History
  • No items yet
midpage
598 S.W.3d 853
Ark. Ct. App.
2020
Read the full case

Background

  • Goodwin & Goodwin (general contractor) subcontracted Summers Drilling & Blasting (SD&B) to drill/blast for a sewer relocation on a highway project at $181/linear foot with a 1,350-ft minimum.
  • SD&B blasted portions of the line, invoiced $279,283 total; Goodwin paid $185,235.40 and withheld later invoices after discovering blasted areas were not to required depth.
  • Goodwin completed the deficient work (renting equipment and hammering rock), sued SD&B for breach of contract alleging failure to blast to project-plan depths and abandonment.
  • Trial court found an enforceable contract (incorporating project plans), that SD&B failed to blast to grade and left before completion, and awarded Goodwin $132,792.26 in damages plus costs and fees.
  • SD&B appealed, arguing (1) the claim sounded in tort not contract, (2) no breach proved (depth/distance), and (3) damages calculation was unsupported. The appellate court affirmed liability but reversed and remanded on damages for recalculation.

Issues

Issue Goodwin's Argument SD&B's Argument Held
Whether the claim sounds in contract or tort Complaint alleges failure to perform per the subcontract and project specifications—so contract Claim is really for deficient performance/negligence, not breach of a specific contractual promise Contractual: complaint pleads existence of agreement, specific obligation (perform to project specs), breach, and damages; claim sounds in contract
Whether SD&B breached depth obligations Contract incorporated AHTD/City project plans specifying depths; SD&B had notice/visited site and thus was bound to blast to grade Written bid was silent on depth; no express depth term in bid so no breach Breach: parol evidence admissible to fill silence; factfinder credited evidence that SD&B failed to reach grade and thus breached
Whether SD&B breached distance/minimum obligations or merely met the 1,350-ft minimum Goodwin asserted SD&B left before completing the project and did not blast required portions SD&B said it met the 1,350-ft contractual minimum and thus did not breach as to distance Court found SD&B left before completion; SD&B did not challenge that finding on appeal, so the court’s factual finding stands
Damages calculation and offsets (including unpaid invoices) Damages measured as cost to complete minus amount owed to SD&B under the contract; Goodwin sought equipment rental, crews, and hammering hours SD&B contended court’s dollar calculation was unsupported and that unpaid invoices must offset any award Remand: appellate court agreed measure of damages was correct but reversed because the court’s computation lacked an evidentiary basis and must be recalculated (including consideration of credits for unpaid invoices)

Key Cases Cited

  • Barnes v. Wagoner, 573 S.W.3d 594 (Ark. Ct. App.) (standard of review for civil bench trials)
  • Sturgis v. Skokos, 977 S.W.2d 217 (Ark. 1998) (distinguishing tort from contract; need for specific contractual promise)
  • McQuay v. Guntharp, 963 S.W.2d 583 (Ark. 1998) (pleading governs characterization of claim)
  • Rabalaias v. Barnett, 683 S.W.2d 919 (Ark. 1985) (elements of breach of contract)
  • Keith Capps Landscaping & Excavation, Inc. v. Van Horn Constr., Inc., 448 S.W.3d 207 (Ark. Ct. App.) (proper measure of damages in construction-contract breaches)
  • MDH Builders, Inc. v. Nabholz Constr. Corp., 17 S.W.3d 97 (Ark. Ct. App.) (damages principles for construction-contract breaches)
Read the full case

Case Details

Case Name: Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc.
Court Name: Court of Appeals of Arkansas
Date Published: Mar 18, 2020
Citations: 598 S.W.3d 853; 2020 Ark. App. 194
Court Abbreviation: Ark. Ct. App.
Log In
    Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc., 598 S.W.3d 853