History
  • No items yet
midpage
STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc.
395 S.W.3d 383
| Tex. App. | 2013
Read the full case

Background

  • STR Constructors hired by Northeast Independent School District to renovate a middle school kitchen; NTI won as low bidder and became subcontractor.
  • Disputes arose over epoxy grout; STR asserted epoxy grout was required, NTI claimed bid excluded it; NTI installed epoxy grout under protest and submitted change orders STR did not pay.
  • District inspection found kitchen tile work unacceptable; STR terminated NTI for cause and NTI sued for breach and quantum meruit.
  • STR contends NTI breached first by defective work; district and architect testimony showed project fell behind schedule attributed to STR; NTI completed substantial portions before termination.
  • Contract provided pay-when-paid structure; STR paid some NTI applications but claimed lack of district payment absolved further obligation; STR also argued waiver and noncompliance with documentation.
  • Jury found STR breached first and NTI recoverable damages; court held substantial performance not required due to first breach; quantum meruit recovery affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did STR breach the contract and breach first? STR argues NTI breached first and termination was proper. NTI contends STR’s termination was improper and tantamount to breach. STR breached first; termination without cause.
Was STR required to pay NTI for work performed after termination? STR paid only some applications; district payment controls pay obligations; waived conditions. NTI’s payment claims arise under contract despite district nonpayment; STR cannot withhold all payments. Evidence supports material breach by STR and failure to pay.
Can NTI recover damages despite STR's breach first and no substantial performance finding? NTI seeks contract damages; substantial performance not required when first breach by STR. Argues against damages without substantial performance finding. NTI may recover damages; substantial performance not required here.
Whether NTI can recover in quantum meruit despite an express contract covering the work? NTI performed additional work benefitting STR; STR retained value; quantum meruit allowed. Existence of express contract bars quantum meruit for covered services. Quantum meruit recovery permissible.
Are NTI’s attorney’s fees recoverable under Chapter 38? NTI prevailed on breach and damages; fees permitted. If damages are reduced, recalculate fees on remand; otherwise contested. Fees award upheld; alternative remand not needed.

Key Cases Cited

  • Dobbins v. Redden, 785 S.W.2d 377 (Tex. 1990) (damages generally barred on breach; exceptions apply)
  • Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195 (Tex. 2004) (material breach factors for determining enforceability)
  • City of Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005) (standard for legal-sufficiency review; 'more than a scintilla')
  • Tips v. Hartland Developers, Inc., 961 S.W.2d 618 (Tex. App. San Antonio 1998) (substantial performance doctrine in contract damages)
  • Truly v. Austin, 744 S.W.2d 934 (Tex. 1988) (quantum meruit recovery when benefits conferred and unjust enrichment exists)
Read the full case

Case Details

Case Name: STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc.
Court Name: Court of Appeals of Texas
Date Published: Feb 20, 2013
Citation: 395 S.W.3d 383
Docket Number: 08-10-00210-CV
Court Abbreviation: Tex. App.