History
  • No items yet
midpage
70 A.3d 1164
D.C.
2013
Read the full case

Background

  • TRG Construction was contracted by D.C. Water to renovate bathrooms at the Central Operations Facility, with a completion deadline of June 13, 2004, later extended to July 31, 2005.
  • TRG requested another extension; D.C. Water demanded a Time Impact Analysis, which TRG delivered late, leading to denial of the extension.
  • D.C. Water issued a Cure Notice alleging numerous deficiencies; TRG refused to fix, asserting work was not substandard and the warranty period had expired.
  • D.C. Water terminated TRG’s contract for convenience under 21 DCMR § 5350.1.1, triggering claims for termination-for-convenience damages and related losses by TRG.
  • TRG asserted various damages: last-invoice payments, bond premium costs, materials left with D.C. Water, and anticipatory profits; D.C. Water sought to deduct its own claims against TRG.
  • The Superior Court granted summary judgment to D.C. Water on several counts; the appellate court remanded for further analysis on termination-for-convenience damages, waiver of timeliness defenses, and delay damages.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Scope of termination-for-convenience damages TRG contends it is entitled to costs for work performed plus a fair profit, net of any valid deductions by D.C. Water. D.C. Water may deduct its own claims against TRG and withhold payments if pre-termination deficiencies/curative issues exist. Remanded for detailed evaluation of damages and potential deductions; summary judgment reversed as to Count IV.
Whether D.C. Water waived timeliness for TRG's delay damages TRG argues D.C. Water waived the 30-day claims deadline by addressing the merits of the claim without raising untimeliness. D.C. Water contends the time limitation is a strict bar unless timely raised. Waiver possible; remanded to determine if D.C. Water's conduct constitutes waiver of § 5346.3 and allows delay-damages recovery.
Recovery for bond retention damages TRG seeks damages for losses due to bond retention and decreased bonding capacity. Damages are speculative and not sufficiently evidenced, with only one unpursued job outside the bond period. Affirmed summary judgment for D.C. Water on Counts I and V; remanded for other issues.

Key Cases Cited

  • Lisbon Contractors, Inc. v. United States, 828 F.2d 759 (Fed.Cir.1987) (government cannot always recover reprocurement costs; constraints on unallowable reductions)
  • Best Foam Fabricators, Inc. v. United States, 38 Fed. Cl. 627 (Fed.Cl. 1997) (termination-for-convenience permits recovery of termination-inventory costs absent gross contractor fault)
  • United Partition Sys., Inc. v. United States, 90 Fed.Cl. 74 (Fed.Cl. 2009) (reprocurement costs and government deductions considerations in termination for convenience)
  • Linan-Faye Const. Co., Inc. v. Housing Auth. of City of Camden, 49 F.3d 915 (3d Cir.1995) (claims and damages framework in termination scenarios; caution against unreasonable recoveries)
  • Copco Steel & Eng’g Co. v. United States, 341 F.2d 590 (Ct.Cl.1965) (considerations on government deductions related to defective work)
  • Hoel-Steffen Const. Co. v. United States, 456 F.2d 760 (Ct.Cl.1972) (notice and adjustment principles in contract claims and waiver implications)
Read the full case

Case Details

Case Name: TRG Construction Inc. v. District of Columbia Water & Sewer Authority
Court Name: District of Columbia Court of Appeals
Date Published: May 9, 2013
Citations: 70 A.3d 1164; 2013 D.C. App. LEXIS 257; 2013 WL 1907452; No. 11-CV-896
Docket Number: No. 11-CV-896
Court Abbreviation: D.C.
Log In
    TRG Construction Inc. v. District of Columbia Water & Sewer Authority, 70 A.3d 1164