History
  • No items yet
midpage
Thunderstruck Signs
ASBCA No. 61027
| A.S.B.C.A. | Aug 16, 2017
Read the full case

Background

  • Contract FA4855-15-P-0136 awarded to Thunderstruck Signs (firm-fixed price, $47,791.16) to supply and install six facility signs for Cannon AFB; original delivery 16 Oct 2015.
  • Contract incorporated FAR 52.212-4 (commercial items) including excusable delays and termination-for-cause provisions.
  • Government delayed providing artwork until 5 Nov 2015; parties later executed a bilateral extension to 15 June 2016; signs ultimately completed and shipped to New Mexico in late July 2016.
  • Government issued show-cause and stop-work communications in Jan–Aug 2016; CO set a final performance deadline of 14 Sept 2016 and warned that failure to meet it would result in termination for cause.
  • Thunderstruck failed to deliver/install by 14 Sept 2016 (signs had been stored off-base and moved to a more distant facility), CO terminated for cause on 8 Nov 2016; appellant appealed seeking contract price plus cancellation charge.
  • Board considered only whether the default termination was proper under the contract and precedent, and heard the appeal on the written record without a hearing.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the government justified termination for default for failure to deliver/install by final date Thunderstruck: government conduct (late artwork, refusal to accept delivery in early Aug, stop-work order, refusal to coordinate electrician) caused or excused the delay Air Force: set a reasonable final deadline (14 days) after extensions; Thunderstruck agreed and still failed to perform Held for government: prima facie default; termination justified because contractor failed to meet reasonable final deadline and prior delays were waived by agreeing to new schedule
Whether pre-deadline government-caused delays excused failure to meet the new final delivery date Thunderstruck: earlier government delays and refusal to permit on-base delivery made timely performance impossible Air Force: earlier delays were superseded by the mutually agreed or reasonable new delivery date; contractor must meet new schedule Held: earlier delays were not excusing because parties agreed (or contractor acquiesced) to a new schedule; contractor bears responsibility to meet it
Whether the CO's unilateral setting of a new deadline must consider contractor capabilities Thunderstruck: unilateral deadline was unreasonable given logistics and subcontractor availability Air Force: deadline was reasonable given contractor's assurances and signs' completion Held: the 14‑day final deadline was reasonable given contractor confirmations and completed status of signs
Whether termination decision was arbitrary, capricious, or an abuse of discretion Thunderstruck: CO's communications and actions (including contacting subcontractor) were arbitrary and prevented performance Air Force: actions aimed to preserve contract performance; final opportunity given before termination Held: termination was not arbitrary; Board denied appeal

Key Cases Cited

  • Lisbon Contractors v. United States, 828 F.2d 759 (Fed. Cir.) (default termination is a drastic remedy and government bears burden to justify)
  • J.D. Hedin Constr. Co. v. United States, 408 F.2d 424 (Ct. Cl.) (standards on imposing default termination)
  • De Vito v. United States, 413 F.2d 1147 (Ct. Cl.) (government must give a reasonable new delivery schedule when acting unilaterally)
  • International Telephone & Telegraph Corp. v. United States, 509 F.2d 541 (Ct. Cl.) (unilateral scheduling must be reasonable considering contractor's capabilities)
Read the full case

Case Details

Case Name: Thunderstruck Signs
Court Name: Armed Services Board of Contract Appeals
Date Published: Aug 16, 2017
Docket Number: ASBCA No. 61027
Court Abbreviation: A.S.B.C.A.