History
  • No items yet
midpage
Venco Imtiaz Construction Company v. Symbion Power LLC
Civil Action No. 2016-1737
D.D.C.
May 31, 2017
Read the full case

Background

  • USAID funded construction of a Kabul power plant; The Louis Berger Group/Black & Veatch (LBG/BV) was the project manager, Symbion Power LLC was the prime contractor, and Venco Imitiaz Construction Co. was a subcontractor for power blocks.
  • LBG/BV and Symbion disputed delays; LBG/BV withheld payment to Symbion, and Symbion withheld payment to Venco. Symbion contended its payments to Venco were conditioned on Symbion receiving payment from LBG/BV; Venco disputed that defense.
  • Symbion and LBG/BV arbitrated first (ICC), and that tribunal found LBG/BV breached but held Symbion could not rely solely on invoices to prove entitlement to payment.
  • Venco separately arbitrated against Symbion (ICC), presented evidence and testimony, and won a final award (July 11, 2016) requiring Symbion to pay roughly $8.46 million (unpaid invoices, interest, fees, arbitration costs).
  • Symbion filed to set aside the Venco award in the U.K.; Venco petitioned this Court to confirm the award under the New York Convention. The U.K. High Court later denied Symbion’s challenge; Symbion sought leave to appeal.
  • This Court evaluated whether to confirm the award and whether to stay enforcement pending the U.K. proceedings.

Issues

Issue Plaintiff's Argument (Venco) Defendant's Argument (Symbion) Held
Whether to confirm the ICC arbitral award under the New York Convention The award is valid and enforceable; no Convention defense applies Enforcement should be denied because it would violate public policy via issue preclusion from the prior LBG/BV–Symbion award Confirmed the award; public policy exception did not apply
Whether issue preclusion (collateral estoppel) bars the Venco award N/A (Venco argues award independently valid) Prior LBG/BV award established rule that invoices alone cannot prove damages and should bind subsequent tribunal Rejected: Venco was not a party to the prior arbitration; nonparty preclusion inapplicable given Taylor framework and lack of adequate representation
Whether to stay enforcement pending U.K. proceedings Opposes stay; requests security only if stay granted Requests stay pending U.K. appeal Denied stay: key Europcar factors (speed of arbitration, status of foreign proceedings) favored enforcement; U.K. trial court had already ruled for Venco
Whether Venco may recover attorney’s fees for confirming the award in this Court Requested fees and costs for this confirmation action Opposed / not addressed substantively Denied fee request for this federal action (no briefing or legal basis shown)

Key Cases Cited

  • Marmet Health Care Ctr., Inc. v. Brown, 565 U.S. 530 (emphatic federal policy favoring arbitration)
  • KPMG LLP v. Cocchi, 565 U.S. 18 (same principle regarding arbitration enforcement)
  • TermoRio S.A. E.S.P. v. Electranta S.P., 487 F.3d 928 (D.C. Cir.) (narrow construction of New York Convention public policy exception)
  • Taylor v. Sturgell, 553 U.S. 880 (nonparty preclusion limited to narrow categories; due process constraints)
  • Europcar Italia S.P.A. v. Maiellano Tours, Inc., 156 F.3d 310 (2d Cir.) (factors for staying enforcement pending foreign proceedings)
  • Montana v. United States, 440 U.S. 147 (policy reasons for issue preclusion)
  • Belize Bank Ltd. v. Gov’t of Belize, 852 F.3d 1107 (D.C. Cir.) (burden on challenger to meet exacting public policy standard)
Read the full case

Case Details

Case Name: Venco Imtiaz Construction Company v. Symbion Power LLC
Court Name: District Court, District of Columbia
Date Published: May 31, 2017
Docket Number: Civil Action No. 2016-1737
Court Abbreviation: D.D.C.