69 F.4th 365
6th Cir.2023Background:
- PHMSA inspected Wolverine's hazardous-liquid pipeline records and issued a Notice of Probable Violation alleging two regulatory breaches under 49 C.F.R. § 195.452: an immediate-repair/pressure-reduction violation (Item 5) and missed 180-day repair deadlines (Item 6).
- For Item 5: an ILI report identifying a topside dent with metal loss was emailed June 10, 2015; Wolverine’s risk specialist did not open the report until June 23, convened a meeting June 26, and completed the repair June 30 without temporarily reducing pressure or shutting down the line.
- PHMSA’s enforcement alleged discovery began on June 10 and recommended a penalty because Wolverine did not document any temporary pressure reduction between June 10 and June 30.
- For Item 6: an ILI report (June 12) listed both R‑STRENG and B31G remaining‑strength calculations; Wolverine used B31G to classify four anomalies as 180‑day conditions and prepared repair plans, but missed the 180‑day deadline at two locations.
- At the agency hearing Wolverine argued (Item 5) discovery was June 26 and the quick repair obviated a pressure reduction, and (Item 6) reliance on R‑STRENG would have shown no 180‑day obligation; PHMSA found violations on both items and assessed a total penalty of $65,800.
- The D.C. Circuit (panel: Nalbandian, Readler; Batchelder dissenting) reviewed under the APA and affirmed PHMSA’s Final Order, rejecting Wolverine’s arbitrary-and-capricious and due-process claims.
Issues:
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether §195.452(h)(4)(i) requires an operator to reduce pressure or shut down pending repair, even if repair can be completed quickly | Wolverine: regulation should not require pressure reduction if operator can repair before a reduction could be effectuated; discovery here was June 26, repair June 30 | PHMSA: text plainly mandates temporary pressure reduction or shutdown pending repair; longstanding agency interpretation applies regardless of repair speed or discovery date | Court: Affirmed PHMSA — regulation requires pressure reduction or shutdown; Wolverine violated it and due‑process/Chenery arguments fail |
| Whether PHMSA arbitrarily enforced 180‑day repair rules when R‑STRENG results (in ILI) would have obviated 180‑day classification | Wolverine: R‑STRENG values in the ILI report showed no 180‑day condition; operator may rely on R‑STRENG and use it as defense | PHMSA: operator documented and relied on B31G in its plans and provided no contemporaneous R‑STRENG calculations at inspection; agency may reject after‑the‑fact methods offered only at hearing | Court: Affirmed PHMSA — operator is bound by the methodology it documented and relied on during inspection; post hoc R‑STRENG analysis cannot defeat enforcement |
Key Cases Cited
- Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (U.S. 1983) (sets deferential arbitrary-and-capricious standard requiring reasoned explanation)
- SEC v. Chenery Corp., 318 U.S. 80 (U.S. 1943) (agency action must rest on grounds actually relied upon by the agency)
- SEC v. Chenery Corp., 332 U.S. 194 (U.S. 1947) (court may not supply post hoc rationalizations for agency decisions)
- Mullane v. Central Hanover Bank & Trust Co., 339 U.S. 306 (U.S. 1950) (due process notice principles for administrative proceedings)
- Yellow Freight Sys., Inc. v. Martin, 954 F.2d 353 (6th Cir. 1992) (agency may not change theories midstream without notice)
- Diebold, Inc. v. Marshall, 585 F.2d 1327 (6th Cir. 1978) (vagueness/fair‑notice doctrine in administrative enforcement)
- ECM BioFilms, Inc. v. FTC, 851 F.3d 599 (6th Cir. 2017) (informal charging documents need not define ambiguous terms in exact detail to provide fair notice)
- Alaska Dep't of Envtl. Conservation v. EPA, 540 U.S. 461 (U.S. 2004) (court may uphold agency action if the agency's path can reasonably be discerned)
