History
  • No items yet
midpage
The Metropolitan Government of Nashville And Davidson County v. Wood Ridge Development, Inc.
M2015-01556-COA-R3-CV
| Tenn. Ct. App. | Nov 4, 2016
Read the full case

Background

  • Wood Ridge Development, Inc. (WRD) was required by Metro to complete public infrastructure for Carothers Crossing; WRD and Lexon Insurance Company (Lexon) executed three "performance agreements" (each labeled with a Bond #) in which WRD was principal and Lexon acted as surety.
  • WRD failed to complete the improvements; Metro demanded payment under the performance agreements and sued WRD and Lexon to enforce them.
  • Lexon denied liability to Metro, filed a cross-claim against WRD, and a third-party claim against Wood Ridge Investments and individual members (the Indemnitors), based on a separate General Agreement of Indemnity they had signed in 2007.
  • Lexon settled with Metro and then moved for summary judgment against the Indemnitors seeking indemnification under the indemnity agreement; the Indemnitors moved for summary judgment arguing no separate bond was ever issued and thus no indemnity obligation arose.
  • The trial court granted Lexon’s summary judgment and denied the Indemnitors’; the court found the performance agreements constituted surety undertakings within the scope of the indemnity agreement and that Indemnitors breached by failing to indemnify and post collateral.
  • The Court of Appeals affirmed, holding Lexon’s execution of the performance agreements constituted "undertakings or other writings obligatory in nature of a bond" under the indemnity agreement, so Indemnitors were liable as a matter of law.

Issues

Issue Lexon (Plaintiff) Argument Indemnitors (Defendant) Argument Held
Whether the trial court complied with Tenn. R. Civ. P. 56.04 Order contained factual findings and legal conclusions stating grounds for grant/denial Order lacked required stated legal grounds; was a party-drafted rubber-stamp Court complied with Rule 56.04; findings and conclusions were adequate and reflected court’s decision
Whether the performance agreements are "bonds/undertakings" within the indemnity agreement Performance agreements signed by Lexon as surety are "undertakings or other writings obligatory in the nature of a bond" and trigger indemnity No separate, statutorily defined bond was issued under Metro regulations, so indemnity condition never arose Held that execution of the performance agreements operated as the contemplated undertaking/bond and triggered indemnity
Whether Indemnitors’ obligation required a prior judicial finding of WRD default or Lexon payment under a formal bond Lexon had claim made, defended, settled, incurred loss and thus indemnity obligations arose under contract Indemnitors argued no indemnity until formal default finding or payment under a separate bond instrument Court found WRD admission of incomplete work and Lexon’s expenditures/settlement sufficient; no separate judicial default finding or separate bond document required
Whether judicial estoppel barred Lexon from seeking indemnity after settling Metro’s claim Settlement does not contradict Lexon’s indemnity claim; Lexon consistently maintained indemnity rights Settlement is inconsistent with prior positions (no bond issued) and should estop Lexon Judicial estoppel inapplicable; settlement is not a sworn contradictory statement and prerequisites for estoppel not met

Key Cases Cited

  • Pitt v. Tyree Org. Ltd., 90 S.W.3d 244 (Tenn. Ct. App. 2002) (summary judgment appropriate for pure contract interpretation)
  • Guiliano v. Cleo, Inc., 995 S.W.2d 88 (Tenn. 1999) (trial court’s contract interpretation not presumptively correct on appeal)
  • Planters Gin Co. v. Fed. Compress & Warehouse Co., Inc., 78 S.W.3d 885 (Tenn. 2002) (unambiguous contract language controls)
  • Cracker Barrel Old Country Store, Inc. v. Epperson, 284 S.W.3d 303 (Tenn. 2009) (judicial estoppel applies only to sworn statements contradicted later)
Read the full case

Case Details

Case Name: The Metropolitan Government of Nashville And Davidson County v. Wood Ridge Development, Inc.
Court Name: Court of Appeals of Tennessee
Date Published: Nov 4, 2016
Docket Number: M2015-01556-COA-R3-CV
Court Abbreviation: Tenn. Ct. App.