History
  • No items yet
midpage
375 F. Supp. 3d 1
D.C. Cir.
2019
Read the full case

Background

  • Turner Construction contracted with U.S. Engineering; U.S. Engineering subcontracted sheet-metal work to United Sheet Metal ("Sheet Metal").
  • Western Surety issued a $585,000 performance bond naming U.S. Engineering as owner and Sheet Metal as contractor; Bond Sections 3–5 set notice and remedies for owner-declared default.
  • Sheet Metal's performance problems culminated in U.S. Engineering terminating the subcontract on September 9, 2013 and completing the work with others without notifying Western Surety.
  • U.S. Engineering notified Western Surety of its claim nine months after termination and after completion of the work; Western Surety refused payment and sought declaratory relief.
  • Western Surety moved for summary judgment seeking a declaration it had no obligation under the Bond; U.S. Engineering moved to reconsider the court's striking of a supplemental arbitration award and opposed summary judgment.

Issues

Issue Plaintiff's Argument (Western Surety) Defendant's Argument (U.S. Engineering) Held
Whether Section 3.2 notice is a condition precedent to Surety liability Section 3.2 requires notice before Surety's obligations arise; timely notice is implied to permit Surety to cure Section 3.2 does not specify a time requirement; U.S. Eng. fulfilled obligations by declaring default and notifying Surety eventually Court: Section 3.2 creates a condition precedent; notice must be timely; U.S. Eng.'s notice was untimely
Whether Surety must show actual prejudice from late notice under Section 3.2 No prejudice showing is required for Section 3.2 because Section 4's prejudice clause applies only to Section 3.1 Surety must prove actual prejudice to be released from liability Court: Prejudice is not required under Section 3.2; Bond language and structure limit Section 4's prejudice requirement to Section 3.1
Whether the Arbitration Award submitted as supplemental authority should be considered (n/a) — Surety moved to strike the award from the record The arbitration award proves Sheet Metal's liability and damages and undermines Surety's prejudice claim Court: Denied Surety's motion to strike; considered the award but found it immaterial to Bond interpretation and outcome
Whether the court should reconsider striking U.S. Eng.'s earlier filing re: supplemental authority (n/a) — Surety had sought strike for untimeliness U.S. Eng. obtained plaintiff's consent to extend its response time and inadvertently failed to notify the court Court: Granted U.S. Eng.'s motion for reconsideration and reinstated consideration of the submission

Key Cases Cited

  • Hunt Construction Group, Inc. v. National Wrecking Corp., 587 F.3d 1119 (D.C. Cir. 2009) (timely notice to surety required so surety can exercise contractual cure options)
  • Conesco Industries, Ltd. v. Conforti & Eisele, Inc., 627 F.2d 312 (D.C. Cir. 1980) (late notice may discharge surety only upon a showing of prejudice where bond language does not make notice to surety a condition precedent)
  • Washington Properties, Inc. v. Chin, Inc., 760 A.2d 546 (D.C. 2000) (definition and effect of a condition precedent under District of Columbia law)
  • Steele Foundations, Inc. v. Clark Construction Group, Inc., 937 A.2d 148 (D.C. 2007) (contract interpretation requires giving meaning to all provisions)
  • Mergentime Corp. v. Washington Metropolitan Area Transit Authority, 775 F. Supp. 14 (D.D.C. 1991) (surety discharge for contract modification is evaluated based on prejudice)
Read the full case

Case Details

Case Name: W. Sur. Co. v. U.S. Eng'g Co.
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Mar 20, 2019
Citations: 375 F. Supp. 3d 1; Civil Action No. 15-cv-00327 (TSC)
Docket Number: Civil Action No. 15-cv-00327 (TSC)
Court Abbreviation: D.C. Cir.
Log In
    W. Sur. Co. v. U.S. Eng'g Co., 375 F. Supp. 3d 1