History
  • No items yet
midpage
Western Watersheds Project v. Debra Haaland
20-5081
| D.C. Cir. | Jun 18, 2021
Read the full case

Background

  • In 2008 the Bureau of Land Management (BLM) adopted a resource management plan (RMP) for an area of Nevada that directed removal of all wild horses from the area because habitat was insufficient.
  • BLM began implementing the RMP with a roundup in October 2009 and acknowledged multiple gathers likely would be needed to reach the zero-horse goal.
  • Some horses remained after 2009; BLM decided on another roundup in April 2018.
  • Conservation groups sued in June 2018 to stop the 2018 roundup; the district court granted summary judgment to BLM.
  • The D.C. Circuit affirmed, holding plaintiffs’ challenge was time-barred under 28 U.S.C. § 2401(a) because the cause of action accrued in 2009 when BLM first implemented the RMP.
  • The court also rejected plaintiffs’ reopening-doctrine theory and deemed other appellate arguments forfeited for inadequate briefing.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
When did the claim accrue for § 2401(a)? Accrual occurred when later roundups (e.g., 2018) caused injury; suit timely. Accrual began when BLM first implemented the 2008 RMP in 2009. Accrual in 2009; six-year limitations expired in 2015; 2018 suit untimely.
Was the 2008 RMP a final agency action? RMP not final until implementation or later rounds. RMP was final agency action that ended decisionmaking. RMP was final agency action.
Does the reopening doctrine restart the limitations period? Subsequent gathers or BLM statements reopened review, restarting accrual. No serious, substantive reconsideration occurred; reopening inapplicable. Reopening doctrine does not apply.
Were the plaintiffs’ other claims preserved on appeal? Plaintiffs raised other claims below and meant to pursue them. Plaintiffs failed to meaningfully brief them on appeal. Other claims forfeited for inadequate briefing.

Key Cases Cited

  • Hardin v. Jackson, 625 F.3d 739 (D.C. Cir. 2010) (accrual under § 2401(a) occurs on date of final agency action)
  • Federal Express Corp. v. Mineta, 373 F.3d 112 (D.C. Cir. 2004) (limitations clock begins when claim ripens)
  • Norton v. Southern Utah Wilderness Alliance, 542 U.S. 55 (2004) (land-use plans bind agency and inconsistent actions may be set aside)
  • Bennett v. Spear, 520 U.S. 154 (1997) (final agency action when decisionmaking ends and legal consequences flow)
  • Ohio Forestry Ass'n, Inc. v. Sierra Club, 523 U.S. 726 (1998) (claim ripens when agency implements a plan)
  • Alliance for Safe, Efficient & Competitive Truck Transportation v. Federal Motor Carrier Safety Administration, 755 F.3d 946 (D.C. Cir. 2014) (reopening doctrine requires serious substantive reconsideration)
  • Government of Manitoba v. Bernhardt, 923 F.3d 173 (D.C. Cir. 2019) (arguments inadequately briefed on appeal are forfeited)
Read the full case

Case Details

Case Name: Western Watersheds Project v. Debra Haaland
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jun 18, 2021
Docket Number: 20-5081
Court Abbreviation: D.C. Cir.