Thomas R. Crowel v. Marshall County Drainage Board
971 N.E.2d 638
Ind.2012Background
- crowel owns 26 acres within Arm #7 watershed of Myers Drain in Marshall County; project plans to reconstruct Arm #7, widening the drain and relocating it, at estimated cost ~$114,474; Board classified Arm #7 as an urban drain and planned a 20-year assessment period; notice and public hearing were conducted; Crowel objected claiming no benefit since his land at high end, with prior adequate drainage, and that his private tile drain blocked by gas line caused any standing water; surveyor testified Crowel’s land contributes to lower-end flooding and thus it is benefited; trial court upheld Board’s decision; Court of Appeals reversed; Supreme Court granted transfer and upheld Board’s assessment with extensive statutory analysis; court holds all land draining into a regulated drain is benefited, and the schedule of assessments may reflect benefits even if some parcels receive less benefit; implications involve statutory interpretation of I.C. §§ 36-9-27-50, -112, -69.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Crowel’s land is benefited by Arm #7 because surface water from his land flows into the drain. | Crowel: no benefit since his land does not flood. | Board: every land draining into the drain is benefited; Crowel contributes to downstream flooding. | Yes; Crowel is benefited because his surface water flows into the regulated drain. |
| Whether the assessment schedule fairly apportions costs based on benefits as required by statute. | Hubenthal/Whitley: uniform per-acre costs without site-specific benefits invalid. | Clouse/Schrader show tiered per-acre approach acceptable after evaluating benefits. | Three-tiered per-acre schedule upheld when benefits were considered. |
| Whether de novo review was appropriate for the claim that benefits were excessive or damages inadequate. | Under I.C. § 36-9-27-107(a) de novo review should apply to excessive benefits. | Board's record should be reviewed on record, not de novo; hybrid option exists. | Court affirmed Board’s determination; de novo review not required here. |
| Whether Crowel’s claim that benefits attributed to his land were excessive is reviewable and reversible. | Excessive benefits challenge should be reviewable. | Procedural pathway under subsection (b) limits review to record; not de novo. | Excessiveness challenge not reversible; Board’s finding upheld. |
Key Cases Cited
- Hubenthal v. Crain, 239 Ind. 646 (1959) (apportionment must reflect benefits; simple watershed approach invalid)
- Hinesley v. Crum, 175 Ind. 10 (1910) (lands may be benefited even if already drained)
- Culbertson v. Knight, 152 Ind. 121 (1899) (land at high end may be benefited by drainage)
- Lipes v. Hand, 104 Ind. 503 (1885) (special-benefits concept; indirect benefits allowed)
- Schrader v. Porter County Drainage Bd., 880 N.E.2d 304 (Ind. Ct. App. 2008) (uniform per-acre assessments allowed when benefits examined)
- Clouse v. Noble Cnty. Drainage Bd., 809 N.E.2d 849 (Ind. Ct. App. 2004) (uniform per-acre maintenance where benefits considered)
- Whitley, Noble & Allen Joint Drainage Bd. v. Tschantz, 461 N.E.2d 1146 (Ind. Ct. App. 1984) (uniform per-acre assessment invalid when benefits not considered)
