History
  • No items yet
midpage
Won Suk Lee v. Holyfield Construction, Inc.
93 So. 3d 868
La. Ct. App.
2012
Read the full case

Background

  • Lees contracted December 2005 with Holyfield to build a customized 5,484 sq ft (7,600 sq ft under roof) house in West Monroe for about $1.13 million, with completion planned for November 30, 2006.
  • Final contract price rose to about $1.3 million due to numerous change orders; delay attributed to unusually wet weather by Holyfield.
  • Lees moved in April 4, 2007; soon noticed musty odor and mold; 44-item punch list developed after inspections by engineers and inspectors.
  • Lees vacated the home September 14, 2007; NHWA claim filed November 2007; Holyfield conceded some defects but offered repairs.
  • Trial in November 2010; experts differed on repair costs; Lees claimed $525,000+; Holyfield estimated $47,500; jury found 250,000 in repair/replacement under NHWA, net of a balance, and denied delay damages.
  • District court later awarded post-trial expert fees and costs; one evidentiary ruling excluded late-brick removal testimony; appeal challenged this ruling and delay damages.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
admissibility of late-brick removal evidence Lees contend removal of bricks revealed new defects; timing justified to locate cause. Holyfield argues late disclosure and risk of trial by ambush; ruling valid under 403 and discretionary review. No abuse of discretion; exclusion affirmed.
entitlement to delay damages under NHWA Lees assert 125-day delay warrants damages; change orders and weather excuses delay; adds interest. Holyfield asserts no proven damages for delay; jury could view progress impeded by Lees’s involvement and weather; delay damages denied is not clearly wrong. Judgment affirming no delay damages upheld.

Key Cases Cited

  • Medine v. Roniger, 879 So.2d 706 (La. 2004) (trial court wide discretion on evidentiary rulings; substantial rights test)
  • Hays v. Christus Schumpert, 72 So.3d 955 (La.App. 2 Cir. 2011) (no reversal for evidentiary error without substantial impact)
  • Cosman v. Cabrera, 28 So.3d 1075 (La.App. 1 Cir. 2009) (damages for delay and undue hardship; standards for reviewing delay damages)
  • Davis v. Tillman, 370 So.2d 1323 (La.App. 2 Cir. 1979) (excessive rainfall as excuse for delay in performance)
  • King Bros. Bldg. Contractors v. McCullen, 393 So.2d 413 (La.App. 1 Cir. 1980) (change orders can excuse delay)
  • Thorn v. Caskey, 745 So.2d 653 (La.App. 2 Cir. 1999) (limited liability NHWA context; completion status pertinent to liability)
Read the full case

Case Details

Case Name: Won Suk Lee v. Holyfield Construction, Inc.
Court Name: Louisiana Court of Appeal
Date Published: Jun 20, 2012
Citation: 93 So. 3d 868
Docket Number: No. 47,204-CA
Court Abbreviation: La. Ct. App.