239 Conn. 284 | Conn. | 1996
This appeal arises from an action brought by the plaintiff, 24 Leggett Street Limited Partnership, against the defendant, Beacon Industries, Inc., to recover damages for the alleged environmental contamination of real property purchased by the plaintiff from the defendant. The plaintiff appeals from the judgment of the trial court, claiming that the trial court improperly: (1) failed to include in the plaintiffs damages for breach of the purchase and sale agreement (agreement) the full cost to excavate and remove certain environmental contamination, including certain estimated
The following facts are not disputed. From 1945 to 1987, the defendant owned and operated a manufacturing facility producing jet engine components on property located at 24 Leggett Street in East Hartford.
On January 12,1988, the plaintiff purchased the property from the defendant. During the course of extensive negotiations lasting four to five months prior to the closing, the plaintiff advised the defendant that the purchase was contingent on the plaintiff receiving certain assurances from the defendant regarding the environmental condition of the property. On October 20, 1987, the defendant provided the plaintiff with a copy of an environmental site assessment report dated July 8,1987 (1987 report). The 1987 report had been prepared by HRP Associates, Inc. (HRP), for Harper Surface Finishing Systems, a company that had earlier expressed interest in the property.
In paragraph 15 (k) of the agreement executed by the parties, the defendant warranted: “Except as may be indicated in a certain Site Assessment Report for the Property, prepared by HRP Associates, Inc., and issued on July 8, 1987 ... no ‘Hazardous Waste’ . . . and/or ‘Spill’ . . . and/or ‘Hazardous Substance’ . . . and/or other environmental contamination now exists, or has ever been stored, on the Premises . . . .”
In September, 1988, the plaintiff discovered a depression in the asphalt in an area within the fenced portion of the property’s parking lot. A contractor assisting in renovation work on the property dug up the asphalt, exposing discolored soil, metal shavings and the stench
On November 8, 1988, HRP conducted additional excavation, which revealed metal shavings, soil discoloration and a hydrocarbon odor. Testing of soil samples taken from this excavation showed xylene above the state action level and the presence of an unknown hydrocarbon mix.
On February 2, 1989, the plaintiff forwarded an invoice to the defendant totaling $59,668.17 for remedia
In August, 1989, the plaintiff remained concerned about further soil contamination on the property and engaged HRP to test other locations at the site. HRP installed thirteen test pits throughout the property and drilled four groundwater monitoring wells in addition to the five existing wells. According to HRP’s November, 1990 report,
In July, 1991, within the five year indemnity period of paragraph 15 (k), the plaintiff commenced this action, alleging fraudulent misrepresentation (count one), negligent misrepresentation (count two), breach of warranty (count three) and breach of contract (count four).
After a seven day bench trial, the trial court rendered judgment in favor of the plaintiff on count three in the amount of $7863.95, but in favor of the defendant on the remaining counts. Specifically, the trial court held the defendant liable for the costs associated with the removal of 1370 cubic yards of contaminated soil prior to December, 1988. The trial court, however, refused to hold the defendant liable for costs associated with the remediation of the contamination as described in HRP’s November, 1990 report and its revised 1991 estimate, reasoning that the report’s assumptions and estimates, although made within the indemnity period,
I
We first address the issues raised by the defendant on cross appeal because resolution of the defendant’s claims eliminates certain substantial issues raised by the plaintiff and simplifies our analysis. We begin with the defendant’s first claim on its cross appeal, namely, that the trial court; improperly held the defendant liable for the remediation of material not covered by paragraph 15 (k) of the agreement. Specifically, the defendant argues that it cannot be held liable for any
A
The defendant first argues that the trial court mischaracterized the metal shavings
Our resolution of the defendant’s claim is guided by the general principles governing the construction of contracts. A contract must be construed to effectuate
The trial court heard evidence that the metal shavings found in the November, 1988 excavation and the subsequent test pits constituted special waste. Although the court did not make a specific determination in its memorandum of decision as to the character of the shavings, implicit in its decision that the defendant breached the agreement is a finding that the shavings constituted, at the very least, an environmental contaminant covered by paragraph 15 (k). We conclude that the metal shavings constitute special waste as defined by the department and, even if not characterized as special waste, the metal shavings, as solid waste subject to regulation by the department, fall within the catchall category of
Paragraph 15 (k) of the agreement warrants that, aside from that disclosed by the 1987 report, the site contains no hazardous waste, as defined by General Statutes (Rev. to 1987) § 22a-115 or General Statutes (Rev. to 1987) § 22a-448;
Specifically, the defendant relies on the doctrine of ejusdem generis, a rule of construction, to support the claim that the phrase “other environmental contamination” cannot encompass the metal shavings because that phrase is limited by the specifically defined terms preceding it. The defendant concludes that this specific limitation means that environmental contamination is covered only if it is hazardous waste or a hazardous substance. We disagree.
The principle of ejusdem generis applies when “(1) the [clause] contains an enumeration by specific words; (2) the members of the enumeration suggest a specific class; (3) the class is not exhausted by the enumeration; (4) a general reference [supplements] the enumeration . . . and (5) there is [no] clearly manifested intent that the general term be given a broader meaning than the doctrine requires.” 2A J. Sutherland, Statutory Construction (5th Ed. Singer 1992) § 47.18. Thus, “[t]he doctrine of ejusdem generis calls for more than . . . an abstract exercise in semantics and formal logic. It rests on particular insights about everyday language usage. When people list a number of particulars and add a general reference like ‘and so forth’ they mean to include by use of the general reference not everything else but only others of like kind. The problem is to determine what unmentioned particulars are sufficiently like those mentioned to be made subject to the [clause’s] provisions by force of general reference.” Id.
The defendant’s conclusion, limiting as it does the definition of “other environmental contamination” to hazardous waste and/or hazardous substances, interprets “like kind” to mean “identical kind.” This interpretation would render the phrase meaningless in the
Our reading of paragraph 15 (k), taking into account the rules of construction and the logic of everyday language, supports an interpretation of the catchall phrase “other environmental contamination” as encompassing those contaminants, including solid and special waste, that are subject to regulation by the department. Our reasoning is twofold: (1) the specifically enumerated classes are alike in that they are forms of waste defined and regulated by the department and, thus, classes of like kind to those enumerated would include defined and regulated wastes; and (2) the ordinary everyday meaning of the word “contaminant” encompasses regulated waste such as solid and special waste.
The 1985 revision of § 22a-209-l of the Regulations of Connecticut State Agencies, in effect at the time of the actions involved here, defined special wastes as “non-hazardous solid wastes which require special handling . . . either more or less restrictive than the requirements imposed on a solid waste disposal area.” (Emphasis added.) See footnote 9. The regulation further provided that “[t]he term includes . . . non-hazardous . . . industrial sludges, liquids, solids or contained gases . . . .” (Emphasis added.) Under this definition, the metal shavings need not exhibit toxicity to be classified as a special waste, but rather need only
The disposal of special waste is regulated by § 22a-209-8 of the Regulations of Connecticut State Agencies, the pertinent provisions of which provide: “Special waste disposal shall comply with the permit and operation and management requirements of solid waste disposal areas with the exceptions and additional special considerations noted in this section. . . . (b) A separate permit to construct or to operate is not required if combined disposal of the waste in question with other solid wastes or special wastes is authorized and the requirements for these special wastes are adequately provided for in the facility plan, (c) The combined disposal of special wastes with other solid wastes or special wastes is prohibited unless specifically approved in writing by the Commissioner. . . . Any such approval shall become part of the facility plan.”
The defendant makes much of the fact that the plaintiff did not seek permission from the department to treat the metal shavings as special waste. Our examination of the record, however, reveals no indication that the waste disposal facility to which the excavated material was taken was not approved by the department as a special waste disposal site. More to the point, the shavings’ status as special waste is determined by the department’s regulatory definition, and not by the plaintiffs actions. Finally, were we to accept the defendant’s argument that the shavings are not special waste, there is no credible argument to be made that the shavings are not solid waste, as defined by General Statutes (Rev. to 1987) § 22a-207 (3); see footnote 22; and as such subject to regulation by the department.
The regulation of special waste is part of an elaborate regulatory scheme administered by the department for the management of all solid waste products, whether
B
The defendant next argues that, even if the metal shavings fall within the purview of paragraph 15 (k), the trial court improperly held the defendant hable for the excavation that tookplace after November 11,1988. Specifically, the defendant argues that the excavation of the additional 370 cubic yards between November 11 and November 15, 1988, was not necessary because there were no actionable levels of contaminants present in test samples taken by HRP on November 11, the results of which were not yet known at the time of the excavation. We disagree.
Implicit in the trial court’s decision awarding the plaintiff damages covering the November, 1988 excava
The defendant has conceded that the initial excavation of 1000 cubic yards of contaminated soil was covered by paragraph 15 (k) of the agreement. This concession appears to be based on the fact that the initial testing of the soil revealed the presence of xylenes in excess of listed state action levels.
The trial court heard testimony that, on November 8, 1988, HRP investigators noted the presence of metal shavings, discolored soil, and a hydrocarbon odor in the soil being removed. Tests taken that day showed elevated xylene levels. HRP’s expert testified that he made the same visual and olfactory observations on November 11 and, on the basis of that evidence, decided to proceed with further excavation, even though the results of tests taken that day were not yet available. Because the November 8 tests indicated elevated xylene levels and the olfactory and visual evidence available to the HRP expert on November 11 was the same as
II
The defendant’s second claim in its cross appeal is that the trial court improperly calculated the damages associated with the 1988 excavations. Specifically, the defendant claims that the court did not take into account a discount that the plaintiff had negotiated with the excavating company, and did not deduct costs associated with a paving upgrade to which the plaintiff has conceded it was not legally entitled.
On February 2, 1989, the plaintiff submitted an invoice to the defendant detailing the cost of the 1988 excavations. Included in those costs was a charge of $35,690 for the excavation itself, as well as an estimated charge of $18,000 for repaving the excavated area.
Again we are asked to review the trial court’s factual determinations. At trial, the court heard testimony regarding the disputed costs and the discounted total excavation cost of $32,936.35, which the plaintiff had negotiated with the excavating contractor but had not passed on to the defendant. The court’s memorandum of decision reflects this testimony and includes a downward adjustment in the excavation cost that reflects the discount negotiated by the plaintiff and another downward adjustment in the paving award. We conclude that the trial court’s conclusion is adequately supported by the record and, therefore, is not clearly erroneous. See Practice Book § 4061; Groton v. Yankee Gas Services Co., supra, 224 Conn. 691.
Ill
We. next consider the plaintiffs appeal, beginning with the proper construction of paragraph 15 (k) of the agreement. The plaintiff argues that the trial court failed to include in its damages all of the costs associated with the remediation of the environmental contamination at the site.
A
The plaintiff argues that the trial court improperly denied recovery of its full measure of damages. In contrast, the defendant claims that it can be held liable only for those costs actually incurred by the plaintiff. We conclude that, under paragraph 15 (k) of the agreement, the plaintiffs damages are not limited to costs actually incurred.
Paragraph 15 (k) provides in relevant part: “Seller shall defend, indemnify and hold Purchaser harmless from and against any liabilities, losses, damages, costs or expenses (including reasonable attorneys’ fees) of any nature arising from the environmental condition of or problem with the Property, which condition or problem arose prior to Closing and whether known by
The defendant argues that it is liable only for the costs actually incurred by the plaintiff. In other words, the defendant claims that its contractual obligation arises only when the plaintiff suffers a loss, rather than mere liability. We disagree. On the issue of whether, in the event of a breach of the contract, the plaintiffs damages would be limited to those actually incurred, this contract presents clear and definitive language that for more than sixty years has been interpreted but one way. The terms in paragraph 15 (k) are unambiguous in their requirement that the defendant will hold the
B
The plaintiff further argues that the trial court improperly refused to award damages in the form of estimated future cleanup costs. Specifically, although the trial court did not require the plaintiff to have actually incurred the damages in order to collect them, the plaintiff asserts that the trial court improperly required it to ascertain with reasonable certainty, prior to expiration of the five year indemnity agreement, the amount of its damages. In response, the defendant contends that the trial court was correct in determining that the November, 1990 and November, 1991 cost estimates were merely speculative. The defendant further argues that the trial court properly excluded the costs associated with the December, 1994 testing from the plaintiffs judgment because that contamination was not actually discovered within the five year indemnity period. We agree with the plaintiff.
In its memorandum of decision, the trial court stated: “The court holds that the defendant cannot be held responsible for any contamination made on the assumptions and estimates of HRP in its November, 1990 and 1991 reports. These assumptions and estimates based on limited data and without further testing were merely speculative.
Assuming, without deciding, that the trial court could properly reject the 1990 and 1991 estimates as speculative, we nevertheless disagree with the trial court’s determination regarding the 1994 investigation. “It is axiomatic that the burden of proving damages is on the party claiming them. Gargano v. Heyman, 203 Conn. 616, 620, 525 A.2d 1343 (1987); Conaway v. Prestia, 191 Conn. 484, 493-94, 464 A.2d 847 (1983); Dixon v. Trubisz, 17 Conn. App. 216, 217-18, 551 A.2d 1259 (1988). When damages are claimed they are an essential element of the plaintiffs proof and must be proved with reasonable certainty. Simone Corporation v. Connecticut Light & Power Co., 187 Conn. 487, 495, 446 A.2d 1071 (1982); Bianco v. Floatex, Inc., 145 Conn. 523, 525, 144 A.2d 310 (1958). Damages ‘are recoverable only to the extent that the evidence affords a sufficient basis for estimating their amount in money with reasonable
“Although damages often are not susceptible of exact pecuniary computation and must be left largely to the sound judgment of the trier; Johnson v. Flammia, [169 Conn. 491, 500, 363 A.2d 1048 (1975)]; this situation does not invalidate a damage award as long as the evidence afforded a basis for a reasonable estimate by the [trier] of that amount. Paiva v. Vanech Heights Construction Co., 159 Conn. 512, 517, 271 A.2d 69 (1970).” (Internal quotation marks omitted.) Conaway v. Prestia, supra, 191 Conn. 494. “Mathematical exactitude in the proof of damages is often impossible, but the plaintiff must nevertheless provide sufficient evidence for the trier to make a fair and reasonable estimate. ...” (Citations omitted.) Falco v. James Peter Associates, Inc., 165 Conn. 442, 445, 335 A.2d 301 (1973).
It is undisputed that, prior to the expiration of the five year indemnity period, the plaintiff notified the defendant that additional contamination existed at the property and that it would require remediation.
We conclude that the trial court improperly required the plaintiff to quantify with reasonable certainty, within the five year indemnity period, the amount of its damages. Although a plaintiff has the evidentiary burden of proving its damages at the time of trial; Falco v. James Peter Associates, Inc., supra, 165 Conn. 445; there is no additional requirement that the plaintiff must satisfy this evidentiary burden prior to the expiration of the applicable limitations period.
IV
Finally, the plaintiff argues that the trial court improperly declined to award it attorney’s fees and costs in
“The general rule of law known as the ‘American rule’ is that attorney’s fees and ordinary expenses and burdens of litigation are not allowed to the successful party absent a contractual or statutory exception. See Alyeska Pipeline Service Co. v. Wilderness Society, 421 U.S. 240, 247, 95 S. Ct. 1612, 44 L. Ed. 2d 141 (1975); Fleischmann Distilling Corporation v. Maier Brewing Co., 386 U.S. 714, 717, 87 S. Ct. 1404, 18 L. Ed. 2d 475 (1967). This rule is generally followed throughout the country. See 20 Am. Jur. 2d, Costs § 72. Connecticut adheres to the American rule. See, e.g., Brookfield v. Candlewood Shores Estates, Inc., 201 Conn. 1, 14, 513 A.2d 1218 (1986); Gino’s Pizza of East Hartford, Inc. v. Kaplan, 193 Conn. 135, 140, 475 A.2d 305 (1984); Gionfriddo v. Avis Rent A Car System, Inc., 192 Conn. 280, 297, 472 A.2d 306 (1984); Litton Industries Credit Corporation v. Catanuto, 175 Conn. 69, 75, 394 A.2d 191 (1978); Central New Haven Development Corporation v. Potpourri, Inc., 39 Conn. Sup. 132, 134, 471 A.2d 681 (1983).” Marsh, Day & Calhoun v. Solomon, 204 Conn. 639, 652, 529 A.2d 702 (1987). There are few exceptions. For example, where a specific contractual term provides for the recovery of attorney’s fees and costs; see, e.g., Storm Associates, Inc. v. Baumgold, 186 Conn. 237, 245, 440 A.2d 306 (1982); or where a statute controls. See, e.g., General Statutes § 52-240a (attorney’s fees may be awarded in products liability action). Additionally, an indemnitee is entitled to recover from an indemnitor, as part of its damages, attorney’s fees, costs and expenses. 41 Am. Jur. 2d, Indemnity § 48 (1995); Sendroff v. Food Mart of Connecticut, Inc., 34 Conn. Sup. 624, 626, 381 A.2d 565 (1977); see Calamita v. DePonte, supra, 122 Conn. 27 (stating indemnitee is entitled to recover not only sum
Here, paragraph 15 (k) expressly provides for the recovery of attorney’s fees and costs.
The judgment is affirmed insofar as it ordered judgment in favor of the plaintiff on liability; insofar as the trial court misapplied the law of damages, the judgment is reversed and the case is remanded to the court with direction to hold a new trial limited to the plaintiffs damages, including attorney’s fees and costs, consistent with this opinion.
In this opinion the other justices concurred.
Although the defendant completed moving its manufacturing operations to a facility in Bloomfield by June, 1987, the defendant continued to own the Leggett Street property until the sale to the plaintiff in 1988.
Based upon a site inspection and background search, the 1987 report recommended that: (1) the 107 waste barrels located in the fenced parking lot be sampled to determine the contents and be disposed of properly; (2) five of the seven transformers be checked for the possible presence of PCBs; (3) four soil-stained areas be surface sampled for contaminants; (4) the thirty-five year old underground oil storage tank be removed and the soil sampled; and (5) monitoring wells be installed in four areas.
Paragraph 15 provides in relevant part: “The Seller represents and warrants . . . (k) Except as may be indicated in a certain Site Assessment Report for the Property, prepared by HRP Associates, Inc. and issued on
Tests revealed the presence of P and M-xylene at 817 parts per billion and O-xylene at 1126 parts per billion, both well in excess of the state action level of 100 parts per billion.
One sample reflected P and M-xylene at 182 parts per billion and O-xylene at 794 parts per billion, both above the state action level. Another sample showed O-xylene present at 69 parts per billion.
Although the test results indicated no compounds in the 8010 or 8020 scan exceeding the state action level, HRP did not at this time test for total petroleum hydrocarbon content. Rather, HRP was concerned about halogenated and aromatic hydrocarbons caused by industrial solvents, and the 8010 and 8020 scans could detect their presence.
Additionally, the defendant disputed the hours necessary for the use of certain construction equipment as well as the area to be repaved.
In order to correct certain inaccuracies in the original report released in November, 1989, HRP issued a revised report in November, 1990.
At the time of the actions involved in this case, § 22a-209-l of the Regulations of Connecticut State Agencies defined “special wastes” as “non-hazardous solid wastes which require special handling, as specified in these regulations, either more or less restrictive than the requirements imposed on a solid waste disposal area. The term includes the following: (1) nonhazardous water-treatment, sewage treatment or industrial sludges, liquids, solids or contained gases; fly-ash and casting sands or slag; and contaminated dredge spoils; (2) scrap tires; (3) bulky waste, as defined in these regulations; and (4) asbestos.” This regulation was subsequently revised in 1990 by adding language not relevant to this opinion.
Because test pit 1A was contaminated, HRP estimated the area of soil to be removed by bisecting the distance to the surrounding uncontaminated test pits. The resulting estimate was 275 cubic yards of soil.
The $299,950 estimate assumed excavation of the full distance from test pit 1A to the surrounding test pits. Walter Gancarz, vice president of HRP, testified: “[W]hen we had assumed halfway before, by going all the way now, basically, you increase the amount by almost four times. The initial estimate is probably on the optimistic side, and [this] estimate on the very conservative side.”
Three additional counts relating to the Connecticut Transfer Act, General Statutes § 22a-134, were withdrawn by the plaintiff at the time of trial.
Specifically, metal shavings were detected in borings 1, 2, 3, 4, 6, 7, 8, 9, 11, 12 and 16 through 27.
The contaminated borings in this area consisted of borings 38, 43, 49, 50 and 51.
These included borings 3, 6, 10, 16, 23 and 38.
Specifically, boring 3 revealed TPH content of 18,720 parts per million, boring 16 revealed TPH content of 2880 parts per million, and boring 23 revealed TPH content of 5300 parts per million. The proposed state action level is 200 parts per million.
On the basis of the December, 1994 survey, HRP originally estimated the remediation cost to be $270,000, which included certain costs for processed stone and asphalt that would upgrade the pavement in the fenced area. The plaintiff conceded that it is not entitled to the upgrade and, thus, reduced the estimate by $15,700 to $254,300.
Specifically, the trial court found in relevant part: “The court holds that the defendant cannot be held responsible for any contamination made on the assumptions and estimates of HRP in its November, 1990 and 1991 reports. These assumptions and estimates based on limited data and without further testing were merely speculative.
“The court further holds that the defendant cannot be held responsible for any contamination which was discovered in December, 1994. The purchase and sale agreement specifically provides that the indemnity set forth therein shall survive (lie closing for a period of five years only. The court interprets this to mean that the seller can only be held responsible for contamination that was actually discovered within the five year period. While certain contamination was discovered within the five year- period, 1370 cubic yards of that soil had been removed and the court finds that the defendant is liable for the costs of that removal. The amount of further contamination expected to be found (prior to the expiration of the five year indemnity period) was based on assumptions, estimates, and speculation, and the plaintiff failed to prove what the amount of that contamination was. The amount of additional contamination actually discovered in December, 1994, was discovered after the five year indemnity period had expired.
“The court, holds that the defendant can only be responsible for the costs of remediation performed prior to December, 1988. . . .’’(Emphasis in original.)
The parties do not dispute the existence of the metal shavings. The only dispute is in regard to the characterization of those shavings.
See footnote 9.
The defendant’s expert testified at trial that the metal shavings were not waste at all because the defendant recovered and recycled the shavings as part of its manufacturing program. The expert immediately contradicted his own testimony, however, by admitting that because they had been discarded, the shavings satisfied the definition of “waste.” Finally, the defendant concedes in its reply brief that the metal shavings are a solid waste.
General Statutes (Rev. to 1987) § 22a-207 (3) defines “solid waste” as “unwanted or discarded materials, including solid, liquid, semisolid or contained gaseous material.”
General Statutes (Rev. to 1987) § 22a-115 (1) provides: “ ‘Hazardous waste’ means any waste material, except by-product material, source material or special nuclear material, as defined in section 22a-151, which may pose a present or potential hazard to human health or the environment when improperly disposed of, treated, stored, transported, or otherwise managed, including (A) hazardous waste identified in accordance with Section 3001 of the Federal Resource Conservation and Recovery Act of 1976 (42 U.S.C. [§] 6901 et seq.), (B) hazardous waste identified by regulation by the department of environmental protection and (C) polychlorinated biphenyls in concentrations greater than fifty parts per million.”
General Statutes (Rev. to 1987) § 22a-448 (3) provides: “ ‘Hazardous waste’ means any waste material which may pose a present or potential hazard to human health or the environment when improperly treated, stored, transported or disposed of or otherwise managed including hazardous waste identified in accordance with Section 3001 of the Resource Conservation and Recovery Act of 1976 (42 U.S.C. [§] 6901 et seq.).”
For purposes of 42 U.S.C. § 9601 et seq., hazardous substances are classified as either listed or unlisted. Listed hazardous substances appear in 40 C.F.R. § 302.4 (1988). Unlisted hazardous substances are those solid wastes, as defined by 40 C.F.R. § 261.2 (1988), which are not excluded from regulation as a hazardous waste under 40 C.F.R. § 261.4 (b) (1988) and which exhibit the characteristics identified in 40 C.F.R. §§ 261.20 through 261.24 (1988). The characteristics of hazardous waste are ignitability (40 C.F.R. § 261.21 [1988]), corrosivity (40 C.F.R. § 261.22 [1988]), reactivity (40 C.F.R. § 261.23 [1988]), and toxicity (40 C.F.R. § 261.24 [1988]).
Public Act No. 85-443, § 1, codified at General Statutes (Rev. to 1987) § 22a-452c, defines “spill” as “the discharge, spillage, uncontrolled loss, seepage or filtration of oil or petroleum or chemical liquids or solid, liquid or gaseous products or hazardous waste.”
The dictionary defines ‘contaminant’ as ‘something that contaminates,’ and it defines ‘contaminate’ as ‘to soil, stain, corrupt, or infect by contact or association’ or ‘to render unfit for use by the introduction of unwholesome or undesirable elements.’ Webster’s Third New International Dictionary (1986).” Heyman Associates No. 1 v. Ins. Co. of Pennsylvania, 231 Conn. 756, 772, 653 A.2d 122 (1995).
See footnote 4.
In addition, the defendant claims that the costs associated with the repaving were only an estimate and had not been “actually incurred” at the time of trial. The defendant argues that because the indemnity provision covers only those costs “actually incurred,” the defendant should not be held liable for the paving costs. We disagree. See part III of this opinion. In the alternative, the defendant argues that it should not be held liable for any pavement upgrades and that it should be credited for the discount negotiated by the plaintiff.
The invoice also included separate charges of $711.99 and $4724.38 for HEP and two separate charges of $270.90 each for American Masons. The parties do not dispute these charges.
Specifically, the plaintiff argues that: (1) paragraph 15 (k) should be interpreted as separate warranty and indemnity provisions; and (2) even if
Additionally, we note that the plaintiff filed its complaint, alleging breach of indemnity, well within the five year indemnity period.
We further note that even the defendant’s expert characterized the December, 1994 investigation as “thorough” and “comprehensive.”
In light of our resolution of this issue, we need not address the plaintiffs fourth claim on appeal that, because the defendant failed to raise the issue of timeliness as a special defense, the trial court improperly considered the defendant’s claim that the expiration of the five year indemnity period set forth in the agreement barred certain of the plaintiffs claimed damages. Additionally, we need not address the plaintiffs arguments, raised separately, regarding its claims of negligent and fraudulent misrepresentation.
Given the defendant’s position that paragraph 15 (k) is a unified provision, the plaintiffs breach of warranty claim encompasses the remedies available under the indemnity language of that paragraph, including attorney’s fees and costs.