midpage
Sign in to see your projects.
34 Neb. App. 329
Neb. Ct. App.
2026
Read the full case

Background

  • Nemaha County hired Vogtscapes as general contractor to replace a county bridge with a concrete box culvert, and Vogtscapes subcontracted dirt work to Nebraska Digging. 1
  • The contract was a $752,311 lump-sum agreement allowing changes only by written change order, and no written change order was ever executed. 2
  • The contract required Vogtscapes to coordinate stockpile location with the County and made Mainelli Wagner responsible for supervision and contract-interpretation questions. 3
  • The parties later agreed the dirt stockpile had to be moved to complete the project, and Nebraska Digging claimed the relocation was extra work requiring additional compensation. 4
  • Appellants presented evidence that, at an October 2023 meeting, Britt and Weiss discussed moving the stockpile as a project overrun and told Nebraska Digging not to pursue a written change order. 5
  • The district court granted summary judgment for Nemaha County, finding the work was contemplated by the contract and that Appellants failed to obtain a written change order. 6

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether summary judgment was proper despite factual disputes over extra work 7 Appellants said material factual disputes existed about waiver and oral modification. Nemaha County said the contract was unambiguous and no written change order existed. Summary judgment reversed; factual disputes precluded judgment. 8
Whether the written change order provision was waived or orally modified 9 Appellants said County agents treated the relocation as compensable overrun work. Nemaha County said no authorized person agreed to pay extra and no change order was approved. A triable issue existed on waiver and oral modification. 10

Key Cases Cited

  • D&M Roofing & Siding v. Distrib., Inc., 319 Neb. 707 (Neb. 2025) (de novo review of summary judgment 11)
  • DH-1, LLC v. City of Falls City, 305 Neb. 23 (Neb. 2020) (contract interpretation and ambiguity are questions of law 12)
  • Humphrey v. Smith, 311 Neb. 632 (Neb. 2022) (summary judgment standard; material facts and admissible evidence 13)
  • D. K. Meyer Corp. v. Bevco, Inc., 206 Neb. 318 (Neb. 1980) (written change-order provisions may be waived by conduct; parties' performance shows contract intent 14)
  • Griffin v. Geneva Industries, Inc., 193 Neb. 694 (Neb. 1975) (contract provisions may be waived, modified, rescinded, or abandoned by words or conduct 15)
Read the full case

Case Details

Case Name: Vogtscapes, Inc. v. Nemaha County
Court Name: Nebraska Court of Appeals
Date Published: Jun 23, 2026
Citations: 34 Neb. App. 329; A-25-481
Docket Number: A-25-481
Court Abbreviation: Neb. Ct. App.
Log In