34 Fed. Cl. 105 | Fed. Cl. | 1995
OPINION
This pre-award protest is before the court on plaintiff and intervenor’s motion to enjoin cancellation of the Solicitation for Offers. Plaintiff, 126 Northpoint Plaza Limited Partnership, and intervenor, Q-Ratio Texas, Inc., request the court enjoin cancellation by defendant, the General Services Administration (GSA) on behalf of the United States, of Solicitation For Offer MTX 93415 (SFO).
Based on testimony obtained at the hearing, oral argument, and the pleadings, this court concludes that the contracting officer abused his discretion in cancelling this SFO. Therefore, cancellation is enjoined and plaintiff and intervenor should be given the opportunity to comply with the agency's current modified requirements.
Factual Background
The SFO was issued on October 18, 1993, soliciting offers for the lease of a single use building in Houston, Texas. The building would serve as a facility for the United States Immigration and Naturalization Service (INS). A total of 21 initial responses were received. Of those buildings, only plaintiff was eventually deemed responsive to INS’ needs. Defendant was concerned that it only had one building to consider; and, in July of 1994, GSA discovered that there were other buildings in the Houston area that could meet the requirements of the SFO. GSA conducted a market survey of the buildings and decided to solicit them. In accordance with GSA’s regulation entitled, “Late Submissions, Modifications, and Withdrawals of Offers,” codified at 48 C.F.R. § 552.270-3, GSA decided to evaluate the new offerors’ buildings. Between July and September 1994, defendant conducted negotiations with the new offerors and continued negotiations with plaintiff.
As of September 21,1994, GSA determined that negotiations were complete with respect to all relevant parties and solicited best and final offers (BAFOs). After evaluating the criteria, GSA forwarded a proposed lease to the intervenor stating, “[t]his proposed lease does not constitute an award.” Thereafter, plaintiff filed a complaint in this court setting out its grounds for a pre-award protest. GSA never signed the lease with intervenor, and instead, determined to cancel the SFO. On April 7,1995, the contracting officer (CO) issued findings and determinations concluding that INS’s requirements had changed substantially due to operational needs, and that upon resolicitation, the potential for enhanced competition and better pricing existed. On April 10, 1995, GSA formally can-celled the solicitation.
Discussion
I. Jurisdiction
This court and its predecessor, the Court of Claims, have long exercised jurisdiction over suits by disappointed bidders for alleged breach of an implied contract to consider bids fairly and honestly. Keco Indus., Inc. v. United States, 192 Ct.Cl. 773, 428 F.2d 1233 (1970); Coastal Corp. v. United States, 6 Cl.Ct. 337 (1984). Successful plaintiffs in these actions were once limited to recovery of bid preparation costs. Morgan Business Assocs., Inc. v. United States, 223 Ct.Cl. 325, 619 F.2d 892 (1980). In 1982, Congress enhanced this court’s remedial powers with respect to such actions by enacting 28 U.S.C. § 1491(a)(3), which provides in pertinent part:
To afford complete relief on any contract claim brought before the contract is*107 awarded, the court shall have exclusive jurisdiction to grant declaratory judgments and such equitable relief as it deems proper, including but not limited to injunctive relief.
The Court of Appeals for the Federal Circuit has held that the equitable jurisdiction of this court includes the power to direct reinstatement of a solicitation, provided the suit requesting this remedy was filed prior to contract award. National Forge Co. v. United States, 779 F.2d 665, 667 (Fed.Cir.1985); see also United States v. John C. Grimberg Co., 702 F.2d 1362, 1372 (Fed.Cir.1983) (the court’s equitable powers under 28 U.S.C. § 1491(a)(3) “can be invoked only by filing a claim with the court before a contract is awarded”). Here, the solicitation had not been awarded as a contract at the time plaintiff filed this action.
II. Standard of Review
Plaintiff and intervenor carry a substantial burden of proof concerning the nature of the contracting officials’ actions. Review is limited because contracting officials “may properly exercise wide discretion in their evaluation of bids and in their application of procurement regulations.” CACI Field Servs., Inc. v. United States, 13 Cl.Ct. 718, 725 (1987), aff'd, 854 F.2d 464 (Fed.Cir. 1988); Electro-Methods, Inc. v. United States, 7 Cl.Ct. 755, 762 (1985). Indeed, a contractor is never assured that it will receive an award and the government retains discretion to reject all bids without liability, even after there have been extensive negotiations with a bidder. American Gen. Leasing, Inc. and Infodyne Systems Corp. v. United States, 218 Ct.Cl. 367, 374, 587 F.2d 54, 58 (1978).
The parties must show, by clear and convincing evidence, that either: (1) the government officials involved in the procurement process lacked a rational or reasonable basis for their cancellation decision; or (2) the procurement procedure involved a clear and prejudicial violation of applicable statutes and regulations. CACI Field Servs., Inc., 13 Cl.Ct. at 725; Aviation Enters., Inc. v. United States, 8 Cl.Ct. 1, 15 (1985); Kinetic Structures Corp. v. United States, 6 Cl.Ct. 387, 394 (1984). With respect to “clear and prejudicial violation of applicable statutes or regulations,” DeMat Air, Inc. v. United States, 2 Cl.Ct. 197, 202 (1983), plaintiff must do more than raise an issue concerning a violation of any law or regulation. The violation in question must be one that denied impartial consideration to which the parties were entitled under the implied contractual obligations of the government. CACI Field Servs., 13 Cl.Ct. at 726.
Finally, in applying the above legal standards, it is significant “that the procurement in this case was conducted in the context of negotiation rather than by formally advertised bidding.” Burroughs Corp. v. United States, 223 Ct.Cl. 53, 65, 617 F.2d 590, 598 (1980). In negotiated procurements, contracting officials possess “broad discretion in the process of obtaining the contract most beneficial to. the government.” CACI Field Servs., 13 Cl.Ct. at 726; Hayes Int’l Corp. v. United States, 7 Cl.Ct. 681, 685 (1985). “In formally advertised bidding the pertinent statutes and regulations are far more strict about the conduct of the procurement than [they are] in a negotiated one[;] consequently in negotiated procurement the contracting officer is entrusted with a relatively high degree of discretion____” Burroughs Corp., 223 Ct.Cl. at 65, 617 F.2d at 598.
III. Final Determination
A. Substantial Changes
In defendant’s final determination, the CO reasoned that substantial changes in INS’ needs warranted cancellation. Moreover, he concluded that cancellation would lead to improved competition and better pric
In the middle of October 1994, GSA was seriously considering two offerors, plaintiff and intervenor. As a matter of fact, interve-nor was issued an initial lease to sign. Around that time, Mr. Kelley received a call from INS voicing concern over the distance from the intervenor’s building to the remote parking lot. Officials from GSA and INS met on October 31, 1994, to discuss issues. The meeting dealt with questions about the number of parking spaces, distance of the parking lot to the building, and the sally-port’s ability to offer protection and security. After this meeting, Mr. Kelley testified that he sat down with the offerors to determine if their buddings could accommodate the agency’s concern. The offerors presented Mr. Kelley with solutions to the agency’s needs. The court is convinced that Mr. Kelley did not believe that these problems were so significant as to warrant cancellation.
On November 28, 1994, however, Mr. Kelley requested a new SF-81 from INS. Nevertheless, he testified that at that time he was still considering amending the current solicitation rather than cancelling and resoli-citing.
B. Duty to consider bids fairly and honestly
Initially, Mr. Kelley testified that, “the biggest reason [for cancelling the solicitation] was the change in square footage.”
Mr. Wallis was also anxious about the number of parking spaces that would be available. Currently the office which INS inhabits has a terrible problem with inadequate parking, both for customers and employees. The court finds significant the fact that INS had a history of problems with parking before the original SFO was issued. Both parties presented evidence that INS has experienced continual problems accommodating their parking requirements. Nevertheless, the “change” in parking has nothing to do with the number of spaces but rather the location of the lot. Oddly, remote parking lot was not questioned until mid-October 1994. INS objected that the parking lot was more than Vs of a mile from intervenor’s building. Thereafter, Mr. Kelley requested verification from the offeror and was satisfied that the parking lot, in terms of travel distance, met the solicitation’s requirement.
Intervenor’s expert, Mr. Wyatt, a real estate specialist in the Houston market, was involved with the SFO from the very beginning. He testified to the continued tirade of problems that began only after INS inspected the Q-ratio building. Specifically, Mr. Wyatt stated, “[i]t seemed like every couple of days, they’d bring up another objection to the building that we would jump through hoops to overcome. They talked about the fact that ... ‘your remote parking lot is down the street; the bus stop is around the corner ... we do not want our visitors walking down the street to and from the building. That’s an unsafe situation.’ We told them we would try to get sidewalks installed to and from those areas. And their response was basically, ‘you’re not going to be able to get that done.’”
Another change involved the sallyport, an enclosed area where criminal detainees could be loaded and unloaded. Ingress and egress from that area also became an issue after INS officials visited intervenor’s building. Evidently Mr. Kelley did not take this issue seriously. Various people, including Mr. Kelley himself, testified to his lukewarm reaction to Mr. Wallis and other INS officials’ distress over the sallyport. In polite terms, Mr. Kelley believed that their concern was foolish. Further, he candidly stated that the sallyport is a temporary structure, which can easily be constructed and taken down. In Mr. Kelley’s own words, “the sallyport is ... nothing more than chain length fence and some barbed wire.”
The court finds that the cancellation occurred as a result of INS’ intent to avoid a contract with a particular building. The CO attempted to work with the agency and amended the solicitation five times to accom
Q: ... you were aware that INS was attempting to knock out the Q-Ratio building, is that correct?
A: ... that’s correct.
Q: ... you or Ms. Berman advised INS officials that course of conduct would invite a protest from my client, is that not correct?
A: That’s correct.
Q: And that they had to elevate their concerns to operational issues, rather than trying to go after a particular buildings [sic]; is that correct?
A: That is correct.
Thereafter, INS formulated its objective needs with an intent to disqualify a particular bidder. The alleged “operational changes” were merely excuses for an alternative agenda.
Defendant’s second reason for cancelling the procurement, an increase in competition, is even less credible. Plaintiff and interve-nor’s experts successfully convinced the court that the availability of other buildings in the Houston market was minimal. Despite his reasoning that cancellation would enhance competition, Mr. Kelley testified that the vacancy rate in the Houston market had decreased, and there would be fewer buildings available in this area today than there had been in 1993. Mr. Travell questioned Mr. Kelley:
Q: You testified ... that you believed the vacancy rates have gone down in the Houston market?
A: Decreased, yes.
Q: ... Which would mean that there
would be less space available for INS? A: Yes.
Thus, the potential for competition had also decreased. Moreover, at the time of cancellation, Mr. Kelley had in mind to solicit only two buildings. The court is confused how two buildings would qualify as an increase in competition. Nevertheless, even these two buildings could not conform to the agency’s current requirements, and defendant had to be aware of this reality. Of the two buildings considered one has sold and currently operates, by the buyer, as a retail store. That sale occurred in March of 1995, one month before the cancellation.
Finady, defendant did not convince the court that, under its own guidelines, a budd to suit was possible. Mr. Kedey testified that the agency is discouraged from “doing budd to suits when there is a[n] adequate supply ... of vacant space in the market of existing buddings.”
Mr. Kedey, however, also testified that, “[bjufld to suits primarily come into play ... if the requirements [for the budding] are so different----”
In Heyer Prods. Co. v. United States, 147 Ct.Cl. 256, 177 F.Supp. 251 (Ct.Cl.1959), the Court of Claims established a governmental duty to conduct fair procurements. The court reasoned that by sodciting for bids, the government impdedly promises to give honest and fair consideration to ad bids. Id. The legal question before the court is whether the government met its impded contractual obdgation to consider fairly and honestly ad responsive bids. Prineville Sawmill Co. v. United States, 859 F.2d 905 (Fed.Cir.1988). The overwhelming evidence presented to the court indicates that the government did not meet its obdgation. It is evident that INS was unhappy with a particular budding. In fact, INS openly and fervently campaigned to rid itself of intervenor’s budding. They were admonished and, fearing a bid protest, GSA directed INS to revise their subjective objections.
The court is surprised how remarkably simdar the instant protest is to one recently decided by another judge on this court and affirmed by the Court of Appeals for the Federal Circuit. In Parcel 49 Ltd. Partnership v. United States, the trial court found that the contracting officer’s primary stated reason for eancedation, a change in space requirements, was merely a pretense for accommodating the agency’s (FCC) displeasure with the selection of Parcel 49C. Parcel 49 Ltd. Partnership v. United States, Slip op. 92-286 (Fed.Cl. Mar. 14,1994). Additionady, the court found that contributing factors, raised at trial, for the eancedation were not credible justifications. The Federal Circuit agreed with the trial court’s determination that the “FCC intended to take whatever steps were necessary to avoid [contracting with Parcel 49C].” Parcel 49C Ltd. Partnership v. United States, 31 F.3d 1147, 1151. In affirming the trial court’s decision, the Court of Appeals for the Federal Circuit states: “[a]s our prior decisions have impdcitly recognized, the government’s duty to treat a bid honestly and fairly runs first of ad to the enterprise submitting that bid.” Id. (citations omitted).
Analogous to Parcel 49 Ltd. Partnership v. United States, GSA, in this procurement, had no rational basis for eancedation. “The law of procurement does not tolerate ‘actions reflecting personal preddeetions of administrative officials, whether aseribable to whim, misplaced zeal, or impermissible influence.’ ” Parcel 49 Ltd. Partnership v. United States
Conclusion
Plaintiff and intervenor request injunctive relief to remedy GSA’s improper action. The court is satisfied that plaintiff and intervenor have demonstrated through clear and convincing evidence that the government’s decision to cancel this award lacked a rational or reasonable basis. The balance of equities are in favor of plaintiff and intervenor; moreover, the public interest is served by this type of injunctive relief. Resolicitation would only result in further, unnecessary expenditures of government resources. It would also reward the illegality, “accomplishing nothing more than a stem finger wagging in the direction of [INS] and GSA.” Parcel 49C Ltd. Partnership v. United States, 31 F.3d 1147, 1154. The government has shown no likelihood of material harm to its interests from an injunction. Imposition of an injunction is consistent with this court’s limited role and will also remove the taint of illegality from this procurement without interfering with defendant’s discretion to select its own contractors. The injunction does not direct the contract award to a particular bidder, but simply restores the status quo before the illegal cancellation. The government retains the power to proceed with its award process that can accommodate INS’ present needs.
In sum, plaintiff and intervenor must still undergo the approval process. The court is also persuaded to grant this relief based on the parties’ representations. Specifically, the court questioned plaintiff and intervenor how they intended to work it out between them if the court does enjoin this cancellation. Both parties responded that they would get it done.
The Clerk is directed to enter judgment in accordance with this opinion. No costs.
. In order to secure reinstatement of the can-celled solicitation, the parties must first demonstrate that they have standing to request such relief. Only those bidders who were “within the zone of active consideration” at the time a solicitation was cancelled have standing to challenge the cancellation. See Morgan Business Assocs., Inc. v. United States, 223 Ct.Cl. 325, 332, 619 F.2d 892, 896 (1980); Vulcan Eng'g Co. v. United States, 16 Cl.Ct. 84, 88 (1988). On April 10, 1995, the date of cancellation, both parties were within the zone of active consideration and thus have standing to challenge the cancellation.
. Tr. at 513 (16-23).
. Tr. at 524 (9-10).
. When the solicitation was actually issued to bidders, however, the square footage requirement had been raised to approximately 70,000 square feet. Therefore, the change in square footage, between the solicitation which was actually issued and the new SF-81, is approximately 5%.
. Tr. at 527(12-16).
. Tr. at 500 (2-8).
. See Tr. at 296 (3-6). GSA, the agency actually charged with awarding the contract, was not so concerned. When questioned how GSA measures whether something meets the 2/10 of a mile requirement, Mr. Kelley responded:
Basically, when we use the terminology, as we did here, it would be as a crow flies, string in a pin. We say 2/10 of a mile, we do 2/10 of a mile on a map. And as long as the points between the property and whatever the thing is that we're looking for fall within that, it would just be the points. That would be satisfactory to us.
. Tr. at 462 (14-25)
. Tr. at 554 (9-13).
. Discovery Documents at 5.
. Supplemental Administrative Record at 63.
. Tr. at 581(9-16), 582(1-9).
. Tr. at 592(1-21).
. Using this building as an example of a potential offeror in the Houston area is disingenuous. When this building was originally considered, and rejected, by GSA, Ms. Linda Perry prepared the pricing memorandum for the site. It states:
[t]his building is a two story building with no windows. Windows would have to be installed in numerous areas. The parking situation is questionable. Currently only 397 spaces are available ... This building is basically land-marked, and the required additional parking would require the effort to buy parking from other retail establishments that sunround this building. The agency was concerned ... about security with this building: access in and out of the building is limited to this location, being prime retail, and a major mall is directly across he street.
See Tab 12 Administrative Record. This building could not, even arguably, accommodate the agency’s stated needs.
. Tr. 395(14-18).
. See Tr. at 541 (3-250).
. Tr. 395 (1-7).
. Tr. at 597(16-23)
. Tr. at 643 (8-25); 644 at (1-25); 645 at (1-9).