History
  • No items yet
midpage
99 F. Supp. 3d 543
E.D. Pa.
2015
Read the full case

Background

  • VA awarded a prime contract to Nason Construction for a Philadelphia VA parking garage; Zurich issued a payment bond for Nason.
  • Marenalley Construction entered a subcontract with Nason for ~$1.33M and performed additional work due to VA-directed changes and unforeseen conditions.
  • Marenalley submitted change orders/equitable adjustment requests to Nason; Nason filed a certified claim with the VA including Marenalley’s claimed amounts; the VA has not decided the claim.
  • Marenalley sued Zurich under the Miller Act to recover unpaid labor and materials (~$590K). Nason intervened and moved to dismiss or stay, arguing the subcontract requires exhaustion of the prime contract’s CDA administrative process before bond suit.
  • The subcontract contains provisions referencing the prime contract’s disputes clause; Marenalley has no privity with the VA and cannot present claims directly to the contracting officer.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the subcontract requires Marenalley to await resolution of Nason’s CDA administrative process before suing the Miller Act bond Marenalley: subcontract does not (and in any event cannot) waive Miller Act rights; it can sue the bond 90 days after completing its work Nason/Zurich: subcontract incorporates prime contract dispute clause and requires exhaustion of CDA remedies before bond suit Court: No waiver; subcontract cannot be read to bar Miller Act suit pre-exhaustion; dismissal denied
Whether the complaint should be dismissed for failure to follow administrative process Marenalley: CDA is only for contractor vs. government and does not resolve prime–subcontractor payment disputes Nason/Zurich: administrative process governs and is pending; dismissal appropriate until it resolves Court: Denied — CDA does not provide subcontractor remedy and does not preclude Miller Act suit
Whether this action should be stayed pending the CDA process Marenalley: stay would cause indefinite delay and defeat Miller Act’s prompt-payment purpose Nason/Zurich: risk of duplicative litigation, inconsistent results, and surety liability is derivative of contractor’s claim against the VA Court: Denied — Miller Act gives subcontractor independent right to prompt suit; stay would undermine statutory protection

Key Cases Cited

  • United States v. Blair, 321 U.S. 730 (1944) (subcontractor has no direct contract claim against the United States)
  • Beacon Construction Co. v. Prepakt Concrete Co., 375 F.2d 977 (1st Cir. 1967) (prime contractor is the party entitled to present claims to contracting officer)
  • Fanderlik-Locke Co. v. United States, 285 F.2d 939 (10th Cir. 1961) (CDA does not provide for hearing disputes between prime and subcontractor)
  • United States ex rel. Sherman v. Carter, 353 U.S. 210 (1957) (surety liability on Miller Act bond must be coextensive with Act’s protections)
  • Walton Technology v. Weststar Engineering, Inc., 290 F.3d 1199 (9th Cir. 2002) (subcontract terms conflicting with Miller Act ineffective; surety liability analyzed under Miller Act)
  • T.M.S. Mechanical Contractors v. Millers Mutual Fire Ins. Co. of Texas, 942 F.2d 946 (5th Cir. 1991) (Miller Act protections displace ordinary derivative-liability rules)
  • Daniel, Urbahn, Seelye & Fuller v. United States, 357 F. Supp. 853 (N.D. Ill. 1973) (history of Heard Act and Miller Act and subcontractor payment issues)
Read the full case

Case Details

Case Name: United States v. Zurich American Insurance
Court Name: District Court, E.D. Pennsylvania
Date Published: Mar 13, 2015
Citations: 99 F. Supp. 3d 543; 2015 WL 1137053; 2015 U.S. Dist. LEXIS 30968; Civil Action No. 14-4581
Docket Number: Civil Action No. 14-4581
Court Abbreviation: E.D. Pa.
Log In
    United States v. Zurich American Insurance, 99 F. Supp. 3d 543