History
  • No items yet
midpage
283 F. Supp. 3d 476
E.D. Va.
2017
Read the full case

Background

  • Kitchens-to-Go (subcontractor) supplied temporary kitchen trailers for a Navy construction project; John C. Grimberg Co. was the prime contractor and Hartford was the payment-bond surety under the Miller Act.
  • Subcontract contained an Article 9 no-damages-for-delay clause (subcontractor entitled only to reimbursement actually recovered from the owner) and Article 15 incorporating the prime contract’s owner-prime dispute procedures.
  • Project delays extended the work; Grimberg submitted a cost worksheet to the Navy seeking ~$686,818 for extended trailer lease; the Navy rejected payment, stating lease extensions were Grimberg’s responsibility.
  • Subcontractor sued under the Miller Act seeking $734,496 (including extended-lease delay damages); Grimberg later paid $127,275 (mooting that portion), leaving the Extended Lease claim contested.
  • Court addressed three issues on partial summary judgment: (1) whether the Miller Act bars enforcement of the no-damages-for-delay clause against the surety; (2) whether the subcontract’s incorporation of owner-prime dispute procedures requires the subcontractor to await that process; and (3) whether the amount of delay damages is ripe for summary judgment given the surety’s Rule 56(d) affidavit.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Enforceability of no-damages-for-delay clause against the surety Clause cannot defeat Miller Act rights; surety cannot enforce it to avoid bond liability Clause conditions subcontractor recovery on owner payment, so no amount is due until owner pays Clause unenforceable against surety; Miller Act controls (summary judgment for plaintiff on this issue)
Effect of subcontract provision incorporating owner-prime dispute procedures Subcontractor need not await owner-prime dispute resolution to sue on payment bond after 90 days Article 15 requires resolving owner-related disputes under prime contract procedures; stay pending those proceedings is appropriate Subcontractor need not await those proceedings; stay denied (summary judgment for plaintiff on this issue)
Validity of waiver via subcontract No valid waiver: statutory waiver must be written, signed, and executed after furnishing labor/materials Subcontract asserts subcontract terms operate as waiver or condition Waiver invalid: clause executed before work, so cannot waive Miller Act rights under 40 U.S.C. § 3133(c)
Amount of delay damages (ripeness for summary judgment) Subcontractor contends amount is established by Grimberg’s submission to the Navy and seeks judgment on amount Surety submitted Rule 56(d) affidavit seeking further discovery on amount and contends passing on claim ≠ admission of amount due Summary judgment on amount denied; Rule 56(d) affidavit permits further discovery to determine genuine dispute of fact

Key Cases Cited

  • Walton Tech., Inc. v. Weststar Eng'g, Inc., 290 F.3d 1199 (9th Cir. 2002) (Miller Act limits on surety enforcing subcontract terms; look beyond principal's contract)
  • United States ex rel. Sherman v. Carter, 353 U.S. 210 (1957) (Miller Act bond liability must be coextensive with Act to effectuate its purpose)
  • F.D. Rich Co. v. United States ex rel. Indus. Lumber Co., 417 U.S. 116 (1974) (Miller Act is remedial and protects suppliers on federal projects)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (1986) (summary judgment standard)
  • Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986) (genuine dispute for trial standard)
  • United States ex rel. Woodington Elec. Co. v. United Pac. Ins., 545 F.2d 1381 (4th Cir. 1976) (subcontract can define measure of recovery, but cannot eliminate Miller Act rights)
  • Moore Bros. Co. v. Brown & Root Inc., 207 F.3d 717 (4th Cir. 2000) (purpose of surety bond to ensure payment when principal does not pay)
Read the full case

Case Details

Case Name: United States ex rel. Kitchens to Go v. John C. Grimberg Co.
Court Name: District Court, E.D. Virginia
Date Published: Oct 19, 2017
Citations: 283 F. Supp. 3d 476; Case No. 1:16–cv–991
Docket Number: Case No. 1:16–cv–991
Court Abbreviation: E.D. Va.
Log In