History
  • No items yet
midpage
Vanderwal v. Albar, Inc.
154 Idaho 816
| Idaho | 2013
Read the full case

Background

  • Albar, Inc. owned a convenience store/marina where an underground storage tank leaked gasoline in 2003; DEQ required remediation and a Fund contractor began work.
  • In 2005 Albar sold the property to JLZ Enterprises; Albar’s counteroffer stated seller had “all responsibility and liability for recent gasoline spill on property and adjoining property.”
  • Albar and its contractor did not complete required testing or excavations; remediation efforts stagnated and DEQ would not issue clearance.
  • JLZ assumed remediation in late 2007 through DEQ’s voluntary program, completed excavation/cleanup work in 2008, and sought DEQ reimbursement later.
  • JLZ sued for breach of contract and rescission; the district court found the contract ambiguous, held Albar obligated to remediate to DEQ standards within a reasonable time, found Albar breached, awarded JLZ $228,044.72 in damages, and offset that against the promissory note; Albar’s Rule 60(b) motion to reduce damages after DEQ paid JLZ was denied.

Issues

Issue Plaintiff's Argument (JLZ) Defendant's Argument (Albar) Held
Whether Albar breached the real estate contract by failing to remediate Contract required seller to continue remediation to DEQ standards; seller failed to perform within a reasonable time Albar contended no specific remediation result or time was bargained for and thus no breach Court: provision ambiguous; evidence supports obligation to remediate to DEQ standards; law implies reasonable time; Albar breached
Whether JLZ’s takeover of remediation was permissible and damages mitigation JLZ was justified to take over remediation to mitigate damages and obtain the bargained-for performance Albar argued JLZ’s actions (changing site use) altered remediation standards and relieved Albar Court: JLZ entitled to assume remediation to mitigate damages; delays caused by Albar’s refusal to do dig-and-haul, not JLZ
Whether the district court’s damages award is supported by the record Damages reflect costs JLZ incurred taking over remediation Albar asserted it was not liable for damages but made no transcript/authority-based challenge Court: Albar failed to properly challenge factual findings; damages supported and affirmed
Whether post-judgment DEQ reimbursement to JLZ reduces the damages award (Rule 60(b) relief) Albar sought reduction of damages by DEQ payment under Rule 60(b)(2),(5),(6) JLZ opposed; argued judgment final and Rule 60(b) relief not warranted Court: Denied relief — (2) payment was not newly discovered evidence; (5) damages are final past harm; (6) Albar failed to show unique and compelling circumstances

Key Cases Cited

  • Argosy Trust ex rel. Its Trustee v. Wininger, 141 Idaho 570 (factual findings will not be set aside unless clearly erroneous)
  • Elliott v. Verska, 152 Idaho 280 (substantial and competent evidence standard for factual findings)
  • Weinstein v. Prudential Prop. and Cas. Ins. Co., 149 Idaho 299 (where no time is expressed, performance is implied within a reasonable time)
  • Curzon v. Wells Cargo, Inc., 86 Idaho 38 (same reasonable-time principle in contract performance)
  • In re Jane Doe, I, 145 Idaho 650 (Rule 60(b)(2) does not cover facts arising after trial)
  • Meyers v. Hansen, 148 Idaho 283 (Rule 60(b)(5) cannot modify damages that represent present debt at judgment)
  • Miller v. Haller, 129 Idaho 345 (Rule 60(b)(6) relief requires unique and compelling circumstances)
  • Triad Leasing & Financial, Inc. v. Rocky Mountain Rogues, Inc., 148 Idaho 503 (prevailing party rule for appellate attorney fees)
Read the full case

Case Details

Case Name: Vanderwal v. Albar, Inc.
Court Name: Idaho Supreme Court
Date Published: Jun 20, 2013
Citation: 154 Idaho 816
Docket Number: 38085-2012
Court Abbreviation: Idaho