History
  • No items yet
midpage
Stock Building Supply of Florida, Inc. v. Soares Da Costa Construction Services, LLC
76 So. 3d 313
| Fla. Dist. Ct. App. | 2011
Read the full case

Background

  • Soares Da Costa contracted with Panterra Development to build a Miami mixed-use project, with Contract Management Services as a related entity owning 40% and providing the subcontract for structural shell.
  • K & A Lumber supplied rebar under the orders of Contract Management and other miscellaneous materials under Soares Da Costa’s order; notices to owner were served in September 2005.
  • The project ceased in January 2006 for funding, with liens recorded by K & A and later satisfied by the Owner in March 2006; K & A executed a Satisfaction and Waiver for the lien tied to Contract Management’s order.
  • In March 2006, a new Notice of Commencement and a new bond with Westchester Fire were recorded, and the project recommenced in April 2006 under a new framework.
  • K & A then supplied rebar again under Contract Management’s order and miscellaneous materials under Soares Da Costa’s order; K & A failed to issue a new Notice to Owner/Contractor for the rebar supplied under Contract Management after recommencement.
  • K & A filed suit on the payment bond; the trial court held K & A was not in privity with Soares Da Costa and failed to serve proper notices, barring claims against Soares Da Costa and Westchester Fire, while allowing recovery against Contract Management.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the First Notice satisfied 713.23(1)(c) or only 713.06 K & A contends the First Notice sufficed to cover all rebar materials under 713.23. Soares Da Costa/Westchester Fire argue the First Notice created a 713.06 lien and that 713.23 requirements apply only to post-bond liens; recommencement required new notices. First Notice created a 713.06 lien; 713.23 not applicable to pre-bond work.
Did K & A need a new Notice to Contractor for the rebar after recommencement Second Notice should cover materials furnished after recommencement under 713.23(1)(c). Second Notice incorrectly described the order as Soares Da Costa’s rather than Contract Management’s; failed to satisfy 713.23(1)(c). K & A failed to provide proper 713.23 notices after recommencement; authority requires a new notice for bonded work.
Effect of waiver/release of the pre-bond lien Waiver released the pre-bond lien on the portion billed to Contract Management. Waiver does not bar post-recommencement claims tied to the new notices and bond. Waiver disposed of the pre-bond lien; post-recommencement rights still governed by new notices and bond.
Whether termination and restart of the Notice of Commencement renewed lien rights requiring new notices Termination of the old commencement and restart with a new commencement should reset notice requirements for post-restart materials. Old notices and bonds may be relevant if proper notices were still in effect. Restart with a new Notice of Commencement requires new notices for post-restart materials.
Overall liability against Soares Da Costa and Westchester Fire on the payment bond K & A should recover against the bond for materials supplied. Without proper notices under 713.23, K & A’s claims on the bond fail; the court should deny recovery against the bond. Affirmed judgment denying recovery against Soares Da Costa and Westchester Fire due to improper notices.

Key Cases Cited

  • Aetna Casualty & Surety Co. v. Buck, 594 So. 2d 280 (Fla. 1992) (strict construction of construction liens and related notice requirements)
  • Design Aluminum, Inc. v. DeSanti, 521 So.2d 285 (Fla. 2d DCA 1988) (notice of commencement details and lien priority)
  • Bishop v. James A. Knowles, Inc., 292 So.2d 415 (Fla. 2d DCA 1974) (statutory intent of 713.23(1)(c) to protect owner from mispayments)
  • Professional Plastering & Stucco, Inc. v. Bridgeport-Strasberg Joint Venture, 940 So.2d 444 (Fla. 5th DCA 2006) (subcontractor must comply with notice requirements even if owner/contractor breached others)
Read the full case

Case Details

Case Name: Stock Building Supply of Florida, Inc. v. Soares Da Costa Construction Services, LLC
Court Name: District Court of Appeal of Florida
Date Published: Oct 5, 2011
Citation: 76 So. 3d 313
Docket Number: 3D10-928
Court Abbreviation: Fla. Dist. Ct. App.