365 P.3d 442
Mont.2015Background
- Teton Co-Operative Canal Company (Teton Canal) filed an April 18, 1890 notice claiming 3,000 inches from the Teton River "for gathering said water in a reservoir"; an April 29, 1891 notice claimed 10,000 inches for "irrigating, reservoirs and other purposes."
- An 1892 GLO plat shows two canals: the Glendora Canal (matching the 1890 diversion point) running to Glendora Reservoir, and the Eureka Canal (matching the 1891 diversion point) running to the Eureka site about two miles upstream.
- The 1891 notice claims (including rights tied to the Eureka Canal) were extinguished by a 1908 Perry decree; the Perry court preserved only the 1890-based 3,000-inch right.
- Teton Canal and the State Water Conservation Board built Eureka Reservoir in 1936–37; Teton Canal later claimed Eureka storage under a 1982 statement of existing rights listing an April 18, 1890 priority date for Eureka storage.
- The Water Court treated Eureka off‑stream storage as part of the 1890 notice; Teton Reservoir objected, arguing the Eureka storage was tied to the nullified 1891 claim, and that Teton Canal lacked diligence to relate the 1936–37 works back to 1890.
- The Montana Supreme Court reversed: it held the record shows Glendora (not Eureka) was the reservoir contemplated by the 1890 notice, the Eureka works arose from the 1891/1921/1936 efforts, and Teton Canal failed to proceed with reasonable diligence to relate 1930s construction back to 1890.
Issues
| Issue | Plaintiff's Argument (Teton Canal) | Defendant's Argument (Teton Reservoir) | Held |
|---|---|---|---|
| Whether off‑stream storage at Eureka is included in the April 18, 1890 notice | 1890 notice and later conduct show intent to include Eureka; diversion point could be moved and storage consolidated under 1890 claim | Eureka storage was claimed under the 1891 notice (extinguished by Perry) and not part of 1890 | Court: No — Eureka was not within the 1890 notice; 1891/1921/1936 filings govern Eureka |
| Whether Teton Canal developed the 1890 diversion point | The company’s predecessors built and used diversion works that support relation back | Objector argued 1890 diversion was not developed at the described point | Court: 1890 diversion was developed at Glendora (not Eureka); Water Court’s contrary finding was clearly erroneous |
| Whether Teton Canal exercised reasonable diligence to perfect Eureka storage so as to relate back to 1890 | Even if diversion could be shifted, company pursued reservoir development efforts across decades justifying relation back | Teton Canal did not steadily prosecute reservoir construction; meaningful efforts only in mid‑1930s | Court: No reasonable diligence before mid‑1930s; cannot relate 1936–37 completion to 1890 |
| Appropriate priority date for Eureka Reservoir | (No alternative date argued on appeal) | Eureka should receive a junior priority based on the 1936 Declaration or later filings | Court: Remanded to Water Court to assign a new (later) priority date consistent with findings |
Key Cases Cited
- Intake Water Co. v. Mont. Dep’t of Natural Res. & Conserv., 171 Mont. 416, 558 P.2d 1110 (discusses relation‑back and the diligence standard under the 1885 appropriation statute)
- Bailey v. Tintinger, 45 Mont. 154, 122 P. 575 (approach to intent and requirements for completed appropriation)
- Power v. Switzer, 21 Mont. 523, 55 P. 32 (importance of claimant’s intent in water appropriations)
- Wheat v. Cameron, 64 Mont. 494, 210 P. 761 (intent at time of appropriation assessed by acts and circumstances)
