History
  • No items yet
midpage
403 S.W.3d 660
Mo. Ct. App.
2012
Read the full case

Background

  • Wehr terminated Purchase Order No. 003 for the Kansas Plaza project citing increased construction costs, not Williams' performance, leading Williams to claim breach and seek damages.
  • Williams sought $60,986.25, comprising $35,000 for lost profits and overhead plus $25,986.25 payable to ABC for engineering services, offset by a $14,972 mobilization payment Wehr had already made.
  • Trial evidence showed Williams had completed some engineering work for ABC but could not supply all submittals within three weeks as required; Wehr canceled the order largely due to cost concerns.
  • The trial court found Wehr breached the contract by terminating for convenience and awarded Williams $20,027.97, denying ABC-related damages of $25,986.25.
  • On appeal, the court held Williams established lost profits with reasonable certainty but disallowed $5,000 of fixed overhead because it could not be tied to gross revenue and because labor overhead would have occurred regardless of the profits.
  • The appellate court calculated Williams’ net recovery as $15,028 (lost profits $30,000 minus the $14,972 mobilization previously paid) and remanded for entry of an amended judgment accordingly.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Wehr breached by terminating the purchase order Williams: termination for convenience breached the contract. Wehr: Williams' first breach (incomplete drawings) justified termination. Wehr breach; termination not excused by Williams' noncompliance.
Whether Williams proved lost profits and overhead damages with sufficient certainty Williams: lost profits proven; overhead recoverable. Wehr: overhead unsupported; only lost profits proven. Lost profits proved; overhead $5,000 not supported; net damages reduced.

Key Cases Cited

  • Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976) (standard of review for contract cases; substantial evidence/weight of the evidence)
  • Salem United Methodist Church v. Bottorff, 138 S.W.3d 788 (Mo.App.2004) (presumption of trial court judgment; burden on appellant)
  • Surrey Condominium Ass’n, Inc. v. Webb, 163 S.W.3d 531 (Mo.App.2005) (evidence viewed in light favorable to prevailing party)
  • Essex Contracting, Inc. v. Jefferson County, 277 S.W.3d 647 (Mo. bane 2009) (credibility; Rule 84.13(d) standard)
  • Strobl v. Lane, 250 S.W.3d 843 (Mo.App.2008) (trial court credibility determinations given deference)
  • Classic Kitchens & Interiors v. Johnson, 110 S.W.3d 412 (Mo.App.2003) (material breach and performance standards; deference to trial court)
  • Parshall v. Buetzer, 195 S.W.3d 515 (Mo.App.2006) (testimony of industry experience supports lost profits with reasonable certainty)
  • American Laminates, Inc. v. J.S. Latta Co., 980 S.W.2d 12 (Mo.App.1998) (recovery of fixed overhead if proven by substantial evidence)
  • Scullin Steel Co. v. PAC-CAR, Inc., 748 S.W.2d 910 (Mo.App.1988) (overhead elements related to gross revenue must be evidenced)
  • Birdsong v. Bydalek, 953 S.W.2d 103 (Mo.App.1997) (damages for lost profits; reasonable certainty standard)
  • Catroppa v. Metal Bldg. Supply, Inc., 267 S.W.3d 812 (Mo.App.2008) (lost profits and overhead proof; cannot double-recover profits and overhead)
Read the full case

Case Details

Case Name: Williams Construction, Inc. v. Wehr Construction, L.L.C.
Court Name: Missouri Court of Appeals
Date Published: Nov 8, 2012
Citations: 403 S.W.3d 660; 2012 WL 5451725; 2012 Mo. App. LEXIS 1405; No. SD 31542
Docket Number: No. SD 31542
Court Abbreviation: Mo. Ct. App.
Log In
    Williams Construction, Inc. v. Wehr Construction, L.L.C., 403 S.W.3d 660