2026 WY 82
Wyo.2026Background
- Lacher hired Case Concrete/Case Construction to build a wheelchair ramp and covered addition at Lacher's home, but the parties never signed a contract or fixed a written price. 1
- Lacher paid Case $73,000 for the project, including $30,000 for siding, but the project remained unfinished and no siding was installed or delivered. 2
- Green River officials discovered permit and code issues, issued a stop-work notice, and later required engineering compliance before the work could continue. 3
- In discovery, Lacher disclosed only that damages were still being computed and never supplemented with a damages calculation before trial. 4
- Case moved in limine to exclude undisclosed damages evidence, and the district court partially granted the motion, later allowing only previously disclosed evidence. 5
- After a bench trial, the district court found the oral contract unenforceable but, more importantly, found Lacher failed to prove damages by a preponderance of the evidence. 6
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Did Lacher preserve review of the damages evidence ruling? 7 | The motion in limine wrongly barred his damages proof. | No offer of proof was made, so review is waived. | Unpreserved; no meaningful review without an offer of proof. 8 |
| Was the no-damages finding clearly erroneous? 9 | The contract price equaled his damages because the whole project was unusable. | Lacher proved no competent measure of damages or need for total rebuild. | No; the district court's damages finding was not clearly erroneous. 10 |
Key Cases Cited
- Elsner v. Campbell Cnty. Hosp. Dist., 566 P.3d 894 (Wyo. 2025) (motions in limine are committed to the trial court's discretion 11)
- Three Way, Inc. v. Burton Enters., Inc., 177 P.3d 219 (Wyo. 2008) (trial-court discretion governs motions in limine 12)
- Parker v. Cook, 501 P.3d 1253 (Wyo. 2022) (excluded-evidence error requires an offer of proof 13)
- Silva v. State, 271 P.3d 443 (Wyo. 2012) (failure to make an offer of proof waives appellate error 14)
- Legacy Builders, LLC v. Andrews, 335 P.3d 1063 (Wyo. 2014) (construction-contract damages follow Restatement section 348 and plaintiff initially bears the damages burden 15)
- Anderson v. Messinger, 587 P.3d 519 (Wyo. 2026) (clearly erroneous review defers to the trial court's factual findings 16)
- Holloway v. Hidden Creek Outfitters, LLC, 569 P.3d 756 (Wyo. 2025) (damages must be proven with reasonable certainty, not speculation 17)
- Knight v. TCB Const. & Design, LLC, 248 P.3d 178 (Wyo. 2011) (plaintiff bears the burden of producing sufficient proof of damages 18)
- Crouch v. Cooper, 556 P.3d 199 (Wyo. 2024) (defendant's burden to challenge damages arises only after plaintiff proves damages 19)
