History
  • No items yet
midpage
784 S.E.2d 265
Va.
2016
Read the full case

Background

  • Heritage Fellowship contracted Gordon (engineer) in 2006 to design a buried rain-tank stormwater system and to provide optional construction coordination; Gordon’s contract required final county approval for design completion.
  • Gordon signed and sealed initial plans in Jan. 2007; the county gave final approval to the site plan (including the tank) on Aug. 5, 2009.
  • General contractor Whitener & Jackson (W&J) built the specified tank in Apr–May 2011; the tank and overlying parking lot collapsed in Aug. 2011, delaying occupancy and requiring replacement.
  • Heritage sued Gordon (negligent design/oversight) and PSI (inspector); W&J sued Heritage for payment and was counterclaimed; courts consolidated related actions.
  • The trial court found Gordon solely liable for the collapse, awarded W&J remediation costs against Heritage (which the court shifted to Gordon), awarded Heritage additional delay damages (including construction-loan interest), and denied Gordon an offset for Heritage’s $200,000 settlement with PSI. Gordon appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
When negligent-design claim accrues (statute of limitations) Heritage: accrual when county finally approved plans (Aug 5, 2009). Gordon: accrual when engineer signed/sealed initial plans (Jan 2, 2007). Accrual upon final approval by county (Aug 5, 2009); claims timely.
Whether owner–contractor agreement shifted design liability to contractor Heritage: Construction Contract did not shift design liability; W&J followed prescriptive specs. Gordon: Contract placed remediation/design responsibility on W&J. Construction Contract did not transfer design responsibility; evidence showed W&J complied with Gordon’s plans, so Gordon liable for remediation costs.
Whether Gordon breached professional standard of care and proximate cause Heritage: Gordon failed to investigate manufacturer specs/site (high water table), provided ambiguous plans, and ignored RFI—breach proximately caused collapse. Gordon: Proper to rely on manufacturer's literature; contractor errors were causal. Sufficient expert evidence supported breach of design and oversight duties and proximate causation; trial court’s finding upheld.
Effect of PSI settlement on Gordon’s liability/offset Heritage: Settlement solely compensated attorneys’ fees to resolve contract with PSI; no offset against Gordon. Gordon: PSI release covered the same injury and/or entitles Gordon to offset under Code § 8.01‑35.1. Settlement released PSI for collapse damages too; court must determine and allocate the consideration attributable to collapse vs. fees and make appropriate offset on remand.
Recoverability of construction‑loan interest as delay damages Heritage: Extended construction-interest payments during delay are compensable (Roanoke Hospital). Gordon: Loan term was not extended by delay; interest payments would have been paid regardless, so not proximately caused by breach. Award of $569,260.49 construction‑loan interest reversed: where loan term wasn’t extended, those interest payments were not caused by delay and thus not recoverable.

Key Cases Cited

  • Virginia Military Institute v. King, 217 Va. 751 (establishes negligent‑design accrual rule: claim accrues when plans are finally approved)
  • Willard v. Moneta Building Supply, 262 Va. 473 (de novo review of statute‑of‑limitations question)
  • Seaward International, Inc. v. Price Waterhouse, 239 Va. 585 (expert proof required to establish professional standard, breach, and proximate cause)
  • Filak v. George, 267 Va. 612 (elements of breach‑of‑contract claim)
  • Acordia of Virginia Ins. Agency v. Genito Glenn, L.P., 263 Va. 377 (burden and procedure for obtaining credit/offset for co‑defendant settlements)
  • Tazewell Oil Co. v. United Virginia Bank/Crestar Bank, 243 Va. 94 (court must allocate settlement consideration among multiple injuries for § 8.01‑35.1 offsets)
  • Roanoke Hospital Ass’n v. Doyle & Russell, Inc., 215 Va. 796 (extended financing interest is compensable when delay forces extension or renegotiation of construction financing)
  • Cox v. Geary, 271 Va. 141 (discussion of single indivisible injury caused by multiple actors)
Read the full case

Case Details

Case Name: William H. Gordon Assocs., Inc. v. Heritage Fellowship
Court Name: Supreme Court of Virginia
Date Published: Feb 12, 2016
Citations: 784 S.E.2d 265; 291 Va. 122; 2016 Va. LEXIS 11; Record 150279.
Docket Number: Record 150279.
Court Abbreviation: Va.
Log In
    William H. Gordon Assocs., Inc. v. Heritage Fellowship, 784 S.E.2d 265