History
  • No items yet
midpage
Voces v. Energy Resource Technology, G.O.M., L.L.C.
704 F. App'x 345
5th Cir.
2017
Read the full case

Background

  • ERT contracted OSF, an independent contractor, to remove the Vermillion 200A offshore platform; the written contract and OSF’s Work Plan assigned OSF responsibility to develop and implement safe removal procedures.
  • OSF crews began prep work cutting pad welds on the ABJ-332 tank; OSF had an internal 50% Rule (do not cut more than 50% of pad welds unless crane support in place).
  • ERT maintained an on-site company man whose role, per the contract, was to monitor OSF’s compliance with the contract and be informed of changes, not to direct day-to-day methods.
  • During prep work, welds failed and the ABJ-332 tank rotated free after remaining connections were cut; welder Peter Voces fell into the Gulf and drowned.
  • BSEE recommended an Incident of Non-Compliance against ERT for (1) accepting OSF’s plan without further engineering verification and (2) the company man’s failure to recognize OSF’s deviation from safety procedures; ERT disputed the findings.
  • Plaintiff sued ERT (and nominally Talos) under Louisiana law (applied on the OCS) alleging (1) vicarious liability under the operational-control/authorization exceptions to the independent-contractor rule, and (2) independent negligence for voluntarily assuming safety duties; district court granted summary judgment for ERT; Fifth Circuit affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether ERT exercised operational control over OSF so as to be vicariously liable ERT’s company man participated in decisions, reviewed the Work Plan, and allegedly approved or influenced procedures Contract and Work Plan reserved step-by-step control to OSF; company man merely monitored compliance and did not direct methods No operational control: contractual reservation of procedural control to OSF and evidence shows company man inspected/monitored only
Whether ERT expressly or impliedly authorized unsafe practices Company man knew of or participated in decisions (e.g., delaying heavy lifts) and failed to stop unsafe work, amounting to authorization Knowledge or discussion isn’t authorization; no evidence ERT ordered or directed unsafe methods No authorization: mere observation/participation does not equal express or implied approval of unsafe means
Whether ERT voluntarily assumed a duty to ensure Work Plan safety (independent negligence) ERT’s letter to BSEE and presence of company man show ERT undertook safety oversight, creating a duty Any oversight was contractual monitoring of OSF obligations; no extra-contractual undertaking shown No assumed duty: plaintiff failed to identify extra-contractual conduct or reliance; summary judgment proper
If ERT undertook a safety duty, whether plaintiff showed required elements (increase in risk, reliance, or supplanting of OSF’s duty) Plaintiff argued Restatement theory permits liability without showing increase in risk or reliance Louisiana law requires increase in risk, reliance, or that the undertaking supplant the contractor’s duty; no such evidence here No triable issue: plaintiff did not show increase in risk, reliance, or that ERT intended to supplant OSF’s duty; summary judgment proper

Key Cases Cited

  • Graham v. Amoco Oil Co., 21 F.3d 643 (5th Cir. 1994) (principal not liable for independent contractor absent exceptions; principal still liable for its own negligence)
  • Bartholomew v. CNG Producing Co., 832 F.2d 326 (5th Cir. 1987) (operational-control exception explained)
  • Ainsworth v. Shell Offshore, Inc., 829 F.2d 548 (5th Cir. 1987) (contract reservation of control central to operational-control analysis)
  • Fruge v. Parker Drilling Co., 337 F.3d 558 (5th Cir. 2003) (operational-control requires control over step-by-step methods)
  • Le-Jeune v. Shell Oil Co., 950 F.2d 267 (5th Cir. 1992) (requiring contractor to follow owner safety rules does not alone create operational control)
  • Duplantis v. Shell Offshore, Inc., 948 F.2d 187 (5th Cir. 1991) (company man’s monitoring does not necessarily establish operational control)
  • Coulter v. Texaco, Inc., 117 F.3d 909 (5th Cir. 1997) (supervision/inspection for contractual compliance insufficient for operational control)
  • Davis v. Dynamic Offshore Res., L.L.C., 865 F.3d 235 (5th Cir. 2017) (company man did not authorize unsafe condition where he did not order the risky act)
  • Little v. Liquid Air Corp., 37 F.3d 1069 (5th Cir. 1994) (conclusory affidavits cannot defeat summary judgment)
  • Lechuga v. S. Pac. Transp. Co., 949 F.2d 790 (5th Cir. 1992) (need non-conclusory evidence to survive summary judgment)
Read the full case

Case Details

Case Name: Voces v. Energy Resource Technology, G.O.M., L.L.C.
Court Name: Court of Appeals for the Fifth Circuit
Date Published: Jul 28, 2017
Citation: 704 F. App'x 345
Docket Number: No. 16-20611
Court Abbreviation: 5th Cir.