Defendants appeal from a judgment for plaintiff in a lien foreclosure action. Plaintiff cross-appeals, assigning error to the court’s denial of his claims for quantum meruit and for prejudgment interest under ORS 701.420(2). We affirm on appeal and cross-appeal.
Defendant Bakke Corporation (Bakke) was the primary contractor on the Dairy substation project for Pacific Power & Light Company (PP&L). In September 1993, Bakke invited plaintiff to bid on the subcontract for excavation. When plaintiff agreed to bid, Bakke faxed it a bid form and site plan. Plaintiff bid on the subcontract on September 29. Upon receiving the bid, Bakke telephoned plaintiff and objected to certain pricing provisions. Plaintiff faxed an amended bid to Bakke on September 30. That bid set the price of certain contract items on a per-unit, rather than lump sum, basis, and contained exclusions and conditions that materially affected the price of the subcontract. Bakke again telephoned plaintiff, this time to discuss the exclusions and conditions and the per-unit pricing. Bakke’s president testified that plaintiffs project manager agreed to amend those portions of the bid. Plaintiffs project manager denied that the parties reached any such agreement. In any event, Bakke accepted the September 30 bid, and plaintiff began work on the excavation project.
On October 7, 1993, approximately the same date that plaintiff began to work on the project, Bakke faxed plaintiff a purchase order. That document contradicted some of the exclusions and conditions in plaintiffs September 30 bid. It also stated, “All work to be done according plans and specifications by Pacific Power & Light Co.” Bakke claims that it sent plaintiff a copy of its contract with PP&L along with the purchase order, but plaintiff denies receiving that contract.
On October 21, 1993, plaintiff billed Bakke for the work it had completed, and Bakke paid plaintiff $57,280. Certain charges in that billing conformed to the terms of the purchase order, rather than to plaintiffs bid. Plaintiff claims that it followed the purchase order only because Bakke *44 refused to pay the first installment otherwise and that it believed that the contract between the parties was the September 30 bid. That belief is evident, plaintiff claims, from a letter it sent Bakke on October 26,1993, stating that the bid was the contract. Bakke claims it never received that letter and argued at trial and in this appeal that the letter is a fabrication.
Plaintiff finished its work on the project on December 21, 1993. Two days later it filed a construction lien on PP&L’s Dairy substation in the amount of $92,000, pursuant to ORS 87.010(1). 1 On January 5, 1994, plaintiff mailed Bakke its final bill for $87,823. The lien and the final bill both were based on the price structure from plaintiffs September 30 bid, rather than on Bakke’s October 7 purchase order. Bakke refused to pay plaintiffs final bill. Bakke also asserts that around that time it began receiving complaints from plaintiffs suppliers and subcontractors, who claimed they had not yet been paid.
On April 20,1994, plaintiff sued Bakke and PP&L to foreclose its lien, demanding payment of $79,000. 2 Under the terms of its contract with PP&L, Bakke was required to indemnify PP&L for any lien claims arising out of the project. Pursuant to that agreement, Bakke filed a construction release bond under ORS 87.076 in June 1994. The effect of that filing was to transfer plaintiffs lien from PP&L’s substation to Bakke’s bond, as provided in ORS 87.083(1). 3 The *45 court then dismissed the foreclosure action as to PP&L. Plaintiff filed an amended complaint against Bakke and defendant United Pacific Insurance Company, the surety on Bakke’s bond.
At trial, the court found that Bakke’s October 7 purchase order was the contract between plaintiff and Bakke. The court found further that plaintiffs lien was perfected in the amount of $61,117. That figure represents the outstanding purchase order contract price of approximately $54,000, plus charges for equipment rental, surveying and extra materials that plaintiff claimed in its lien.
On appeal, defendants raise several assignments of error. We review lien foreclosure judgments
de novo. Miller v. Ogden,
In their first assignment of error, defendants argue that the trial court erred in finding that they were presently obligated to pay plaintiff anything on the contract, because plaintiff materially breached the contract by failing to pay some of its subcontractors. Plaintiff conceded at trial that some of its suppliers and subcontractors have yet to be paid. However, it argues that its relationship with those parties does not affect Bakke’s present duty to pay the remainder of the subcontract price.
As a general proposition, “[a] subcontractor is not required either to pay first for the labor and materials he furnishes or to deduct from the contract price his unpaid bills therefor before he may file a valid lien.”
Jersey & Son v. Bailey Const. Co.,
Defendants argue that Bakke’s October 7 purchase order incorporates by reference the entire contract between *46 Bakke and PP&L. They base that contention on the sentence in the purchase order that reads: “All work to be done according plans and specifications by Pacific Power & Light Co.” According to defendants, that sentence binds plaintiff to all general and specific terms and conditions of Bakke’s contract with PP&L, including conditions relating to payment of subcontractors.
We disagree. The quoted language from the purchase order is insufficient to incorporate the entire prime contract into the contract between plaintiff and Bakke. The purchase order simply requires that plaintiffs “work” must comply with the “plans and specifications” in PP&L’s contract. It does not mention or refer to conditions for payment or any other portion of the prime contract and, therefore, does not incorporate those provisions by reference.
Defendants cite
McGrath v. Electrical Const. Co.,
“[A]ll your costs, expense and profit, direct and incidental, for your performance of the work in accordance with the foregoing understandings and the terms in the General Conditions, Specifications and Agreement of the Contract * * * and all supplements thereto.” Id. at 298.
The broad language in the
McGrath
subcontract binding the subcontractor to “General Conditions, Specifications and Agreement of the Contract” has no parallel in the subcontract between plaintiff and Bakke. Mindful that we may not read into contracts provisions that the parties themselves have not included,
Thompson v. Bolliger, Hampton & Tarlow,
Defendants’ second assignment of error addresses the trial court’s conclusion that plaintiff s construction lien is valid. Defendants make three separate arguments that the lien is invalid. First, they contend that the lien is invalid because it overstates the amount owed to plaintiff. As previously noted, the court found that Bakke owed plaintiff only $61,117 after plaintiff sought first $92,000 and then $79,000 in its foreclosure action.
Overstatements will not automatically invalidate a lien. “In order for the overstatement to invalidate the hen, it must be an intentional one or one made through culpable negligence.”
Hays v. Pigg,
Here, plaintiffs overstatement was based on its contention that its bid, and not Bakke’s purchase order, formed the contract between the parties. The trial court did not accept that contention, as noted above. However, the court also upheld plaintiffs lien and found that it had been filed in good faith, thereby implicitly rejecting defendants’ contention that the lien was overstated through fraud or culpable negligence. Defendants dispute the latter finding because, they argue, the testimony of plaintiffs officers regarding the bid and purchase order was so unbelievable and self-contradictory as to raise the presumption that they were lying, or at least that they were grossly negligent in preparing their lien.
*48
We reject defendants’ argument. Although we review lien foreclosure claims
de novo,
we give substantial weight to the trial court’s credibility findings.
Teeny v. Haertl Constructors, Inc.,
Nor do we agree with defendants that plaintiffs overstatement was the result of culpable negligence. On this record, it is easy to see how the parties could have reasonable but conflicting interpretations of their business communications. Plaintiff was not culpably negligent when it believed that its bid was the contract or when it based its lien claim on that belief. We find that the overstatement of plaintiffs lien was not the result of fraud or culpable negligence and decline to find the hen invalid on that basis.
Defendants next contend that the lien is invalid because it included both lienable and nonlienable charges, and those charges were not segregated on the face of the lien. This argument is based upon the fact that plaintiff asked for more money than the trial court awarded and sought per-unit payment for certain items as provided in its bid, which items were payable in lump sums under Bakke’s purchase order. The traditional Oregon rule — known as the “rule of segregation”— is that a lien which commingles lienable and nonlienable charges is invalid if those charges can only be segregated through resort to extrinsic evidence.
See, e.g., Smith v. Lichtenthaler,
Relevant to this case, modern Oregon courts have declined to invalidate unsegregated liens where “the owners had sufficient knowledge with which to question the amount of the lien and thus would not have been prejudiced in settlement negotiations prior to the commencement of the suit.”
Robertson,
Here, defendants had such knowledge at all times relevant to this litigation. They knew that the difference in the amount on the face of the lien and the amount they believed they were obligated to pay was the result of the parties’ disagreement concerning the terms of their contract. Given that defendants had such knowledge, we decline to hold that the parties’ good faith disagreement regarding the contract price is sufficient reason to invalidate plaintiffs lien.
That result is consistent with our recent decisions in similar cases. In
Robertson,
we held that a hen was valid even though it contained a charge for over $40,000 in materials that had been purchased but never incorporated into the project.
We conclude that, as in those cases, defendants here had sufficient knowledge to question the amount on the face of the lien and to separate lienable from nonlienable charges. Accordingly, the lien was not invalid because it included charges that the trial court ultimately decided defendants were not obligated to pay. The trial court properly found that the lien was valid and could be foreclosed after deduction of those nonlienable charges.
Defendants’ third challenge to the validity of the lien is premised on the fact that plaintiff, a subcontractor, filed a lien for the subcontract price, rather than for the reasonable value of the work it performed. The traditional Oregon rule is that a subcontractor may file a lien against an owner only in the amount of the reasonable value of labor and material supplied.
See, e.g., Lakeview Drilling Co. v. Stark et al.,
The difficulty with defendants’ argument is that the reasonable value hmitation applies to liens by subcontractors against owners. This is an action by a subcontractor against a contractor, and the parties are clearly in contractual privity. It is true that plaintiffs lien was originally filed against the owner, PP&L, but, as noted above, the lien transferred from PP&L’s property to Bakke’s bond when that bond was filed. ORS 87.083(1). Plaintiff’s foreclosure action against PP&L was dismissed with prejudice. We decline to apply the limitation on subcontractor’s liens against owners in this case, where applying the hmitation would allow Bakke to avoid paying on its own contract with plaintiff.
In sum, we affirm the trial court on defendants’ second assignment of error. None of defendants’ three grounds for invalidating the hen is persuasive. The trial court did not err in finding that plaintiffs hen was valid in the amount of $61,117.
Our resolution of those issues also effectively disposes of defendants’ third and fourth assignments of error. In their third assignment, defendants seek attorney fees under ORS 87.060(5), which grants such fees in lien foreclosure actions to the party who prevails on the issues of hen validity and foreclosure. Because defendants have not prevailed on those issues, they are not entitled to attorney fees under ORS 87.060(5). In their fourth assignment of error, they seek to recover attorney fees and bond premiums that they were contractually obligated to pay to PP&L following plaintiffs original lien foreclosure action against PP&L. Defendants assert that they are entitled to recover those fees and premiums *52 from plaintiff because plaintiff breached its contract with Bakke by failing to pay its subcontractors and suppliers. Because we have held that plaintiff did not breach its contract with Bakke in that manner, we reject defendants’ claim. Defendants also claim in their fourth assignment of error that they are entitled to recover their bond premiums under ORS 87.076(4)(a), which allows recovery of bond costs from a lienholder who fails to release or foreclose a lien within the time provided by statute. Because plaintiff moved to foreclose its lien within the statutory time period, ORS 87.055, defendants’ argument fails.
Plaintiff cross-appeals, assigning error to the denial of its claims for
quantum meruit
and for prejudgment interest. Because plaintiff has recovered the amount owed under the contract in its lien foreclosure action, we need not reach the alternative argument on the
quantum meruit
claim.
King v. All Pro Services, Inc.,
Plaintiff also cross-appeals from the trial court’s denial of its request for prejudgment interest under ORS 701.420(2). That statute provides for one percent monthly interest on payments withheld from a contractor or subcontractor under ORS 701.420(1). That subsection, in turn, allows an owner, contractor or subcontractor to withhold up to five percent of the contract price as “retainage.” “Retain-age” is defined as “the difference between the amount earned * * * under a construction contract and the amount paid on the contract * * ORS 701.410(4). Plaintiff appears to argue that defendants treated the entire contract price as retainage when they delayed payment to plaintiff based on their belief that plaintiff had breached the subcontract.
The trial court denied plaintiffs claim, stating “I do not feel that [ORS 701.420(2)] applies in this situation.” We agree. Retainage is a portion of the contract price deliberately withheld to assure that a contractor or subcontractor will satisfy its obligations and complete a project.
Contractors, Inc. v. Tri-Met,
Affirmed on appeal and on cross-appeal.
Notes
ORS 87.010(1) provides:
“Any person performing labor upon, transporting or furnishing any material to be used in, or renting equipment used in the construction of any improvement shall have a lien upon the improvement for the labor, transportation or material furnished or equipment rented at the instance of the owner of the improvement or the construction agent of the owner.”
That demand was less than the original lien of $92,000 because plaintiff agreed to partial satisfaction of its claim during negotiation.
ORS 87.083(1) provides:
“Any suit to foreclose a lien pursuant to ORS 87.060 which is commenced or pending after the filing of a bond or deposit of money under ORS 87.076 shall proceed as if no filing or deposit had been made except that the lien shall attach to the bond or money upon the filing or deposit and the service of notice thereof upon the lien claimant. The property described in the claim of lien shall thereafter be entirely free of the lien and shall in no way be involved in subsequent proceedings.” (Emphasis supplied.)