History
  • No items yet
midpage
Virginia Electric and Power Co v. Bransen Energy, Inc
850 F.3d 645
| 4th Cir. | 2017
Read the full case

Background

  • Dominion contracted with Bransen to supply ~600,000 tons of Run-of-Mine (performance) coal for pre-commissioning testing of a new power plant; Master Agreement, Pre-COD Confirmation, and Services Agreement governed the transactions.
  • Bransen delivered ~599,920 tons to a leased CTI stockpile but included ~43,000 tons of coke breeze (a non-coal industrial byproduct) and otherwise delivered GOB (waste) coal rather than Run-of-Mine coal.
  • Dominion discovered the contamination (anonymous tip, interview with Bransen president, and independent SGS testing) and refused to deliver the stockpile to the Plant for pre-COD use; Dominion procured alternative fuel and sought to remediate/blend the stockpile.
  • Dominion sued for breach of contract and sought damages; district court granted partial summary judgment on the coke-breeze portion and held for Dominion after a bench trial on the remaining GOB/waste coal, awarding about $22.9 million (net award after earlier partial recovery $20,936,688).
  • Key contract provisions: Section 5 (quality adjustments, rejection, suspension) applies to shipments that violate numeric specification limits; Section 8.8 limits damages for other breaches to direct actual damages; parties agreed Virginia law applies.

Issues

Issue Plaintiff's Argument (Dominion) Defendant's Argument (Bransen) Held
1) Did Bransen materially breach by delivering coke breeze and GOB (waste) coal instead of Run-of-Mine coal? Bransen delivered non-coal coke breeze and waste (GOB) coal that defeated the contract’s essential purpose (performance fuel for testing). Coke breeze was a small fraction and met some specs; Dominion accepted deliveries or failed to timely reject under UCC. Yes. Court found coke breeze is not Run-of-Mine coal and GOB is waste coal; Bransen committed the first material breach.
2) Was Dominion the first breaching party by declining future Post-COD purchases? Dominion had no obligation to purchase post-COD; Post-COD Confirmations gave Dominion ordering option, not a purchase obligation. Dominion purportedly decided not to purchase through 2017, constituting first breach. No. Post-COD purchases were optional; Dominion’s decision did not breach.
3) Do Section 5 remedies (quality adjustments/rejection/suspension) exclusively limit Dominion’s remedies for the product delivered? Section 5 remedies apply to shipments that violate numeric specifications, but Dominion’s claim is that Bransen failed to deliver the contracted product (a separate ‘‘product’’ defect), so broader damages are available. Section 5 is the Master Agreement’s exclusive remedy for nonconforming coal shipments. Section 5 is exclusive only for remedies tied to specification nonconformity; it does not preclude recovery where the seller failed to deliver the contracted product (product-definition issue). Thus Section 8.8 (direct damages) controls here.
4) Were the district court’s damages (processing, replacement coal, lease and permit costs, stockpile depreciation) improper or speculative? Damages are direct and compensate cost to put Dominion in the position it would have been in but for breach (costs to process/repair stockpile, replacement coal, leases, permit costs). Expert’s damages included impermissible indirect or lost-profit items; calculations relied on abandoned missing-coal theory. Damages were within the contract’s direct-damages limitation and supported by expert testimony; district court adjusted for abandoned theories and did not commit clear error.

Key Cases Cited

  • Dreamstreet Invs., Inc. v. MidCountry Bank, 842 F.3d 825 (4th Cir. 2016) (summary judgment standard cited)
  • Raleigh Wake Citizens Ass’n v. Wake Cty. Bd. of Elections, 827 F.3d 333 (4th Cir. 2016) (bench-trial mixed standard: legal conclusions de novo, factual findings for clear error)
  • Andrews v. Am.’s Living Ctrs., LLC, 827 F.3d 306 (4th Cir. 2016) (clear-error standard explained)
  • Mallory v. Booth Refrigeration Supply Co., 882 F.2d 908 (4th Cir. 1989) (discussion of clear-error review)
  • TransDulles Ctr., Inc. v. USC Corp., 976 F.2d 219 (4th Cir. 1992) (measure of direct damages: cost to complete or cost of repair)
  • Long v. Abbruzzetti, 487 S.E.2d 217 (Va. 1997) (definition of direct damages as those flowing naturally from breach)
Read the full case

Case Details

Case Name: Virginia Electric and Power Co v. Bransen Energy, Inc
Court Name: Court of Appeals for the Fourth Circuit
Date Published: Mar 9, 2017
Citation: 850 F.3d 645
Docket Number: 16-1254
Court Abbreviation: 4th Cir.