History
  • No items yet
midpage
23 N.E.3d 682
Ind. Ct. App.
2014
Read the full case

Background

  • On April 28, 2006 an overhead crane ladle at ArcelorMittal unexpectedly descended, tipped and spilled molten iron, causing a fire and extensive property damage. ArcelorMittal traced the event to fractured blowout coils in two dynamic-brake contactors and an unexpected electrical condition in the hoist controller. ArcelorMittal purchased the contactors via WESCO (which obtained them from EPSU).
  • EDT (an engineering consultant retained by ArcelorMittal’s insurer) concluded the event resulted from the fractured blowout coils combined with a loose C5 switch in the controller; initial plant testing and replacement of blowout coils restored normal operation.
  • ArcelorMittal discarded or altered certain controller components soon after the incident (parts from the controller were rebuilt/ thrown away); WESCO sought sanctions for spoliation and an adverse-inference instruction; the trial court denied sanctions and the instruction.
  • Pretrial and trial disputes included admissibility of ArcelorMittal’s experts on causation and product source, discoverability of insurer/adjuster files (work product/attorney-client assertions), exclusion of evidence of subsequent remedial measures (Ind. Evid. R. 407), and the appropriate measure of damages. A 22-day jury trial awarded ArcelorMittal $36,134,477; the trial court added prejudgment interest of ~$3.9M to reach final judgment.
  • WESCO appealed, arguing (inter alia) erroneous denial of summary judgment/directed verdict on causation (expert testimony inadmissible), erroneous refusal to sanction for spoliation, improper admission of product-identification expert testimony, exclusion of subsequent-remedial-measures evidence, discovery rulings, and that prejudgment interest was improper.

Issues

Issue Plaintiff's Argument (ArcelorMittal) Defendant's Argument (WESCO) Held
Admissibility of expert causation opinions / summary judgment EDT experts’ reconstruction and testimony created genuine issues of fact about causation (blowout coils were a substantial factor); experts qualified under Rule 702 Expert causation rested on unsupported assumptions (operator lowered hoist; loose screws) and was therefore inadmissible; summary judgment or directed verdict required Court affirmed: the expert methodology was admissible and, together with non-expert evidence (replicated descent, fractured coils, restoration after replacement), raised fact issues for the jury; judgment-denial proper
Spoliation / sanctions and adverse-inference instruction Destruction/disposal occurred but not with intent to deprive; both sides equally prejudiced because parts were destroyed before inspection; no sanctions warranted Plant personnel intentionally discarded/altered evidence and deprived WESCO of inspection—dismissal or adverse inference appropriate Court affirmed trial court’s discretion to deny sanctions and adverse-inference instruction: no intentional destruction to hinder litigation shown and prejudice was not one-sided
Product identification expert testimony (source of coils) Dr. Jur’s document review and experience with procurement analyses gave him specialized/skill-level knowledge admissible under Rule 702 (or at least Rule 701 skilled-witness testimony) Dr. Jur’s source-opinion was not expert testimony; identification was lay/factual and cumulative—admission unfairly bolstered plaintiff’s case Court affirmed admission: trial court did not abuse discretion; testimony also admissible under Rule 701 and was cumulative of other evidence linking parts to WESCO
Foreseeability / proximate cause (superseding/intervening cause) A defective braking-component used in a crane transporting molten iron could reasonably foreseeably cause significant damage; fractured coils were a substantial factor even if other factors contributed The particular convergence of events was unforeseeable as a matter of law; fracture was not proximate cause Court affirmed: proximate cause and foreseeability were fact questions properly submitted to the jury; fractured coils could be a substantial factor
Exclusion of subsequent remedial measures (policy change; spring return-to-center) Exclusion proper under Ind. Evid. R. 407; evidence was offered to prove culpability, not for permissible purposes Evidence of policy change and reinstallation of safety features was relevant for impeachment/feasibility and to rebut impression that no further incidents occurred Court affirmed exclusion (no abuse): additional evidence was cumulative or inadmissible to prove fault; admissible facts about post-incident changes were otherwise in the record
Prejudgment interest award ArcelorMittal urged interest on claimed repair costs because invoices were stipulated as authentic and repairs were incurred WESCO argued damages required jury judgment and were not readily ascertainable; prejudgment interest therefore improper Court reversed prejudgment interest award: the jury verdict required interpretation and the damages were not a single readily-ascertainable component; prejudgment interest was improper on verdict as a whole

Key Cases Cited

  • Fowler v. Campbell, 612 N.E.2d 596 (Ind. Ct. App. 1993) (elements of breach of contract and substantial-factor causation standard)
  • Lytle v. Ford Motor Co., 814 N.E.2d 301 (Ind. Ct. App. 2004) (expert testimony must be supported by appropriate validation)
  • Armstrong v. Cerestar USA, Inc., 775 N.E.2d 360 (Ind. Ct. App. 2002) (trial court gatekeeper role for expert qualification under Rule 702)
  • Sears Roebuck & Co. v. Manuilov, 742 N.E.2d 453 (Ind. 2001) (once methodology is reliable, weight and credibility are for the jury)
  • Gribben v. Wal–Mart Stores, Inc., 824 N.E.2d 349 (Ind. 2005) (spoliation doctrine and possible consequences; inference available for intentional first-party spoliation)
  • Howard Reg’l Health Sys. v. Gordon, 952 N.E.2d 182 (Ind. 2011) (factors for sanctions for spoliation: culpability and prejudice continuum)
  • Noble Roman’s, Inc. v. Ward, 760 N.E.2d 1132 (Ind. Ct. App. 2002) (prejudgment interest proper where contract damages are ascertainable by simple calculation)
Read the full case

Case Details

Case Name: Wesco Distribution, Inc. v. Arcelormittal Indiana Harbour Llc. and Espu, Inc.
Court Name: Indiana Court of Appeals
Date Published: Nov 10, 2014
Citations: 23 N.E.3d 682; 2014 Ind. App. LEXIS 550; 2014 WL 5819375; 45A03-1307-PL-274
Docket Number: 45A03-1307-PL-274
Court Abbreviation: Ind. Ct. App.
Log In