21st Mtge. Corp. v Balliraj21st Mtge. Corp. v Balliraj
Daniel E. Bertolino, P.C., Upper Nyack, NY (Jonathan B. Schloss of counsel), for respondents.
In an action to foreclose a mortgage, the plaintiff appeals from an order of the Supreme Court, Rockland County (Victor J. Alfieri, Jr., J.), dated November 7, 2016. The order granted the motion of the defendants Ramjit Balliraj and Nirmala Balliraj pursuant to
Ordered that the order is affirmed, with costs.
In February 2015, the plaintiff commenced this action to foreclose a mortgage encumbering certain real property located in Pearl River. The defendants Ramjit Balliraj and Nirmala Balliraj (hereinafter together the defendants) moved pursuant to
“A defendant who seeks dismissal of a complaint pursuant to
“As a general matter, an action to foreclose a mortgage may be brought to recover unpaid sums which were due within the six-year period immediately preceding . . . the action” (Wells Fargo Bank, N.A. v Burke, 94 AD3d 980, 982 [2012]; see
Where a mortgage is payable in installments, the note and mortgage may contain an acceleration provision that gives the lender “the option to demand due the entire balance of principal and interest upon the occurrence of certain events delineated in the mortgage” (1 Bergman on New York Mortgage Foreclosures § 4.02 [2018]; see Wells Fargo Bank, N.A. v Burke, 94 AD3d at 982-983). Where the terms of the note and mortgage provide that “the acceleration of the maturity of a mortgage debt on default is made optional with the holder of the note and mortgage, some affirmative action must be taken evidencing the holder‘s election to take advantage of the accelerating provision, and until such action has been taken the provision has no operation” (Wells Fargo Bank, N.A. v Burke, 94 AD3d at 982-983; see Bank of N.Y. Mellon v Dieudonne, 171 AD3d at 37; Esther M. Mertz Trust v Fox Meadow Partners, 288 AD2d 338, 340 [2001]; see also 1 Bergman on New York Mortgage Foreclosures §§ 4.05, 5.11 [2] [2018]; cf. Phoenix Acquisition Corp. v Campcore, Inc., 81 NY2d 138, 142-144 [1993]).
The acceleration of a mortgage debt may occur when the holder of the note “commences an action to foreclose upon [the] note and mortgage and seeks, in the complaint, payment of the full balance due” (Milone v US Bank N.A., 164 AD3d 145, 152 [2018]). Once the holder of the note and mortgage has exercised its contractual option to accelerate the mortgage debt in accordance with the terms of the note and mortgage, “the entire amount is due and the Statute of Limitations begins to run on the entire debt” (EMC Mtge. Corp. v Patella, 279 AD2d 604, 605 [2001]; see Bank of N.Y. Mellon v Dieudonne, 171 AD3d at 37-38; Nationstar Mtge., LLC v Weisblum, 143 AD3d at 867; Wells Fargo Bank, N.A. v Burke, 94 AD3d at 982). However, “[w]here . . . the prior action [was] dismissed on the ground that the plaintiff lacked standing, the purported acceleration is a nullity, and the statute of limitations does not begin to run at the time of the purported acceleration” (U.S. Bank N.A. v Auguste, 173 AD3d 930, 932 [2019]; see Wells Fargo Bank, N.A. v Burke, 94 AD3d at 983; EMC Mtge. Corp. v Suarez, 49 AD3d 592, 593 [2008]).
Here, the defendants demonstrated that the plaintiff‘s predecessor in interest validly elected to accelerate the mortgage debt in 2006 by commencing a prior foreclosure action against them in which the predecessor in interest sought payment of the full balance due (see Deutsche Bank Natl. Trust Co. v Adrian, 157 AD3d 934, 935 [2018]; U.S. Bank N.A. v Martin, 144 AD3d 891, 892 [2016]). Since the defendants demonstrated, as a matter of law, that the acceleration of the mortgage debt occurred more than six years prior to the commencement of the present action, the defendants sustained their initial burden of demonstrating, prima facie, that the action was untimely. In opposition, the plaintiff failed to raise a question of fact.
The plaintiff‘s remaining contention is not properly before this Court and, in any event, without merit (see Bank of N.Y. Mellon v Dieudonne, 171 AD3d at 39-40).
Accordingly, we agree with the Supreme Court‘s determination to grant the defendants’ motion pursuant to