Volmar Construction, Inc.
ASBCA No. 60710-910
| A.S.B.C.A. | Oct 7, 2016Background
- Volmar Construction was awarded a renovation contract by the U.S. Army Corps of Engineers (Contract No. W912QR-12-C-0074).
- On 19 May 2016 Volmar submitted seven certified claims (plus one earlier-decided claim) seeking money and time extensions for various impacts and costs (asbestos, extended overhead, canopy modification, peeling paint, booster fans, etc.).
- The contracting officer (CO) issued a final decision on the kitchen equipment claim on 18 July 2016 and notified Volmar that the remaining seven final decisions would be issued on or before 31 March 2017.
- Volmar petitioned the ASBCA under Board Rule 1(a)(5) (CDA § 7103(f)(4)) asking the Board to direct the CO to issue decisions sooner, arguing the CO’s March 31, 2017 date was unreasonably delayed.
- The government defended the March 31, 2017 date, explaining the current CO lacks prior exposure to the claims and intends to hire an outside scheduling expert (estimated ~150 days for contracting and expert report), plus time to assemble documentation and confer with technical experts.
- The Board found the government’s timetable unreasonably long given the claims had been pending (and parts submitted) for months and that staffing/time-to-hire issues are within the government’s control; the Board directed the CO to issue decisions by January 13, 2017.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the CO’s proposed deadline (Mar 31, 2017) for issuing final decisions is unreasonable delay under the CDA | The Mar 31, 2017 date is undue delay (10–13 months after submissions); Board should direct an earlier date | The date is reasonable because the new CO needs to hire an outside scheduling expert and must gather documentation and consult technical experts | The Board held Mar 31, 2017 was undue delay and directed the CO to issue decisions by Jan 13, 2017 |
| Whether internal government staffing/timing for review justifies extended decision period | N/A (Volmar argued only that delay was undue) | CO’s unfamiliarity with the claims and internal resourcing justify additional time | The Board rejected governmental staffing/resourcing as a persuasive reason; internal staffing is within government control and not a CDA factor |
| Whether retaining an outside expert justifies the CO’s timetable | Volmar argued expert needs did not justify such a long delay given prior submissions | Government contended outside scheduling expert would require ~90 days to contract plus ~60 days to produce report | The Board found the expert report could be produced earlier (mid-October under govt’s estimate) and that the remaining time requested was excessive; deadline shortened to Jan 13, 2017 |
Key Cases Cited
- No officially reported (bluebook-format) cases with reporter citations appear in the opinion; the Board relied on prior ASBCA decisions reported in B.C.A. digests but did not cite cases with official reporter citations.
