midpage
Projects
Sign in to see your projects.
2018 Ohio 1859
Ohio Ct. App.
2018
Read the full case

Background

  • Servpro (defendant) hires subcontractor Tackle (plaintiff) for restoration work on multiple projects; Tackle sued for $6,320.13 for five projects.
  • Parties agreed Servpro owed amounts on Upper Trent Way, Holman, Peeks, and Adams projects; dispute centered on Kimball project (house restoration).
  • Tackle invoiced $8,120.66 for Kimball; Servpro credited $6,616.81 for work not done and had paid Tackle $2,000. Servpro claimed lost profit/overhead of $3,421.08 after homeowner fired Servpro when job remained incomplete.
  • Magistrate found Tackle failed to complete Kimball wrongfully, that failure caused Servpro to lose the project, and deducted Servpro’s $3,421.08 loss as a set-off, resulting in Tackle owing Servpro $3,917.23 on Kimball.
  • Netting all projects, magistrate recommended judgment for Tackle of $2,284.41; trial court adopted decision. Tackle appealed, arguing manifest-weight error as to Kimball findings and entitlement to prejudgment interest.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Servpro was obligated to purchase/baseboard-front costs for Kimball Tackle: Servpro agreed to "front" money for the baseboard and thus was obligated Servpro: "Fronting" is discretionary courtesy; no agreement to fund baseboard Court: No obligation shown; trial court did not lose its way
Whether Tackle’s failure to finish Kimball was wrongful Tackle: Left because Servpro refused to pay for baseboard, so failure not wrongful Servpro: Tackle was contractually responsible for supplying/installing baseboard Court: Failure was wrongful; record supports finding
Whether Tackle’s failure caused Servpro to lose the project Tackle: Servpro’s refusal to pay caused the loss Servpro: Homeowner fired Servpro because Tackle did not install acceptable baseboard Court: Causal link found; trial court’s finding upheld
Whether Servpro’s lost profit/overhead ($3,421.08) was proven Tackle: Insurance estimate and returns imply smaller lost profit; alternate calculation shows less loss Servpro: Insurer’s estimate allocated $3,421.08 profit/overhead and Pedtke testified he lost that amount Court: Amount reasonable and supported by testimony and insurer estimate; finding not against manifest weight
Whether Tackle is entitled to prejudgment interest under R.C. 1343.03(A) Tackle: Claim accrued Sept. 1, 2016; prejudgment interest due Servpro/Trial court: No request/motion for prejudgment interest made below; money due/payable unclear pre-judgment Court: Denied—trial court did not err in refusing interest not requested and where due date was disputed

Key Cases Cited

  • State v. Thompkins, 78 Ohio St.3d 380 (establishes manifest-weight standard applied in civil cases)
  • Eastley v. Volkman, 132 Ohio St.3d 328 (same manifest-weight framework; deference to factfinder credibility)
  • Crawford v. Hawes, 995 N.E.2d 966 (2d Dist.) (applies Thompkins/Eastley standard to civil appeals)
  • Kosier v. DeRosa, 169 Ohio App.3d 150 (lost-profit determination is question of fact)
  • TJX Cos., Inc. v. Hall, 183 Ohio App.3d 236 (amount of damages may be reasonably estimated; exactness not required)
  • State v. DeHass, 10 Ohio St.2d 230 (credibility determinations are for the trier of fact)
Read the full case

Case Details

Case Name: Tackle Constr. Group, L.L.C. v. Pedtke Ents., Inc.
Court Name: Ohio Court of Appeals
Date Published: May 11, 2018
Citations: 2018 Ohio 1859; 113 N.E.3d 980; 27813
Docket Number: 27813
Court Abbreviation: Ohio Ct. App.
Log In