Opinion
Plaintiff, a grading and excavating contractor, appeals from that part of a judgment denying foreclosure of an asserted mechanic’s lien upon property owned by those defendants who were homeowners of and lenders having liens on a part of the property described in the claim of lien.
The action arose out of two contracts; one under date of December 12, 1963, for excavating and grading an undeveloped tract of land, described as the West one-half of Pueblo Lot No. 1786, Pueblo Lands of San Diego, owned by Harbor Crest, a partnership; and the other under date of March 9, 1964, for the construction of storm drains on that tract.
Harbor Crest planned development of the whole tract. The initial development contemplated a three-unit subdivision of a portion of the tract to be known respectively as Harbor Crest Unit No. 1, consisting of 32 lots, Harbor Crest Unit No. 2, consisting of 14 lots and Harbor Crest Unit No. 3, consisting of 46 lots. As a part of the preliminaries to this development, Harbor Crest applied for and obtained a special land development permit from the City of San Diego issued February 13, 1964, authorizing the excavating, grading and storm drain work covered by the two contracts with plaintiff. The Subdivision Map Act (Bus. & Prof. Code, § 11500 et seq.) and chapter 10, article 2, division 2 of the San Diego Municipal Code (§ 102.0200 et seq. San Diego Mun. Code) prescribe the procedures incident to filing and recording a subdivision map. These statutes provide, in substance, the property owner intending to subdivide shall file a tentative map with the planning department; upon approval of this map and compliance with designated prerequisites shall submit a final map to the city engi *729 neer; prior to any construction of improvements or land development shall submit detailed plans and specifications thereof and enter into a contract with the city to make, install and complete them within a fixed time; but, in the event he desires to do certain work prior to entering into such an agreement, may make an application to do so under a special permit which shall be accompanied by plans describing the work proposed. The city engineer may issue such a permit providing a bond is posted in an amount assuring the rehabilitation of the land, including grading and planting, in the event the subdivision map is not recorded. When the special permit is for all work required in connection with the subdivision and the work has been completed, the agreement with the city to make, install and complete such work is not required. Where the required work has been completed or the subdivider executes the agreement to do that work and other prerequisites have been complied with, the city council shall accept the map and authorize its recording. The special permit obtained by plaintiff to do the excavating, grading and storm drain work in question was issued pursuant to the foregoing statutes.
Pertinent to the issue at bench is a chronology of the events following execution of the contracts by plaintiff and Harbor Crest. The work required thereby was performed under the special permit during the period February 14, 1964, through June 5, 1964. On June 25, 1964, plaintiff sent Harbor Crest its final invoice showing the total sum payable under the contracts was in excess of $254,000 of which there was then unpaid $125,028.82. On November 24, 1964, an inspector, acting on behalf of the city engineer, made a final inspection of the work to be done under the special permit and initialed the permit indicating the work had been completed. On January 28, 1965, final subdivision maps for Harbor Crest Units 1, 2 and 3 were approved. On the same date, preliminary to such approval, Harbor Crest executed an agreement with the city to make, install and complete all of the improvements and land development on the subdivision sites in accord with the plans theretofore submitted with the proposed maps. The evidence shows this agreement was directed primarily to work other than that performed under the two contracts by plaintiff under the special permit. The subdivision maps were recorded March 1, 1965. Thereafter defendant homeowners purchased lots in Unit 3, and defendant lenders made loans secured by an appropriate lien on those lots. On October 20, 1965, the city filed a notice of completion on Unit No. 1, and on September 8, 1966, filed a notice of completion on Unit No. 2, indicating compliance by Harbor Crest with the provisions of the subdivision agreement respecting those two units. A notice of completion formally accepting Unit No. 3 had not been filed up to time of trial. On March 28, 1967, plaintiff filed a claim of lien against Lots 47 through 96 inclusive of Harbor Crest Unit No.3 and the *730 north one-half of the west one-half of Pueblo Lot No. 1786, Pueblo Lands of San Diego, being that part of the original tract owned by Harbor Crest not included within the subdivision. Noteworthy is the omission from the claim of lien of any of the property in Harbor Crest Units Nos. 1 and 2.
The work done by plaintiff under the two contracts and the special permit consisted in grading, excavating and storm drain construction on the land eventually constituting Harbor Crest Units Nos. 1, 2 and 3 and also on parts of the adjoining land in the tract.
Plaintiff sought a personal judgment against Harbor Crest for the sum of $52,628.82; that this amount be adjudged a lien upon all of the land described in their claim of lien; and that this lien be foreclosed. Defendant homeowners and lenders by their answer asserted the claim of lien was ineffective because not filed within the time prescribed by law; that plaintiff attempted to place the burden of payment for the work performed under its two contracts upon the owners of Harbor Crest No. 3 and the property not subdivided in spite of the fact those contracts pertained to the development of Harbor Crest Units Nos. 1, 2 and 3, and the property not subdivided; that plaintiff was estopped to assert its lien; and that plaintiff was guilty of laches. The court decreed recovery by plaintiff of the sum of $52,028.82 from Harbor Crest; denied foreclosure of plaintiff’s asserted mechanic’s hen against the interest of defendant homeowners and lenders in the property described in that hen; and made no disposition respecting the asserted hen upon the property of Harbor Crest, i.e., the property not subdivided. Plaintiff appeals only from that part of the judgment in favor of the defendants, homeowners and lenders.
The court found and the evidence supports the finding A. Alan Baxter is president and sole shareholder of plaintiff A. A. Baxter Corporation and also a hmited partner in Harbor Crest; the work of improvement performed by plaintiff under its contracts with Harbor Crest constituted a separate work of improvement as defined in section 1184.1 of the Code of Civil Procedure; this work was performed under the special permit and was completed in a manner acceptable to the city engineer on November 24, 1964; subsequent to completion of the work on November 24, 1964, plaintiff was aware of the fact Harbor Crest was developing the land upon which the work had been performed into a subdivision, that residential dwellings were being constructed thereon, that these dwellings were being sold to defendant homeowners, and that defendant lenders were extending loans secured by deeds of trust on the land; the claim of lien filed by plaintiff did not specify what portion of the amount due it for such work was allocable to Unit No. 3; plaintiff did not submit proof of the reasonable value of the work performed on Unit No. 3 but only submitted proof of the total amount owing for *731 work performed on Units 1, 2 and 3 as well as the land not subdivided; and although the work under said contracts had been completed on November 24, 1964, plaintiff did not take any action to assert its right to a lien until filing its claim of lien on March 28, 1967.
The court concluded plaintiff’s claim of lien had not been filed within the time prescribed by section 1193.1 of the Code of Civil Procedure; under the San Diego Municipal Code work performed under a special permit is deemed completed when acceptable to the city engineer; the signing of the special permit by the agent of the city engineer signified the work performed under the permit was completed in a manner acceptable to the city engineer and constituted an acceptance of the work by the City of San Diego; plaintiff’s delay from November 24, 1964, until March 28, 1967, in asserting its claim of lien was unreasonable and prejudicial and, under the equitable doctrine of laches, plaintiff is barred from asserting any claim of lien; and plaintiff’s claim of lien was insufficient because the reasonable value of the work performed on Unit No. 3 was not stated or proved.
There is evidence supporting the conclusion Mr. Baxter had knowledge Harbor Crest was experiencing financial difficulties; nevertheless plaintiff did not assert its claim of lien on the subdivision property which would have foreclosed acceptance of the subdivision maps, but permitted the maps to be filed and the property therein to be sold to persons having no knowledge of its claimed right to a lien; on September 15, 1965, plaintiff entered into an agreement with Harbor Crest allowing its lien rights on the property in Unit No. 1 to expire without filing a lien in consideration of an agreement to pay and an assignment to it by Harbor Crest of a minimum of $900 from every lot sale escrow on Harbor Crest Units Nos. 1, 2 and 3 until the sum of $58,028.82 and accrued interest of $8,172.82, together with interest on the unpaid balance was paid in full; the sum of $5,400 was paid under this agreement; and it was further provided therein Harbor Crest would delay acceptance of Unit No. 2 and Unit No. 3 until the aforementioned sums were paid in full, and in the event payments were not made as prescribed by the agreement on Units No. 2 and 3, or acceptance thereof occurred, prior to payment of said sums, plaintiff should exercise its right to file a lien on Units 2 and 3. Execution of the foregoing agreement under the circumstances noted supports the conclusion plaintiff and Harbor Crest contemplated the sale of lots in the subdivision and the subjection of the lots in Units 2 and 3 to a secret claim of lien by plaintiff by manipulating the time within which plaintiff believed it might file a claim of lien.
We conclude the judgment should be affirmed because (1) plaintiff’s claim of lien against only a part of the tract upon which the work under its contracts has been performed is not authorized by the mechanic's lien statute; (2) its claim of lien was not filed within the time prescribed by the *732 statute; and (3) relief properly was denied under principles of estoppel and laches.
Plaintiff was entitled to a claim of lien for the work performed under its two contracts by virtue of section 1184.1 of the Code of Civil Procedure which provides “Any person who, at the instance or request of the owner ... of any lot or
tract of land,
grades, fills in, or otherwise improves the same, . . . has a lien upon said lot or
tract of land
for his work done and materials furnished.” (Italics ours.) The right to a lien thus conferred is distinct from but similar to that conferred by section 1181 of the Code of Civil Procedure which provides that all persons performing labor upon or furnishing materials to be used in the construction, alteration, addition to or repair of any building, structure or other work of improvement shall have a lien upon the property upon which they have bestowed labor or furnished materials. As these liens are the creatures of statute the objects thereof are limited to those designated by the statute.
(Davis
v.
MacDonough,
Plaintiff actually completed the work of improvement described in its contracts on June 5, 1964. However, the trial court found the work of improvement encompassed within those contracts was subject to acceptance by the City of San Diego; the completion of that work for lien filing purposes, by virtue of section 1193.1, subdivision (e) of the Code of Civil Procedure, was deemed to be the date of such acceptance; acceptance occurrred when the inspector initialed the special permit under which the work had been performed, indicating its completion on November 24, 1964; a claim of lien, by virtue of section 1193.1, subdivision (c) of the Code of Civil Procedure, to be effective, should have been filed within 90 days after November 24, 1964; and the claim of lien filed on March 28, 1967, was ineffective. Both parties agree the work was subject to acceptance by the city. Plaintiff contends the acceptance was that required by the subdivision improvement agreement between Harbor Crest and the City of San Diego under date of January 28, 1965; acceptance of the work under that agreement has not taken place; lacking such acceptance completion of the work has not occurred; and, for this reason, its claim of lien was filed within the time prescribed by section 1193.1, subdivision (c), i.e., within 90 days after completion of the work. Defendants contend, and the court concluded, the acceptance was that required by the special permit under which it was performed, rather than by the subdivision improvement agreement. The latter position is well taken. A work of improvement is “subject to acceptance” by governmental authority within the contemplation of section 1193.1, subdivision (e) only when required by legislative enactment.
(Howard A. Deason & Co.
v.
Costa Tierra Ltd.,
Defendants presented the issues of estoppel and laches by their answer. The findings of the court did not set forth specifically each of the elements of estoppel. The conclusion of law drawn, by the court declares plaintiff is barred from asserting any claim of hen under the equitable doctrine of laches, but makes no reference to the doctrine of estoppel. However, the facts found and those established by undisputed evidence support an application of both doctrines. Plaintiff, through its president and sole stockholder, knew of the financial insecurity of Harbor Crest but withheld filing its claim of lien. Plaintiff’s president and sole stockholder was a limited partner in Harbor Crest, and his financial interests in the partnership would be subserved by withholding any public assertion of plaintiff’s right to a mechanic’s lien. Plaintiff’s contracts with Harbor Crest provided: “Terms of payment are cash, payable every two weeks.” If plaintiff had insisted upon payment as provided by its contract and upon nonpayment had asserted its claim of lien the subdivision map would not have been accepted by the city; the lots in the subdivision would not have been subjects for sale; defendant homeowners would not have purchased and improved those lots; and defendant lenders would not have loaned money on them. By remaining silent respecting its claim of lien plaintiff, acting through its president and sole stockholder, preserved the latter’s interest in Harbor Crest without jeopardizing his sole ownership interest in plaintiff. The net result of the manipulation in which plaintiff engaged, through its president and sole
*735
stockholder, if successful, would have been to preserve the financial integrity of Harbor Crest at the cost and expense of defendants homeowners and lenders. The purpose of the mechanic’s lien statute is the protection of property owners as well as lien claimants.
(R. D. Reeder Lathing Co.
v.
Allen,
The judgment is affirmed.
Brown (Gerald), P. J., and Whelan, J., concurred.
