History
  • No items yet
midpage
VICI Racing, LLC v. T-Mobile USA, Inc.
2014 U.S. App. LEXIS 15506
| 3rd Cir. | 2014
Read the full case

Background

  • VICI Racing LLC and T-Mobile USA, Inc. entered a Sponsorship Agreement for 2009–2011 Le Mans seasons.
  • Section 5.8 granted T-Mobile exclusive wireless carrier rights for telematics programs beginning in 2011; its meaning was disputed at trial.
  • Section 11.2 purportedly limited damages to $20,000 or aggregate payments, whichever higher, creating a dispute over liquidated damages.
  • T-Mobile breached by failing to pay $7 million due January 1, 2010; VICI sued for damages and cross-appealed for $7 million under the liquidated-damages clause.
  • The district court severed section 5.8 as ambiguous, enforcing the remainder of the contract, and found VICI’s breach excused by force majeure due to a racecar accident.
  • The district court awarded VICI $7 million in damages for 2010 but denied the 2011 $7 million, concluding mitigation and liquidated-damages issues.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether severance of 5.8 was proper VICI argues severance preserved the contract's remainder. T-Mobile contends severance ignores essentiality and intent of contract. Section 5.8 severed; remainder enforced.
Whether force majeure excused VICI’s nonperformance VICI asserts accident-modified nonperformance fell within force majeure. T-Mobile contends no force majeure justification for missing races. Force majeure excused nonperformance; damages narrowed.
Whether section 11.2 constitutes a liquidated damages clause VICI claims section 11.2 fixes liquidated damages for breach of the entire contract. T-Mobile argues the clause limits liability as liquidated damages. Section 11.2 is not a liquidated-damages clause; liability is a cap.
Appropriate measure and calculation of 2010 damages VICI seeks full expectancy damages with costs incurred; mitigation not waived for 2010. T-Mobile asserts deduction for costs avoided and mitigation should reduce damages. District court applied proper standard; affirmed as to 2010 damages
but implied offset of costs avoided; not clearly erroneous.
Validity of 2011 damages and mitigation/waiver VICI argues entitled to second $7 million under contract. T-Mobile argues mitigation and waiver prevent recovery of 2011 amount. District Court erred in 2011 damages analysis; remanded for proper measurement without mitigation argument (waived).

Key Cases Cited

  • Gulf Oil Corp. v. F.E.R.C., 706 F.2d 444 (3d Cir. 1983) (force majeure defines events beyond control; uncertainty element recognized)
  • Orenstein v. Kahn, 119 A. 444 (Del. 1922) (severability and intent considerations in contract terms)
  • Scarborough v. State, 945 A.2d 1103 (Del. 2008) (contract must be reasonably definite to be enforceable; severability guidance)
  • Paul v. Deloitte & Touche, LLP, 974 A.2d 140 (Del. 2009) (damages should place injured party in position as if contract performed)
  • Duncan v. Theratx, Inc., 775 A.2d 1019 (Del. 2001) (reasonable foreseeability and loss in contract damages; mitigation context)
Read the full case

Case Details

Case Name: VICI Racing, LLC v. T-Mobile USA, Inc.
Court Name: Court of Appeals for the Third Circuit
Date Published: Aug 13, 2014
Citation: 2014 U.S. App. LEXIS 15506
Docket Number: 13-1615, 13-1780
Court Abbreviation: 3rd Cir.