History
  • No items yet
midpage
Wa Federal Savings, Res/cross-app. v. Algo, Inc. And Allen R. Grant, Apps/cross-res.
72114-3
| Wash. Ct. App. | Feb 21, 2017
Read the full case

Background

  • Grant defaulted on his Washington Federal loan in 2011 and the bank foreclosed the collateral securing the loan.
  • The parties mediated and signed a Settlement Agreement on August 1, 2012, promising Grant $1 million via a promissory note secured by real property, with potential discounts for early payment and 0% interest for 60 months (12% on default).
  • Grant never signed a promissory note or secured collateral; he repudiated the Settlement Agreement on February 11, 2013.
  • Washington Federal sought summary judgment on breach; the trial court granted it in part, awarding $1 million, later reduced to $850,000, plus prejudgment interest and attorney fees; costs were awarded as requested.
  • Grant bankruptcy proceedings treated Washington Federal as an unsecured creditor; the trial court’s order and the post-judgment posture are on appeal.
  • The court ultimately held that the $1 million principal sum was due immediately upon Grant’s material breach, reversed the discount-based reduction to $850,000, affirmed prejudgment interest, and reversed the attorney-fees award.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Damages for breach amount Washington Federal: full $1M due immediately due to material breach Grant: only $850K (discounts apply; note not executed) $1,000,000 principal due immediately
Prejudgment interest Interest should accrue on liquidated sum from breach date No interest until payment due date Affirmed prejudgment interest
Attorney fees Contract allows fees to enforce the note; fees should follow Settlement Agreement does not authorize fees for enforcement; not applicable Reversed; no attorney fees awarded to Washington Federal
Discounts and present value Discounts should reduce the amount due if applicable Discounts should apply only if note executed and payment timely Discounts not applicable; present value reduction rejected
Acceleration clause/foreseeable breach Draft note implied acceleration upon breach No general acceleration clause; note not executed; cannot accelerate No general acceleration; damages awarded on $1M unaffected by acceleration

Key Cases Cited

  • Rathke v. Roberts, 33 Wn.2d 858 (1949) (liquidated damages and full performance concepts under contract law)
  • Colorado Structures, Inc. v. Ins. Co. of the West, 161 Wn.2d 577 (2007) (breach; liquidated damages; remedies for total breach)
  • Prier v. Refrigeration Enq'a Co., 74 Wn.2d 25 (1968) (prejudgment interest on liquidated sums; computation as of breach date)
  • Bulman v. Safeway, Inc., 144 Wn.2d 335 (2001) (contract elements; consideration; acceleration concepts)
  • CPK, Inc. v. GRS Const. Co., 63 Wn. App. 601 (1991) (breach and continuing performance; damages patterns)
  • Berg v. Hudesman, 115 Wn.2d 657 (1990) (interpretation of integrated writings; admissibility of negotiations to interpret contract)
Read the full case

Case Details

Case Name: Wa Federal Savings, Res/cross-app. v. Algo, Inc. And Allen R. Grant, Apps/cross-res.
Court Name: Court of Appeals of Washington
Date Published: Feb 21, 2017
Docket Number: 72114-3
Court Abbreviation: Wash. Ct. App.