History
  • No items yet
midpage
932 F.3d 861
9th Cir.
2019
Read the full case

Background

  • PURPA requires utilities to purchase all energy a Qualifying Facility (QF) offers (must-take) and to pay an avoided-cost rate, with QFs able to choose avoided cost calculated at contract or delivery. 18 C.F.R. §§ 292.303(a)(1), 292.304(d)(2).
  • California Public Utilities Commission (CPUC) created Re‑MAT: a two‑month auction-like program with a statewide cap (750 MW) allocated among utilities and per‑utility, per‑category two‑month limits (e.g., PG&E capped at 5 MW per category per period).
  • Re‑MAT sets market‑adjusted prices that move every two months based on QFs’ acceptance behavior rather than on utilities’ avoided costs; initial peaking price was $89.23/MWh and adjusted thereafter.
  • CPUC also offered a Standard Contract that purportedly pays avoided‑cost rates via a six‑variable formula, but three variables cannot be determined at contract time, so it does not permit a contract‑time avoided‑cost calculation.
  • Winding Creek Solar participated in Re‑MAT, received lower offers than the initial price, rejected them, challenged the program at FERC, then sued in district court; the district court granted summary judgment for Winding Creek but declined to order a contract at the initial price.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Re‑MAT’s purchase caps violate PURPA must‑take requirement Re‑MAT’s caps allow utilities to decline available QF output, violating 18 C.F.R. § 292.303(a)(1) Re‑MAT is an alternative state program and acceptable if the state provides other PURPA‑compliant options Re‑MAT’s caps violate PURPA and are preempted because they permit utilities to purchase less than QFs offer
Whether Re‑MAT pricing complies with PURPA avoided‑cost requirement Re‑MAT’s market‑adjusted auction price is not tied to a utility’s but‑for avoided costs and thus is noncompliant CPUC contends market rates and state methodologies are permissible; FERC suggested alternatives may be acceptable Re‑MAT pricing is not an avoided‑cost rate under PURPA and therefore violates PURPA
Whether the Standard Contract supplies a PURPA‑compliant alternative Winding Creek: Standard Contract fails to allow avoided‑cost calculation at contract time because key variables are unknowable then CPUC/FERC: Standard Contract provides an avoided‑cost mechanism and thus cures Re‑MAT’s defects Standard Contract is noncompliant because it does not give QFs the option to fix avoided cost at contracting time as required by 18 C.F.R. § 292.304(d)(2)
Appropriate remedy (order for specific contract at initial Re‑MAT price) Winding Creek sought a contract at the initial $89.23/MWh price CPUC/PG&E opposed court‑ordered specific contract and argued equitable relief should be limited Court affirmed district court’s refusal to order a contract at the initial price; courts should not force a nonparty to enter a modified version of a preempted regulatory program

Key Cases Cited

  • Indep. Energy Producers Ass’n, Inc. v. Cal. Pub. Utils. Comm’n, 36 F.3d 848 (9th Cir. 1994) (describing PURPA’s purpose and FERC’s QF framework)
  • La. Pub. Serv. Comm’n v. FCC, 476 U.S. 355 (U.S. 1986) (state regulations conflicting with federal regulations are preempted)
  • Kisor v. Wilkie, 139 S. Ct. 2400 (U.S. 2019) (limits and conditions for deference to agency interpretations of their own rules)
  • Allco Renewable Energy Ltd. v. Mass. Elec. Co., 875 F.3d 64 (1st Cir. 2017) (federal courts are not authorized or well‑suited to set avoided‑cost rates)
  • Husain v. Olympic Airways, 316 F.3d 829 (9th Cir. 2002) (standard of review for bench trial findings)
Read the full case

Case Details

Case Name: Winding Creek Solar LLC v. Carla Peterman
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Jul 29, 2019
Citations: 932 F.3d 861; 17-17531
Docket Number: 17-17531
Court Abbreviation: 9th Cir.
Log In