History
  • No items yet
midpage
2018 CO 56
Colo.
2018
Read the full case

Background

  • U.S. Welding (Welding) and Advanced Circuits (Advanced) entered a requirements contract: Advanced agreed to buy all its liquid nitrogen from Welding; initial two-year term began June 16, 2011 and auto‑renewed for one year on June 16, 2013.
  • Advanced sought bulk deliveries (cheaper) in late 2013; negotiations with Welding failed. Advanced solicited bids and contracted with Buckeye for bulk deliveries, then informed Welding it would terminate at the contract end (June 16, 2014) but also sought a buyout amount to be excused earlier (after Feb 28, 2014).
  • Advanced began receiving bulk deliveries from Buckeye on Feb 26, 2014; the district court found Advanced breached the contract by accepting Buckeye deliveries before contract expiration (equivalent to 161 dewars).
  • Welding refused to provide a pre‑expiration lost‑profits projection or to convert to bulk deliveries; district court held Welding failed to mitigate and awarded no damages. The court of appeals affirmed on mitigation.
  • The Colorado Supreme Court granted certiorari and reversed the courts below, holding a nonbreaching party cannot be required to mitigate by surrendering contractual rights (i.e., accept an accord/buyout in lieu of contract remedies) and remanded for further proceedings.

Issues

Issue Plaintiff's Argument (Welding) Defendant's Argument (Advanced) Held
Whether Welding was required to provide a pre‑expiration projection/buyout as mitigation Welding argued it was not required to give up contract rights or accept a buyout; its damages should be measured by actual sales Advanced diverted during the term Advanced argued the buyout offer was a reasonable mitigation option and Welding’s refusal was a failure to mitigate, barring recovery Court held a nonbreaching party cannot be compelled to mitigate by surrendering contract rights; requiring a buyout would force relinquishment and is not required
Proper measure of damages (actual lost sales vs. projected expected purchases) Welding: damages measured by actual amount Advanced purchased from another seller during contract term (lost‑volume seller expectation) Advanced: damages should be based on hypothetical expectations of what would have been purchased under dewar deliveries Court held damages should be measured by the injured party’s actual loss (value of the other party’s actual performance lost), not a speculative projection of hypothetical purchases
Whether failure to mitigate is an affirmative defense and its burden Welding: argued mitigation defense must be pled and proved, and steps requiring relinquishment of rights cannot be required Advanced: argued Welding’s refusal to settle/convert justified denial of damages under mitigation principles Court reiterated failure to mitigate is an affirmative defense that must be pled and proved; relinquishment of contractual rights cannot form the basis for mitigation liability
Whether rejecting a settlement/accord can bar all recovery or affect prevailing‑party fees Welding: rejecting buyout should not bar recovery of damages actually suffered; fee issues moot if recovery permitted Advanced: relied on mitigation and settlement rejection as justification to deny damages and fees Court held denying all recovery for refusing a buyout would be improper; rejecting a settlement may have other statutory consequences for fees/costs but cannot eliminate recovery for proven damages caused by breach

Key Cases Cited

  • Fair v. Red Lion Inn, 943 P.2d 431 (Colo. 1997) (duty to mitigate does not require abandoning contractual rights or accepting disadvantageous renegotiation)
  • Publicker Chem. Corp. v. Belcher Oil Co., 792 F.2d 482 (5th Cir. 1986) (cannot mitigate by accepting arrangement conditioned on surrender of rights under repudiated contract)
  • Teradyne, Inc. v. Teledyne Indus., Inc., 676 F.2d 865 (1st Cir. 1982) (rejecting mitigation that requires surrender of breach claims)
  • Stanspec Corp. v. Jelco, Inc., 464 F.2d 1184 (10th Cir. 1972) (no duty to accept modified contract that conditions abandonment of right of action)
  • Stone v. Satriana, 41 P.3d 705 (Colo. 2002) (failure to settle cannot amount to failure to mitigate when settlement would forfeit legal rights)
Read the full case

Case Details

Case Name: U.S. Welding, Inc. v. Advanced Circuits, Inc.
Court Name: Supreme Court of Colorado
Date Published: Jun 18, 2018
Citations: 2018 CO 56; 420 P.3d 278; Supreme Court Case 16SC365
Docket Number: Supreme Court Case 16SC365
Court Abbreviation: Colo.
Log In
    U.S. Welding, Inc. v. Advanced Circuits, Inc., 2018 CO 56