History
  • No items yet
midpage
Unified Contractor, Inc. v. Albuquerque Housing Auth.
34,826
| N.M. Ct. App. | Apr 24, 2017
Read the full case

Background

  • Unified Contractor (Unified) contracted with Albuquerque Housing Authority (AHA) to provide exterior stucco/painting work at multiple properties; the contract incorporated Form HUD-5370 and contained a disputed-billings clause and prompt-payment provisions.
  • Dispute arose over the elastomeric coating used and whether Unified applied it per the manufacturer's specifications (AHA approved ParexUSA coating; Unified purchased 79 pails). AHA inspected and reported visible defects and suspected under-application.
  • AHA withheld payments in part, audited Unified’s supplier invoices, then terminated the contract for material breach (use of non-approved materials and failure to follow manufacturer application). Unified sued for breach, unjust enrichment, and Prompt Payment Act violations; AHA counterclaimed for breach and damages to repair/complete work.
  • At trial the court found both parties breached: AHA for imperfect compliance with disputed-billing notice provisions (but not liable for Prompt Payment Act interest due to a "major dispute"), and Unified for materially breaching by under-applying coating and misrepresenting performance. District court awarded Unified recovery for unpaid work and awarded AHA damages to repair; offset produced a net judgment for AHA.
  • On appeal, this Court affirmed liability findings except it (1) rejected Unified’s notice-and-cure requirement claim, (2) allowed AHA to rely on under-application grounds at trial, (3) agreed that AHA gave sufficient notice to avoid Prompt Payment Act interest, but (4) reversed the damages calculation and remanded to apply the contract-price-limitation rule, reducing AHA’s recoverable damages.

Issues

Issue Plaintiff's Argument (Unified) Defendant's Argument (AHA) Held
Whether contract or HUD default clause required notice and opportunity to cure before termination Contract required notice and an opportunity to cure as condition precedent to termination Contract permissively allowed AHA to give notice but did not require it; HUD/Form default clause does not guarantee right to cure Held: No mandatory cure right; Contract’s language is permissive ("may"), so AHA could terminate for material breach without providing cure notice
Whether AHA could rely at trial on termination grounds other than those stated in its pre-trial termination notice (i.e., under-application vs. number-of-coats) Pre-trial notice limited AHA to stated grounds; raising different theory prejudiced Unified Different articulation (under-application vs. two-coat violation) is substantively the same defect and caused no prejudice; later-proof of other grounds is allowed Held: AHA may prove default on any ground supported by the facts at termination time; district court did not err in considering under-application theory
Sufficiency / method of proving damages and whether award was speculative AHA’s damages evidence was speculative and legally insufficient AHA produced expert inspection and repair estimates; evidence supports damages Held: Damages supported by substantial evidence; however district court miscalculated net recoverable amount by permitting a double recovery and must apply the contract-price-limitation rule
Whether AHA’s mid-October correspondence triggered Prompt Payment Act interest liability AHA failed to give timely disputed-billing notice; Unified is entitled to statutory interest AHA’s mid-October communications put Unified on notice of a "major dispute," limiting statutory interest Held: AHA’s correspondence sufficed to place Unified on notice of a material dispute; Prompt Payment Act interest not awarded to Unified

Key Cases Cited

  • Cockrell v. Cockrell, 117 N.M. 321, 871 P.2d 977 (N.M. 1994) (a request for findings is not the only way to preserve sufficiency-of-evidence claims on appeal)
  • Public Serv. Co. of N.M. v. Diamond D Constr. Co., 131 N.M. 100, 33 P.3d 651 (N.M. Ct. App. 2001) (principles of contract interpretation: harmonize provisions and give meaning to all clauses)
  • Paiz v. State Farm Fire & Cas. Co., 118 N.M. 203, 880 P.2d 300 (N.M. 1994) (contract remedies should not place injured party in a better position than full performance)
  • Castricone v. Michaud, 583 N.E.2d 1184 (Ill. App. Ct. 1991) (applies contract-price-limitation rule: damages = cost to complete/repair minus unpaid contract balance)
  • McDonnell Douglas Corp. v. United States, 35 Fed. Cl. 358 (Ct. Cl. 1996) (discussion on when government may justify termination for default on grounds different from those initially asserted)
Read the full case

Case Details

Case Name: Unified Contractor, Inc. v. Albuquerque Housing Auth.
Court Name: New Mexico Court of Appeals
Date Published: Apr 24, 2017
Docket Number: 34,826
Court Abbreviation: N.M. Ct. App.