History
  • No items yet
midpage
295 P.3d 62
Or. Ct. App.
2012
Read the full case

Background

  • Plaintiff is a Portland church and contracted with a general contractor to construct the facility’s first phase.
  • Defendants include the general contractor and several subcontractors who worked on the facility, with post-construction changes continuing after 1999.
  • Plaintiff began religious services in February 1999 and held a dedication in March 1999; construction activities continued, including system and landscaping changes.
  • Plaintiff filed suit on March 16, 2009, asserting negligence and negligence per se based on alleged construction defects.
  • The trial court granted summary judgment to defendants, holding claims time barred under accrual and repose statutes.
  • On appeal, the court reverses summary judgment, finding genuine issues of material fact regarding accrual and 10-year repose timing under ORS 12.135.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether accrual began under the contract clause Armstrong argues accrual runs from substantial completion date certified by architect. General contractor contends accrual begins at substantial completion per contract, earlier date. Genuine issues preclude summary judgment on accrual date.
Whether ORS 12.135 applies as the repose statute Claims arise from construction and are within ORS 12.135(1) 10-year repose. Subcontractors argue ORS 12.115 applies; or ORS 12.135 controls as the specific statute. ORS 12.135 applies; governs repose for this construction.
Whether plaintiff's written acceptance occurred to trigger ORS 12.135(3) timing Plaintiff accepts facility in writing when substantial completion is achieved. No written acceptance shown; repose begins upon written acceptance or when maintenance responsibilities shift. There is a factual dispute about written acceptance and timing.
Whether the subcontractors are barred by the written-acceptance framework and timelines Not all work accepted; substantial work continued after 1999, delaying acceptance. Once substantial completion or acceptance occurs, repose bars claims after 10 years. Trial court erred; summary judgment improper for subcontractors due to unresolved acceptance timing.

Key Cases Cited

  • Lozano v. Schlesinger, 191 Or App 400 (2004) (ORS 12.135(1) applies to construction claims; predecessor analysis cited)
  • Kambury v. DaimlerChrysler Corp., 334 Or 367 (2002) (specific repose statutes control over general negligence provisions)
  • Andres v. American Standard Ins. Co., 205 Or App 419 (2006) (contract interpretation honors parties' definitions in construction disputes)
  • Fredericks v. Universal Underwriters Ins. Co., 140 Or App 269 (1996) (burden-shifting on summary-judgment defenses under ORCP 47(C))
Read the full case

Case Details

Case Name: Sunset Presbyterian Church v. Brockamp & Jaeger, Inc.
Court Name: Court of Appeals of Oregon
Date Published: Dec 12, 2012
Citations: 295 P.3d 62; 2012 Ore. App. LEXIS 1500; 2012 WL 6194064; 254 Or. App. 24; C091601CV; A146006
Docket Number: C091601CV; A146006
Court Abbreviation: Or. Ct. App.
Log In
    Sunset Presbyterian Church v. Brockamp & Jaeger, Inc., 295 P.3d 62