History
  • No items yet
midpage
Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C.
2:16-cv-01131
E.D. La.
Oct 2, 2017
Read the full case

Background

  • Team Contractors contracted with Waypoint to renovate seven floors of the Hyatt House in New Orleans; HCA was the architect and subcontracted MEP design to KLG.
  • HCA delivered MEP plans (KLG) that contained code noncompliance (ventilation, omitted smoke dampers); construction had already begun when defects were discovered.
  • Waypoint issued construction change directives requiring removal and reinstallation of defective MEP work, which Team says caused additional work, recurring expenses, and an extended performance period.
  • Team’s damages expert applied the Eichleay formula to calculate extended home office overhead damages for the alleged delay.
  • Defendants (HCA, KLG successor, Beach, Lundstrum) moved for partial summary judgment arguing Team cannot meet Eichleay’s prerequisites (no suspension/stoppage); Team responded with testimony asserting a functional stoppage or significant slowdown.
  • The court denied summary judgment, finding disputed material facts as to whether work stopped or significantly slowed and whether Team was on standby, so Eichleay entitlement is a factual question for trial.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Entitlement to extended home office overhead under Eichleay Team says MEP corrections caused delay, additional overhead, and a requirement to remain on standby, warranting Eichleay damages Defendants say there was no suspension or stoppage; work continued (supervisors/subcontractors remained busy), so Eichleay prerequisites not met Denied summary judgment — genuine disputes of material fact exist about stoppage/standby and damages entitlement
Degree of work stoppage required Team contends a "functional" stoppage/ significant slowdown suffices Defendants assert lack of total stoppage defeats Eichleay recovery Court adopts federal view that total stoppage not required; significant slowdown or functional stoppage can suffice; factual question for trial
Applicability of Eichleay in private-contract context Team applied Eichleay formula to calculate overhead damages Defendants did not contest Eichleay’s applicability here; instead challenged proof of prerequisites Court assumed Eichleay may apply and focused on prerequisites; did not foreclose private-contract use but required plaintiff to prove entitlement at trial
Appropriateness of summary judgment on damages Team relies on deposition and expert opinion showing slowdown and overhead costs Defendants relied on deposition testimony they say shows no stoppage and ongoing work Summary judgment improper because factual disputes about stoppage, standby, and causation remain for jury/trier of fact

Key Cases Cited

  • Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment standard)
  • Anderson v. Liberty Lobby, 477 U.S. 242 (standard for genuine issue of material fact)
  • First Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S. 253 (summary judgment jurisprudence)
  • Gilchrist Constr. Co., LLC v. State, Dep’t of Transp. & Dev., 166 So. 3d 1045 (La. App. 1 Cir. 2015) (Louisiana’s three-prong Eichleay prerequisites and reluctance to broaden Eichleay)
  • JMR Constr. Corp. v. United States, 117 Fed. Cl. 436 (Fed. Cl. 2014) (Eichleay recovery permissible where work stopped or significantly slowed; minor tasks do not defeat standby)
  • P.J. Dick Inc. v. Principi, 324 F.3d 1364 (Fed. Cir. 2003) (Eichleay analysis: work slowed can satisfy standby)
  • Altmayer v. Johnson, 79 F.3d 1129 (Fed. Cir. 1996) (Eichleay jurisprudence)
Read the full case

Case Details

Case Name: Team Contractors, L.L.C. v. Waypoint NOLA, L.L.C.
Court Name: District Court, E.D. Louisiana
Date Published: Oct 2, 2017
Docket Number: 2:16-cv-01131
Court Abbreviation: E.D. La.