printed contract provided: “All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to the Contract Documents or the breach thereof . . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.”
“Arbitration is a creature of contract.” John A. Errichetti Associates v. Boutin, 183 Conn. 481, 488, 439 A.2d 416 (1981); Gangemi v. General Electric Co., 532 F.2d 861, 865 (2d Cir. 1976); Board of Education v. Bridgeport Education Assn., 173 Conn. 287, 290, 377 A.2d 323 (1977). It is designed to avoid litigation and secure prompt settlement of disputes and is favored by the law. John A. Errichetti Associates v. Boutin, supra; Hartford v. American Arbitration Assn., 174 Conn. 472, 480, 391 A.2d 137 (1978); Board of Education v. Bridgeport Education Assn., supra. “ ‘But a person can be compelled to arbitrate a dispute only if, to the extent that, and in the manner which, he has agreed so to do. Visselli v. American Fidelity Co., 155 Conn. 622, 624, 237 A.2d 561 [1967]; Frager v. Pennsylvania General Ins. Co., 155 Conn. 270, 274, 231 A.2d 531 [1967] . . . .’ Marsala v. Valve Corporation of America, 157 Conn. 362, 365, 254 A.2d 469 (1969).” John A. Errichetti Associates s. Boutin, supra. No one can be forced to arbitrate a contract dispute who has not previously agreed to do so. Ginsberg v. Coating Products, Inc., 152 Conn. 592, 596, 210 A.2d 667 (1965). The issue of whether the parties to a contract have agreed to arbitration is controlled by their intention. Hatcho Corporation v. Della Pietra, 195 Conn. 18, 20, 485 A.2d 1285 (1985); First Hartford Realty Corpora
It is therefore a question of fact in this instance whether the parties, in altering the printed contract by substituting “may” for “shall” in the contract’s arbitration provision, intended to modify the contract to provide for consensual arbitration, rather than mandatory arbitration upon the demand of a single party. Three S. Development Co. v. Santore, 193 Conn. 174, 178, 474 A.2d 795 (1984); First Hartford Realty Corporation v. Ellis, supra; see Lavigne v. Lavigne, 3 Conn. App. 423, 427, 488 A.2d 1290 (1985). The trial court’s finding on that issue is not reversible by this court unless it was a finding that the court could not reasonably have made. First Hartford Realty Corporation v. Ellis, supra; Heyman v. CBS, Inc., 178 Conn. 215, 227-28, 423 A.2d 887 (1979); Lar-Rob Bus Corporation v. Fairfield, supra. The plaintiff can prevail on appeal, therefore, only if it is able to demonstrate that the trial court’s interpretation of the amended contract was clearly erroneous. Ginsu Products, Inc. v. Dart Industries, Inc., supra; Practice Book § 4061;
The cardinal rule in construing contracts is to ascertain the intention of the parties. Finlay v. Swirsky, 103 Conn. 624, 634, 131 A. 420 (1925); McVay v. Anderson, 221 Ga. 381, 385, 144 S.E.2d 741 (1965). “[Interpretation of an agreement [by a court] is a search for the intent of the parties.” Lavigne v. Lavigne, supra, 428; Lar-Rob Bus Corporation v. Fairfield, supra. “A contract is to be construed [by the trier of fact] according to what is fairly to be assumed to be the understanding and intent of the parties.” Bridge-Mile Shoe Corporation v. Liggett Drug Co., 142 Conn. 313, 318, 113 A.2d 863 (1955); Bronx Derrick & Tool Co. v. Porcupine Co., 117 Conn. 314, 318, 167 A. 829 (1933). “Such a determination of what the parties intended is normally a question of fact, reversible only if the trier of fact could not reasonably have arrived at the conclusion that it had reached.” Thompson & Peck, Inc. v. Harbor Marine Contracting Corporation, supra, 130. “ ‘The intent developed is alone material, and when that is ascertained it is conclusive.’ Whitney v. Wyman, 101 U.S. 392, 395 [25 L. Ed. 1050 (1880)]; Adams v. Whittlesey, 3 Conn. 560 [1821]; Ogden v. Raymond, 22 Conn. 379, 385 [1853].” Massaro v. Savoy Estates Realty Co., 110 Conn. 452, 458, 148 A. 342 (1930).
The trial court was confronted by a printed form contract containing arbitration provisions that originally included a provision that required that disputes arising under the contract “shall be settled by arbitration.” The use of the word “shall” denotes that the directive
Because the command word “shall” was deliberately removed from the contract by the parties and replaced by the word “may,” it was not unreasonable for the trial court to have determined that the parties intended to modify their contract to provide for consensual rather than mandatory arbitration. See Shulman v. Zoning Board of Appeals, 154 Conn. 426, 429, 226 A.2d 380 (1967); Miller v. Phoenix State Bank & Trust Co., 138 Conn. 12, 16, 81 A.2d 444 (1951). We certainly cannot say that it was clearly erroneous for the court to have attributed such a meaning to the amended arbitration provision. See Rowe v. Cormier, supra, 373.
Finally, the plaintiff argues that even though the wording of the contract’s arbitration provision was changed to read “may” arbitrate, rather than “shall” arbitrate, there remains other wording in the printed
We cannot say that the trial court erred by concluding that arbitration, under the amended contract, required the consent of both parties.
The judgment is affirmed.
In this opinion the other justices concurred.
American Institute of Architects, Document A201, General Conditions of the Contract for Construction (13th Ed. 1976) §§ 7.9.1, 7.9.2 and 7.9.3 provide:
“7.9 ARBITRATION.
“7.9.1. All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof, except as provided in Subparagraph 2.2.11 with respect to the Architect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment as provided by Subparagraphs 9.9.4 and 9.9.5, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. No arbitration arising out of or relating to the Contract Documents shall include, by consolidation, joinder or in any other manner, the Architect, his employees or consultants except by written consent containing a specific reference to the Owner-Contractor Agreement and signed by the Architect, the Owner, the Contractor and any other person sought to be joined. No arbitration shall include by con
“7.9.2 Notice of the demand for arbitration shall be filed in writing with the other party to the Owner-Contractor Agreement and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Subparagraph 2.2.12 where applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.
“7.9.3 Unless otherwise agreed in writing, the Contractor shall carry on the Work and maintain its progress during any arbitration proceedings, and the Owner shall continue to make payments to the Contractor in accordance with the Contract Documents.”
Article 7 of the parties’ supplemental conditions, entitled “Miscellaneous Provisions,” provides:
“7.9 arbitration—In Paragraph 7.9.1 modify wording of first sentence as follows:'. . . provided by Subparagraphs 9.9.4 and 9.9.5, may be decided by arbitration . . . .’ ”
In support of its position the plaintiff cites a number of cases from the federal courts and courts of other states in which the use of the word “may” has been construed as mandating arbitration on the demand of a single party. None of those cases, however, is analogous to the present case because they do not implicate the specific factual situation encompassed herein, i.e., a modification from “shall” to “may” of the contract provision concerning arbitration. Absent the express change, the result in this instance might very well have been different. See, e.g., Bonnot v. Congress of Independent Unions Local #14, 331 F.2d 355, 359 (8th Cir. 1964); Louisa v. Newland, 705 S.W.2d 916, 919 (Ky. 1986).
The Connecticut cases cited by the plaintiff for the proposition that “may” mandates arbitration under the facts of this case are inapposite. See Paranko v. State, 200 Conn. 51, 509 A.2d 508 (1986); East Hartford v. East Hartford Municipal Employees Union, Inc., 10 Conn. App. 611, 525 A.2d 112 (1987), rev’d on other grounds, 206 Conn. 643, 539 A.2d 125 (1988).