History
  • No items yet
midpage
493 F.Supp.3d 585
S.D. Tex.
2020
Read the full case

Background

  • Three private developers (Binnacle, Lone Trail, SSLT) contracted with R. Hassell Properties to perform roadway/infrastructure work in Galveston County.
  • Hanover issued payment and performance bonds for those projects and required Hassell to sign an indemnity agreement assigning to Hanover Hassell’s contract rights and remaining balances upon default.
  • Hassell defaulted, Hanover paid bond claims (~$437,000) and received assignment of Hassell’s contract balances (Hanover says ~$570,000 remain).
  • Each construction contract contained a $2,500 per diem liquidated-damages clause for late completion; defendants claim about $900,000 in accrued liquidated damages and seek to offset Hanover’s recovery.
  • Hanover moved for partial summary judgment that the clauses are unenforceable penalties; defendants argued the clauses are authorized as “economic disincentives” under Tex. Water Code §49.271(e) or otherwise enforceable.
  • The court held the Water Code did not apply and, under Texas common law, the $2,500/day clauses are unenforceable penalties and granted Hanover’s motion.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does Tex. Water Code §49.271(e) govern these contracts? Water Code doesn't apply because these are private contracts and not contracts "made by the board" or with a district. Contracts benefit a municipal utility district and thus are "district contracts" authorizing economic disincentives; parties may incorporate statutory rights. Water Code does not apply; "district contract" means a contract with or by the district, and mere benefit or parroting of the statute is insufficient.
Are the $2,500/day liquidated-damages provisions unenforceable penalties? Clauses are penalties: no study or reasonable forecast supports $2,500/day and actual damages are essentially zero, so the charge is grossly disproportionate. Clauses are enforceable (and authorized by Water Code); otherwise defendants did not meaningfully rebut Hanover’s facts. Clauses are unenforceable penalties under Texas law (fails reasonable-forecast and proportionality inquiries); summary judgment for Hanover.

Key Cases Cited

  • Atrium Med. Ctr., LP v. Hous. Red C LLC, 595 S.W.3d 188 (Tex. 2020) (reaffirming test for liquidated damages and when disparity renders clause unenforceable)
  • Phillips v. Phillips, 820 S.W.2d 785 (Tex. 1991) (two-factor test: difficulty of estimation and reasonable forecast of just compensation)
  • Garden Ridge, L.P. v. Advance Int’l., Inc., 403 S.W.3d 432 (Tex. App.—Houston [14th Dist.] 2013) (liquidated damages unenforceable where amount was unsupported and actual damages were zero)
  • Loggins Constr. Co. v. Stephen F. Austin State Univ. Bd. of Regents, 543 S.W.2d 682 (Tex. App.—Tyler 1976) (per diem liquidated damages held penalty where actual damages were small)
  • Caudill v. Keller Williams Realty, Inc., 828 F.3d 575 (7th Cir. 2016) (applying Texas law: liquidated-damages clause unenforceable where plaintiff sustained no actual damages)
  • Stewart v. Basey, 245 S.W.2d 484 (Tex. 1952) (Texas principle limiting contractual damages to just compensation)
Read the full case

Case Details

Case Name: The Hanover Insurance Company v. Binnacle Development, LLC f/k/a Binnacle Development and Construction, LLC
Court Name: District Court, S.D. Texas
Date Published: Oct 6, 2020
Citations: 493 F.Supp.3d 585; 3:19-cv-00111
Docket Number: 3:19-cv-00111
Court Abbreviation: S.D. Tex.
Log In