THE CENTECH GROUP, INC. v. United States
1:19-cv-01752
| Fed. Cl. | Mar 11, 2025
Read the full case

Background

  • CENTECH, a government contractor, sued the U.S. Air Force for breach of contract after the Air Force canceled a previously approved Bill of Materials (BOM) for communications infrastructure at Vandenberg Air Force Base.
  • CENTECH had acquired the BOM materials through subcontractor Iron Bow, following explicit government approval, and incurred nearly $2 million in costs, plus expenses for storage, transport, and insurance after the Air Force refused to accept or pay for the materials.
  • The Air Force halted the installation due to concerns over labor costs, approved only partial invoicing for delivered materials, and instructed CENTECH to cancel the remainder of the BOM order.
  • CENTECH submitted claims for damages under the Contract Disputes Act, including the cost of materials, related handling expenses, and attorneys’ fees incurred during negotiation.
  • The matter is before the Court on cross-motions for summary judgment regarding breach, damages, and entitlement to attorneys’ fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Duty to reimburse for BOM materials USAF approved purchase; CENTECH complied with contract; entitled to reimbursement for all materials Materials weren't ultimately required/used; full reimbursement not owed USAF breached duty by failing to reimburse for all government-approved materials
Effect of delivery/invoicing compliance Failure to deliver or invoice via proper system was technical, not material; USAF prevented completion Materials were neither delivered nor accepted; contract not complied with Delivery/acceptance requirements excused as USAF hindered performance; noncompliance not material breach
Damages for handling (storage/transport/insurance) Costs arose naturally from breach; were foreseeable and directly caused by USAF’s failure to pay Costs are indirect/collateral; not directly caused by USAF’s breach Costs were foreseeable and directly caused by breach; genuine factual disputes over mitigation remain
Attorneys’ fees as contract administration costs Fees were for pre-claim negotiations, reasonable under FAR Fees relate to Iron Bow (no longer a subcontractor) and are mostly for claim/litigation, thus unallowable Factual dispute: unclear if fees were for negotiation vs. claim prosecution; no summary judgment

Key Cases Cited

  • San Carlos Irrigation & Drainage Dist. v. United States, 877 F.2d 957 (Fed. Cir. 1989) (sets forth requirements for breach of contract claim: contract, duty, breach, damages)
  • Coast Fed. Bank, FSB v. United States, 323 F.3d 1035 (Fed. Cir. 2003) (plain language of unambiguous contracts governs)
  • LAI Servs., Inc. v. Gates, 573 F.3d 1306 (Fed. Cir. 2009) (plain contract language controls interpretation)
  • Robinson v. United States, 305 F.3d 1330 (Fed. Cir. 2002) (non-breaching party must act reasonably to mitigate damages)
  • Bill Strong Enters., Inc. v. Shannon, 49 F.3d 1541 (Fed. Cir. 1995) (standard for distinguishing allowable contract administration costs from unallowable claim prosecution costs)
Read the full case

Case Details

Case Name: THE CENTECH GROUP, INC. v. United States
Court Name: United States Court of Federal Claims
Date Published: Mar 11, 2025
Docket Number: 1:19-cv-01752
Court Abbreviation: Fed. Cl.