History
  • No items yet
midpage
Total Industrial Plant Services, Inc. v. Turner Industries Group, LLC.
2013 MT 5
| Mont. | 2013
Read the full case

Background

  • TIPS, an Oklahoma contractor, had a fixed-price subcontract with Turner for insulation work at a CHS refinery in Montana; work was delayed by weather and other subs, leading to a switch to time-and-materials invoicing in February 2008; TIPS submitted change orders for some increases, which Turner paid, but TIPS claims additional compensation for pre-February 4 costs and inefficiencies; TIPS filed a lien in September 2008 after Turner withheld further payments; Turner posted a substitution bond; District Court granted partial summary judgment for retainage return and denied other relief; bench trial in 2011 resulted in a verdict in Turner's favor on all counts, with decisions on lien timeliness and retainage appeal; on appeal, TIPS challenges contract-based remedies, lien timeliness, retainage, and costs; Court of Appeals reviews de novo and for clearly erroneous findings of fact; final opinion affirmed in part, reversed in part, remanded on prejudgment interest.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the court err denying quantum meruit or unjust enrichment claims? TIPS asserted oral promises and pre-February 4 costs warranted compensation. Turner argued only written change orders could trigger extra pay under fixed price. Yes; quantum meruit/undue enrichment claim rejected; no basis under express contract.
Was Turner the prevailing party entitled to costs? TIPS contends it prevailed on retainage and partial summary judgment. Turner argues no final judgment on merits and denial of prevailing party status. No; court upheld Turner not prevailing party; but reversed on prejudgment interest issue and remanded.
Was TIPS's lien time-barred under § 71-3-535, MCA? TIPS contends lien timely under ongoing work. Work after June 25, 2008 under CHS contract tolls no Montana lien. Lien barred; 91 days after final furnishing under Turner contract; not tolled by CHS work.
Did the district court err in granting partial summary judgment on retainage and ordering return? Retention owed pending release of lien; bond discharge should release lien. Bond discharge replaced lien; retainage should be released. Reversed; prejudgment interest on retainage awarded and remanded for value of interest.
Was Turner’s bill of costs properly filed under § 25-10-501, MCA? Costs allowed by contract subdivision; procedural compliance required by statute. Contract displaces § 25-10-501; filing irregularities cured by contract. No; § 25-10-501 applies; $. bill of costs timely filed given notice date; not abuse of discretion.

Key Cases Cited

  • Rodgers v. Mony Life Ins. Co., 2005 MT 290 (2005 MT 290) (costs on claims for money or damages; statutory costs rule applies)
  • Dalakow v. Geery, 132 Mont. 457 (1957) (oral modifications evidence under contract)
  • Lewistown Miller Constr. Co. v. Martin, 2011 MT 325 (2011 MT 325) (clearly erroneous standard; contract interpretation)
  • Estate of Pruyn v. Axmen Propane, Inc., 2009 MT 448 (2009 MT 448) (quasi-contract claims require absence of express contract)
  • Frank J. Trunk & Son v. De Haan, (Mont. 1964) (1964) (timing of lien continuation under multiple contracts)
  • Helena Steam-Heating & Supply Co. v. Wells, (Mont. 1895) (1895) (early lien timing principles for construction projects)
  • Sperry Rand Corp. v. United States, 201 Ct. Cl. 169 (1973) (fixed-price contract risk allocation to subcontractor)
  • E.C.A. Envtl. Management Servs. v. Toenyes, 208 Mont. 336 (1984) (prevailing party; awards not limited to monetary judgments)
  • Roseneau Foods v. Coleman, 140 Mont. 572 (1962) (costs recoverable outside strict statutory list by stipulation)
Read the full case

Case Details

Case Name: Total Industrial Plant Services, Inc. v. Turner Industries Group, LLC.
Court Name: Montana Supreme Court
Date Published: Jan 15, 2013
Citation: 2013 MT 5
Docket Number: DA 11-0769
Court Abbreviation: Mont.