History
  • No items yet
midpage
Wavelink, Inc v. United States
20-749
| Fed. Cl. | Jul 1, 2021
Read the full case

Background

  • GSA conducted an "on-ramp" procurement under the OASIS SB vehicle (Pools 1, 3, and 4) to add many contractors; offerors submitted proposals (six volumes) by June 28, 2019 using the Symphony self-scoring system.
  • The RFP scored Relevant Experience (4,000), Past Performance (4,000), and Systems/Certifications (2,000); cost/price was reviewed for fairness but not scored.
  • The RFP cautioned that direct labor rates outside specified ranges required a “clear and convincing rationale,” warning failure to provide one would render the offeror ineligible for award.
  • GSA initially excluded several offerors for failing to provide required rationale for low labor rates; those offerors protested to GAO, and GSA then issued corrective action treating rates below the range as not unfair per se and awarded contracts to multiple offerors with out-of-range low rates.
  • WaveLink filed a post-award bid protest claiming (1) GSA should have allowed updates to Relevant Experience/Past Performance during the lengthy evaluation; (2) GSA conducted discussions with some offerors without allowing all to submit FPRs; and (3) GSA violated mandatory solicitation terms by awarding contracts to offerors without the required rate rationales.
  • The Court held WaveLink had standing, rejected most challenges, but found GSA violated the solicitation/FAR by awarding contracts to offerors who failed to provide the required rationale for out-of-range low labor rates and that WaveLink was prejudiced in Pool 3 (not Pool 1). The Court enjoined continuing those Pool 3 awards and ordered remedial options.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether GSA had to allow offerors to update Relevant Experience/Past Performance after a 10-month evaluation delay WaveLink: the long delay rendered submitted experience stale and GSA should have sought updates or allowed FPRs GSA: evaluation schedule and procedure were reasonable; no legal requirement to reopen or update non-past-performance volumes Court: No error — GSA reasonably declined to seek such updates and was not required to solicit refreshed Relevant Experience absent discussions (claim denied)
Whether GSA conducted discussions that triggered FAR's requirement to permit FPRs to all competitive-range offerors WaveLink: clarification exchanges with some offerors amounted to discussions and required FPRs for all GSA: exchanges were limited clarifications, responsibility inquiries, or permitted missing-document requests — not discussions Court: communications were clarifications/responsibility checks; no discussions that required FPRs (claim denied)
Whether GSA violated mandatory solicitation terms by awarding contracts to offerors who proposed direct labor rates below RFP ranges without the required ‘‘clear and convincing rationale’’ WaveLink: RFP language was mandatory; awarding such offers violated FAR 15.305(a) and 15.206(d) and prejudiced WaveLink GSA: it reasonably reinterpreted/implemented corrective action (and later argued differently in related litigation) to treat low rates as not unfair per se Court: RFP language was clear and mandatory; GSA violated the solicitation and FAR by accepting noncompliant offers without amending the RFP, holding discussions, or rejecting them
Whether WaveLink was prejudiced (entitled to relief) and whether injunction/remedy is warranted WaveLink: prejudiced because removing ineligible awardees (or otherwise remedying) would have put WaveLink into award range for Pool 3; seeks injunction and reevaluation GSA: WaveLink is not next in line; any benefit is speculative; remedial options would be burdensome Court: WaveLink showed prejudice in Pool 3 (but not Pool 1); injunction granted limited to Pool 3 with options for GSA to (a) enforce solicitation and cancel ineligible awards, (b) conduct discussions and permit FPRs, or (c) amend solicitation and proceed consistent with FAR

Key Cases Cited

  • EP Prods., Inc. v. United States, 63 Fed. Cl. 220 (Fed. Cl. 2005) (explains mandatory-solicitation provisions promote fair competition in negotiated procurements)
  • Information Tech. & Applications Corp. v. United States, 316 F.3d 1312 (Fed. Cir. 2003) (standing/prejudice analysis where discussions could have improved protester’s chance of award)
  • Alfa Laval Separation, Inc. v. United States, 175 F.3d 1365 (Fed. Cir. 1999) (agency may not award to a bid that fails mandatory solicitation requirements; prejudice can be shown when the only competing bid was unacceptable)
  • DigiFlight, Inc. v. United States, 150 Fed. Cl. 650 (Fed. Cl. 2020) (construing identical OASIS SB solicitation language and holding omission of required rationale could be fatal to eligibility)
  • Centech Grp., Inc. v. United States, 554 F.3d 1029 (Fed. Cir. 2009) (proposal failing to meet RFP requests is unacceptable and cannot form basis for award)
  • Niz-Chavez v. Garland, 141 S. Ct. 1474 (U.S. 2021) (government must comply with clear legal requirements; cited for principle that government must "turn square corners")
Read the full case

Case Details

Case Name: Wavelink, Inc v. United States
Court Name: United States Court of Federal Claims
Date Published: Jul 1, 2021
Docket Number: 20-749
Court Abbreviation: Fed. Cl.