History
  • No items yet
midpage
Tully Construction Co., A.J. Pegno Construction Co., J v. v. Canam Steel
684 F. App'x 24
| 2d Cir. | 2017
Read the full case

Background

  • Tully contracted to supply steel for a New York State Whitestone Bridge project and subcontracted fabrication to Eastern Bridge; Eastern Bridge later sold assets/liabilities to Canam under an Asset Purchase Agreement (APA).
  • Disputes over delayed deliveries led to a Completion Agreement (2007) and later a Delivery Agreement containing arbitration clauses; Tully demanded arbitration against Canam in 2008.
  • After 17 days of hearings and extensive evidence, the arbitrator issued an award (Revised Award) largely in Tully’s favor, awarding roughly $6.88 million to Tully and $366,914 to Canam.
  • Tully moved in district court to confirm the award; Canam moved to vacate, arguing manifest disregard of law, improper contractual interpretation (Letter Agreement and APA), lack of a reasoned award, and erroneous escrow credit handling.
  • The district court confirmed the award and denied vacatur; the Second Circuit affirmed, rejecting Canam’s manifest-disregard, reasoned-award, and escrow arguments.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether arbitrator manifestly disregarded New Hampshire court order (preclusive effect) Canam: NH order precludes liability for pre-APA breaches; arbitrator ignored it Tully: NH language was obiter dicta; arbitrator permissibly treated it as non-preclusive Court: Affirmed arbitrator; no manifest disregard — arbitrator reasonably treated NH language as dicta
Effect/interpretation of the Letter Agreement (timing extension) Canam: Letter Agreement extended delivery schedule; arbitrator miscalculated delay/damages Tully: Letter Agreement was an unenforceable agreement-to-agree; arbitrator reasonably rejected it Court: Affirmed arbitrator; qualified, tentative language supports arbitrator’s conclusion
Whether Canam may be held liable for pre-APA breaches under the APA Canam: Section 2.03(ii) prohibits assuming liabilities for pre-APA breaches Tully: Arbitrator permissibly found Canam responsible for some damages based on evidence and contract interpretation Court: No clear manifest disregard; award could be justified on the factual record and contract interpretation
Whether award was reasoned and whether escrow credit should include earned interest Canam: Award lacked adequate explanation for percentage allocations; escrow credit should include interest Tully: Award provided sufficient reasoning; escrow credit limited to principal per Delivery Agreement Court: Arbitrator issued a reasoned award; escrow credit limited to principal only

Key Cases Cited

  • Kolel Beth Yechiel Mechil of Tartikov, Inc. v. YLL Irrevocable Trust, 729 F.3d 99 (2d Cir.) (standard of review for confirmation/vacatur)
  • Porzig v. Dresdner, Kleinwort, Benson, N.A. LLC, 497 F.3d 133 (2d Cir.) (manifest-disregard standard reviewed de novo)
  • Wallace v. Buttar, 378 F.3d 182 (2d Cir.) (manifest disregard requires more than legal error)
  • STMicroelectronics, N.V. v. Credit Suisse Sec. (USA) LLC, 648 F.3d 68 (2d Cir.) (FAA §9 confirmation framework)
  • D.H. Blair & Co., Inc. v. Gottdiener, 462 F.3d 95 (2d Cir.) (high burden to vacate arbitration award)
  • Duferco Int’l Steel Trading v. T. Klaveness Shipping A/S, 333 F.3d 383 (2d Cir.) (limited grounds for vacatur)
  • T.Co Metals, LLC v. Dempsey Pipe & Supply, Inc., 592 F.3d 329 (2d Cir.) (manifest disregard discussion)
  • Leeward Constr. Co., Ltd. v. Am. U. of Antigua–Coll. of Med., 826 F.3d 634 (2d Cir.) (definition of a reasoned award)
  • Major League Baseball Players Ass’n v. Garvey, 532 U.S. 504 (U.S.) (arbitrator’s improvident factfinding not ground for vacatur)
Read the full case

Case Details

Case Name: Tully Construction Co., A.J. Pegno Construction Co., J v. v. Canam Steel
Court Name: Court of Appeals for the Second Circuit
Date Published: Mar 23, 2017
Citation: 684 F. App'x 24
Docket Number: 16-1324-cv
Court Abbreviation: 2d Cir.