History
  • No items yet
midpage
Treadwell Corporation v. United States
133 Fed. Cl. 371
| Fed. Cl. | 2017
Read the full case

Background

  • Navy issued RFP for Low Pressure Electrolyzer (LPE) systems for submarines (IDIQ, lowest-priced technically acceptable). Proposals were evaluated on Technical Capability, Corporate Experience, and Past Performance.
  • Treadwell and Hamilton were the only offerors ultimately found technically acceptable; Hamilton submitted the lowest-priced technically acceptable bid and received the award on July 13, 2016.
  • RFP delivery terms required first-article testing and contemplated that production/delivery of simulators and production units would follow first-article approval; FAR 52.209-3 and FAR 9.305 were incorporated and warned that production prior to approval is at contractor’s risk.
  • After award, the Navy issued Delivery Order 0001 and later (Nov. 2, 2016) modified the delivery schedule to extend deadlines and clarify that production-unit delivery would occur 12 months after first-article approval.
  • Treadwell sued in the Court of Federal Claims seeking a preliminary injunction and stay of Hamilton’s performance, asserting multiple procurement defects (nonresponsiveness/technical acceptance, unequal treatment, improper post-award modification/cardinal change, unlawful award-with-intent-to-modify, failure of meaningful discussions).
  • The court found the administrative record sufficient, declined to supplement it with certain post hoc documents proffered by Treadwell, and denied the preliminary injunction.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Hamilton's proposal was nonresponsive / not technically acceptable because it did not commit to the strictest simultaneous delivery timeline Treadwell: Hamilton failed to show it could meet the most aggressive 15-month simultaneous delivery schedule required by solicitation and thus was nonresponsive Gov/Hamilton: RFP did not require simultaneous delivery; delivery orders and first-article approval timing were discretionary; Hamilton agreed to solicitation terms and committed to 15-month qualification Court: RFP did not require simultaneous delivery; Hamilton’s proposal was responsive and technically acceptable
Whether Navy treated offerors unequally on delivery-schedule evaluation Treadwell: Navy relaxed schedule requirements for Hamilton while holding Treadwell to a stricter timeline Gov/Hamilton: Both offers were evaluated per RFP criteria; Treadwell’s proposed aggressive schedule exceeded RFP requirements and raised no evaluative issue Court: No unequal treatment shown; record shows equal evaluation consistent with RFP
Whether post-award modification to delivery schedule was a cardinal change (outside scope) or award-with-intent-to-modify Treadwell: Modification materially altered scope and showed intent to modify after award (violating procurement rules) Gov/Hamilton: Modification clarified delivery timing within scope (RFP left issuance timing to government); FAR clauses and RFP contemplated sequencing; no recompetition required Court: Modification fell within original procurement scope (not a cardinal change); no evidence of bad faith intent to award with intent to modify
Whether preliminary injunctive relief (stay of performance) was warranted Treadwell: Without a stay it will suffer irreparable harm and likely would have been awarded but for alleged errors Gov/Hamilton: Treadwell delayed bringing action; Hamilton performance underway; public interest and Navy readiness weigh against a stay; record undermines plaintiff’s likelihood of success Court: Treadwell failed to show irreparable harm and is unlikely to succeed on merits; injunction denied

Key Cases Cited

  • Banknote Corp. of Am. v. United States, 365 F.3d 1345 (Fed. Cir.) (establishes standards for overturning procurement decisions under APA)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (U.S.) (agency action arbitrary and capricious where important aspects ignored or explanation runs counter to evidence)
  • Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402 (U.S.) (presumption of regularity in agency decisions and focus on administrative record)
  • Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374 (Fed. Cir.) (limits on supplementing the administrative record)
  • PGBA, LLC v. United States, 389 F.3d 1219 (Fed. Cir.) (four-factor test for preliminary injunctions in bid protests)
  • AT&T Communications v. Wiltel, Inc., 1 F.3d 1201 (Fed. Cir.) (analysis of cardinal change and scope of original procurement)
Read the full case

Case Details

Case Name: Treadwell Corporation v. United States
Court Name: United States Court of Federal Claims
Date Published: Jul 19, 2017
Citation: 133 Fed. Cl. 371
Docket Number: 17-287C
Court Abbreviation: Fed. Cl.