History
  • No items yet
midpage
United States v. Liberty Mutual Insurance Company
8:12-cv-02921
M.D. Fla.
Dec 28, 2015
Read the full case

Background

  • Jack Daniels Construction, Inc. sues Liberty Mutual and Safeco (Sureties) under the Miller Act for labor/costs on the Joint Intelligence Technical Training Facility project.
  • Peter Brown Construction, prime contractor, provided payment bond; Ragghianti Foundations III, LLC performed subcontracts and Jack Daniels performed sub-subcontracted concrete work.
  • Subcontract and Sub-Subcontract governed the work; the Sub-Subcontract was not incorporated by reference to the Subcontract.
  • A joint payment of $92,623.56 was made via an unconditional lien waiver, but Jack Daniels alleges nonpayment on several invoices.
  • Ragghianti case resolved some issues, but this case was stayed pending that outcome; upon return, both sides moved for partial summary judgment.
  • Court grants/denies various motions, including denial of certain claims and discovery of contested facts related to damages and waivers.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Sureties are liable for unearned profits under the Miller Act Daniels does not pursue lost profits; any question about 80627 remains factual Invoice 80627 seeks loss-profits; Miller Act does not cover unearned profits Summary judgment denied on extent of 80627 as profits may be recoverable or not; factual question remains
Whether CO Nos. 5 and 8 are barred by the Sub-Subcontract Delays caused by Peter Brown; costs attributable to delay are recoverable under Pertun CO 5/8 constitute non-continuous mobilizations included in lump-sum price; not recoverable Not entitled to summary judgment; genuine issue of fact exists as to whether costs were expended due to delay
Whether the Waiver releases Jack Daniels' Miller Act claims for CO Nos. 7, 8, 9, and 2.1 Waiver lacks express release of Miller Act rights; invoices not included Waiver purports broad release of lien/bond claims Summary judgment not appropriate; issues of material fact remain about Waiver scope
Whether Jack Daniels is entitled to Attorneys’ Fees Texas law governs fees; Miller Act permits fee recovery if contract provides F.D. Rich Co. controls; federal law; no applicable contract provision here Sureties entitled to summary judgment on attorneys’ fees (no applicable fee provision under state law)
Whether Sureties’ affirmative defenses of prior breach and setoff survive No privity; Sureties cannot rely on contract defenses against Miller Act claim Sureties stand in principal’s shoes; may raise defenses; privity exists via contract Plaintiff entitled to summary judgment on both prior breach and setoff defenses

Key Cases Cited

  • Pertun Constr. Co. v. Harvesters Grp., Inc., 918 F.2d 915 (11th Cir. 1990) (Miller Act delay costs recoverable as out-of-pocket costs)
  • F.D. Rich Co. v. United States for the Use of Industrial Lumber Co., 417 U.S. 116 (1974) (Miller Act remedies are federal; attorneys’ fees governed by federal law; American Rule applies)
  • Mariana v. Piracci Constr. Co., 405 F. Supp. 904 (D.D.C. 1975) (Costs incurred due to delay may be recoverable under Miller Act)
  • Krupp Steel Prods. v. Aetna Ins. Co., 831 F.2d 978 (11th Cir. 1987) (Miller Act remedies; surety liability limited to labor/material costs)
  • Trane Co., a div. of Am. Standard v. Whitehurst-Lassen Const. Co., 881 F.2d 996 (11th Cir. 1989) (Right to sue on bond; waiver analysis; scope of release)
Read the full case

Case Details

Case Name: United States v. Liberty Mutual Insurance Company
Court Name: District Court, M.D. Florida
Date Published: Dec 28, 2015
Docket Number: 8:12-cv-02921
Court Abbreviation: M.D. Fla.