Walsh Construction Co. v. United States
132 Fed. Cl. 282
| Fed. Cl. | 2017Background
- The Army Corps awarded a construction contract (Aug. 17, 2012) requiring 272 drilled piers; Walsh subcontracted the drilling work to Ammero, which subcontracted to Goettle.
- Goettle drilled shafts to CO-specified tip elevations; the Army Corps repeatedly recalculated/revised tip elevations and conducted multiple re-inspections, forcing 471 additional equipment moves and extra costs; to meet schedule Goettle increased equipment and labor.
- During drilling five shafts (the “Five Problem Shafts”) encountered rock/voids/fractures causing collapses and extra remediation costs.
- On Nov. 30, 2015 Walsh (for Goettle) submitted an REA seeking an equitable adjustment (~$8.76M), asserting (1) a differing site condition for the Five Problem Shafts and (2) reimbursement for disruption/delay caused by the Army Corps’ downhole inspections (presented as a differing site condition).
- The CO issued a final decision (Apr. 18, 2016) denying the REA: found the Five Problem Shafts not materially different from contract, and held the inspection program was contract-required (not a differing site condition).
- Plaintiffs sued in the Court of Federal Claims (July 2016; amended Feb. 13, 2017) asserting: Count One — additional costs from delay caused by downhole inspections; Count Two — breach of implied duty of good faith and fair dealing; Count Three — differing site condition for the Five Problem Shafts. The government moved to dismiss Counts One and Two for lack of jurisdiction or to merge counts.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Count One (additional costs from inspections/delay) was presented to the CO so CO decision prerequisite satisfied | The REA put the CO on notice of operative facts (multiple inspections caused equipment moves/delay and costs); CO addressed and denied inspection-related claims, so Count One arises from same operative facts | REA presented only differing site condition theory; plaintiffs are improperly recasting it as a delay/extra-costs claim and thus did not present this distinct theory to the CO | Court: Jurisdiction exists for Count One — it arises from same operative facts presented to the CO; not merged with Count Three |
| Whether Count Two (breach of implied duty of good faith/fair dealing) was presented to the CO | Plaintiffs say REA’s allegations of multiple inspections and resulting costs put the CO on notice of a breach-of-duty claim | Government says REA only sought equitable adjustment under differing site condition clause and did not give CO notice of a good-faith breach theory | Court: No jurisdiction over Count Two — REA did not provide clear notice of a breach-of-duty claim; Count Two dismissed for lack of jurisdiction but case stayed 3 months to permit submission to CO |
| Whether Count Three (differing site condition for Five Problem Shafts) was properly presented to CO | Plaintiffs: REA raised differing site condition for the Five Problem Shafts and sought adjustment | Government does not contest CO presentation; CO denied on merits | Court: Jurisdiction exists for Count Three — it was presented and denied by the CO |
| Whether Counts One and Three should be merged as same claim | Plaintiffs assert they are distinct (different facts and relief) | Government contends both were framed as differing site conditions and should be merged | Court: Declined to merge; Counts rest on different operative facts and seek different relief |
Key Cases Cited
- Contract Cleaning Maint., Inc. v. United States, 811 F.2d 586 (Fed. Cir. 1987) (administrative CDA claim must give CO clear notice of basis and amount)
- Scott Timber Co. v. United States, 333 F.3d 1358 (Fed. Cir. 2003) (CDA claim to CO need not use exact legal label; court may hear claims arising from same operative facts)
- Reliance Ins. Co. v. United States, 931 F.2d 863 (Fed. Cir. 1991) (no jurisdiction where only equitable-adjustment claims submitted and breach-of-duty theory not presented to CO)
- Randa/Madison Joint Venture III v. Dahlberg, 239 F.3d 1264 (Fed. Cir. 2001) (elements for differing site condition entitlement)
- Precision Pine & Timber, Inc. v. United States, 596 F.3d 817 (Fed. Cir. 2010) (standard for breach of implied duty of good faith and fair dealing)
- Metcalf Const. Co. v. United States, 742 F.3d 984 (Fed. Cir. 2014) (duty of good faith and fair dealing implied in government contracts)
- Bell/Heery v. United States, 739 F.3d 1324 (Fed. Cir. 2014) (breach occurs when government acts to reappropriate contractual benefits)
