History
  • No items yet
midpage
Zafer Taahhut Insaat Ve Ticaret A.S. v. United States
2016 U.S. App. LEXIS 15077
| Fed. Cir. | 2016
Read the full case

Background

  • Zafer, a Turkish construction contractor, entered a firm-fixed-price contract with USACE in May 2011 to deliver materials and build a facility at Bagram; contractor bore delivery risk and contract incorporated FAR Changes and Default clauses.
  • USACE postponed site availability and issued a bilateral modification extending completion to Oct. 2013.
  • In Nov. 2011 Pakistan closed the Karachi–Afghanistan land route after a U.S./NATO incident; the route was closed ~219 days (reopened July 2012), and many of Zafer’s shipments were held in Karachi.
  • Zafer repeatedly notified USACE (Mar., July, Oct. 2012) of delays and sought direction, additional time, and compensation for increased shipping/storage costs; USACE told Zafer to deliver materials “by whatever means necessary,” suggested Zafer request a non‑compensable time extension, and requested documentary proof.
  • Zafer submitted an equitable adjustment and a certified claim; contracting officer denied it, finding no constructive change and concluding Zafer had made a business decision to ship through Karachi. Zafer sued in the Court of Federal Claims; that court granted summary judgment for USACE and denied Zafer’s motion to supplement the record with news/social‑media items.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Constructive acceleration (constructive change) Zafer says USACE’s “by whatever means necessary” and insistence on performance despite excusable delay amounted to constructive acceleration requiring equitable adjustment USACE says contract never mandated Karachi route; it only enforced express contract obligations and did not deny a time‑extension request Court held Zafer failed to prove an essential Fraser element—USACE did not deny a timely, sufficient extension request; summary judgment for USACE affirmed
Government fault theory for delay (sovereign acts exception) Zafer argues U.S./NATO action caused closure and U.S. negotiation with Pakistan prolonged closure, making the U.S. at fault USACE argues Pakistan (a foreign sovereign) closed the route and U.S. acts were not aimed at nullifying contract rights; sovereign‑acts defense applies Court held no evidence U.S. acted to nullify contract rights; sovereign‑acts defense bars Zafer’s claim
Sufficiency of Zafer’s requests for relief (procedural sufficiency) Zafer contends its notices and certified claim sufficed to preserve rights to time and cost relief USACE contends Zafer never requested a specific extension or provided required documentation Court found Zafer failed to request a specific time extension or supply required documentation; correspondence showed an ongoing dialogue, not a denial
Admissibility of news and social‑media articles proffered by Zafer Zafer sought to supplement the record with news/social media to show route was contemplated and U.S. negotiating culpability USACE argued the materials were hearsay and barred by parol evidence rule Court of Federal Claims did not abuse discretion in excluding them as hearsay and barred by parol evidence rule; decision affirmed

Key Cases Cited

  • Fraser Constr. Co. v. United States, 384 F.3d 1354 (2004) (sets five‑element test for constructive acceleration claim)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (1986) (summary judgment proper when nonmoving party lacks proof of an essential element)
  • Conner Bros. Constr. Co. v. Geren, 550 F.3d 1368 (2008) (explains sovereign‑acts defense and exception for acts directed to nullifying contract rights)
Read the full case

Case Details

Case Name: Zafer Taahhut Insaat Ve Ticaret A.S. v. United States
Court Name: Court of Appeals for the Federal Circuit
Date Published: Aug 17, 2016
Citation: 2016 U.S. App. LEXIS 15077
Docket Number: 2015-5083
Court Abbreviation: Fed. Cir.